THARISA PLC - Production report for the quarter ended 30 June 2019

Release Date: 09/07/2019 07:05
Code(s): THA     PDF:  
Wrap Text
Production report for the quarter ended 30 June 2019

Tharisa plc
(Incorporated in the Republic of Cyprus with limited liability)
(Registration number HE223412)
JSE share code: THA
LSE share code: THS
A2X share code: THA
ISIN: CY0103562118
('Tharisa' or the 'Company')



Production report for the quarter ended 30 June 2019
Overall production improvement sets up a strong finish



Salient features for the quarter ended 30 June 2019
- Quarterly improvement in reef tonnes mined and