DRDGOLD LIMITED - Operating update for the quarter ended 30 September 2026

Release Date: 20/10/2026 08:00
Code(s): DRD     PDF:  
Wrap Text
Operating update for the quarter ended 30 September 2026

DRDGOLD LIMITED
(Incorporated in the Republic of South Africa)
(Registration number 1895/000926/06)
ISIN: ZAE000058723
JSE & A2X share code: DRD
NYSE trading symbol: DRD
(“DRDGOLD” or the “Company”)

OPERATING UPDATE FOR THE QUARTER ENDED 30 SEPTEMBER 2026

The operating update of the Group for the quarter ended 30 September 2026 is as follows:

                                                     QUARTER        QUARTER                   QUARTER
                                                       ENDED          ENDED           %         ENDED         %
                                                      30 SEP         30 JUN      change        30 SEP    change
                                                        2026           2026                      2025
Production
Gold produced                              kg          1,307          1,283           2         1,191        10
                                           oz         42,021         41,249           2        38,291        10
Gold sold                                  kg          1,324          1,322           *         1,158        14
                                           oz         42,568         42,503           *        37,231        14
Tonnage throughput             Metric (000't)          6,170          6,345         (3)         6,481       (5)
Yield                            Metric (g/t)          0.212          0.202           5         0.184        15
Key financial results summary
Revenue                                    Rm        2,950.6        3,142.6         (6)       2,254.9        31
                                         US$m          181.2          190.8         (5)         127.9        42
Cash operating cost                        Rm      (1,300.7)      (1,226.7)           6     (1,157.4)        12
                                         US$m         (79.9)         (74.5)           7        (65.6)        22
Operating profit #                         Rm        1,627.4        1,885.1        (14)       1,148.9        42
                                         US$m          100.0          114.5        (13)          65.2        53
Price and costs
Average gold price received          R per kg      2,223,112      2,364,070         (6)     1,943,398        14
                                   US$ per oz          4,247          4,465         (5)         3,429        24
Cash operating costs                  R per t            211            193           9           179        18
                                    US$ per t             13             12           8            10        30
Cash operating costs                 R per kg        999,396        951,162           5       955,086         5
                                   US$ per oz          1,909          1,796           6         1,685        13
All-in sustaining costs **           R per kg      1,135,423      1,058,000           7     1,066,287         6
                                   US$ per oz          2,169          1,998           9         1,881        15
All-in costs **                      R per kg      1,562,538      1,951,197        (20)     1,745,213      (10)
                                   US$ per oz          2,985          3,685        (19)         3,079       (3)
Capital expenditure
Sustaining                                 Rm          119.7           98.1          22          51.5       132
                                         US$m            7.4            6.0          23           2.9       155

Growth/non-sustaining                      Rm          555.7        1,160.0        (52)         781.1      (29)
                                         US$m           34.1           70.4        (52)          44.3      (23)
Average R/US$ exchange                                 16.28          16.47         (1)         17.63       (8)
rate

  Rounding of figures may result in computational discrepancies.
  * Change less than 1%
  # Operating profit is net of the movement in gold in process. Operating profit may not be comparable to similarly titled
  measures of other companies and is not a measure of performance under International Financial Reporting Standards
  (IFRS) and should be considered in addition to, and not as a substitute for, other measures of financial performance and
  liquidity.
  ** All-in sustaining costs and all-in costs are based on the guidance note on non-GAAP Metrics issued by the World
  Gold Council in November 2018.

  Unless otherwise indicated, comparisons in this operating update are against the quarter ended
  30 September 2025. Information for the quarter ended 30 June 2026 is presented for supplementary
  comparative purposes.

1. Revenue

   Revenue for the quarter ended 30 September 2026 increased by 31% to R2,950.6 million from
   R2,254.9 million for the quarter ended 30 September 2025, reflecting both a 14% increase in gold sold to
   1,324kg and a 14% increase in the average Rand gold price received, to R2,223,112/kg. Gold production
   increased by 10% to 1,307kg, supported by a 15% improvement in yield to 0.212g/t, despite tonnage
   throughput being 5% lower.

2. Cash operating costs

   Group cash operating costs increased by 12% to R1,300.7 million from R1,157.4 million for the quarter ended
   30 September 2025, mainly due to higher reagent and diesel costs, as well as the purchase and processing
   of higher-grade third-party material. The increase in diesel costs was attributable to the ongoing conflict in the
   Middle East. Electricity costs were also higher following the tariff adjustment and the impact of two winter
   months, partially offset by lower consumption of Eskom-sourced electricity due to the contribution of Ergo
   Mining Proprietary Limited's (“Ergo”) solar plant and battery energy storage system (BESS). Cash operating
   costs at Far West Gold Recoveries Proprietary Limited (“FWGR”) also increased, mainly due to higher labour
   and other costs associated with the commissioning of the elution plant and smelthouse, as well as preparations
   for the commissioning of the DP2 Plant expansion.

   Cash operating costs per kilogram increased by 5% from R955,086/kg to R999,396/kg, while cash operating
   costs per tonne increased by 18% from R179/t to R211/t. The increase in cash operating costs per tonne was
   further impacted by tonnage throughput being 5% lower than in the quarter ended 30 September 2025.

   Compared with the quarter ended 30 June 2026, Group cash operating costs increased by 6% to
   R1,300.7 million, primarily due to wage increases effective from 1 July 2026 at both operations, as well as
   higher contractor and machine hire costs, attributable to the increase in the diesel price. Cash operating costs
   per kilogram consequently increased by 5% to R999,396/kg, while cash operating costs per tonne increased
   by 9% to R211/t, also reflecting the impact of the 3% decrease in tonnage throughput to 6.2Mt.

3. Capital expenditure

   Growth capital expenditure decreased by 29% to R555.7 million from R781.1 million for the quarter ended
   30 September 2025, reflecting the progression of certain Vision 2028 projects towards completion and the
   resulting reduction in capital expenditure.

   The majority of capital expenditure incurred at FWGR related to the construction of the Regional Tailings
   Storage Facility (“RTSF”), which was 77% complete as at 30 September 2026, with construction work required
   for beneficial occupation being 99% complete. Beneficial occupation remains subject to obtaining the
   necessary regulatory approvals and favourable weather conditions. The DP2 Plant expansion was
   substantially completed by 30 September 2026, with commissioning scheduled for October 2026. Construction
   of the Libanon reclamation station commenced in September 2026 following receipt of the necessary
   regulatory approvals. Capital expenditure at Ergo decreased following the completion and commissioning of
   the Daggafontein Tailings Storage Facility in July 2026, while the regulatory approval process at Withok
   remains ongoing.

   All-in sustaining costs increased by 6% to R1,135,423/kg from R1,066,287/kg for the quarter ended
   30 September 2025, primarily due to the increase in cash operating costs and higher sustaining capital
   expenditure.

   All-in costs decreased by 10% to R1,562,538/kg from R1,745,213/kg for the quarter ended
   30 September 2025, mainly reflecting lower growth capital expenditure during the quarter ended
   30 September 2026.

4. Liquidity
  
   Cash and cash equivalents decreased by R318.9 million, from R2,770.0 million as at 30 June 2026 to
   R2,451.1 million as at 30 September 2026, following payment of the final cash dividend of R1,042.5 million
   for the year ended 30 June 2026 (“FY2026”) on 14 September 2026. Free cash inflow, comprising operating
   cash flow less investing cash flow, amounted to R725.8 million for the quarter, compared to R90.6 million for
   the quarter ended 30 September 2025, mainly reflecting increased profitability and lower capital expenditure
   as certain Phase 2 projects at FWGR progressed towards completion.

   The Company’s cash position allows it to continue funding its extended capital expenditure programme without
   incurring debt, and, if current conditions prevail and barring any unforeseen events, the Company is favourably
   positioned to consider an interim dividend in February 2027.

   The Group remained debt free as at 30 September 2026 (30 June 2026: Rnil). To support liquidity and fund
   its significant capital expansion programme, the Group has access to a R1 billion revolving credit facility with
   a R500 million accordion option and a R500 million general bank facility with Nedbank Limited (acting through
   its Corporate and Investment Banking division), which may be utilised if required.

5. Operational performance outlook

   The Company’s FY2026 results, published on 19 August 2026, included production guidance for the year
   ending 30 June 2027 (“FY2027”) of between 160,000 ounces and 170,000 ounces of gold, at cash operating
   costs of approximately R1,099,000/kg and all-in sustaining costs of R1,230,000/kg. The Company remains on
   track to achieve its FY2027 production guidance while maintaining its operating cost guidance.

   The information contained in this announcement does not constitute an earnings forecast. The financial
   information provided is the responsibility of the directors of DRDGOLD, and such information has not been
   reviewed or reported on by the Company’s auditors.


  Johannesburg
  20 October 2026

  Sponsor
  One Capital
Date: 20/10/2026 08:00:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,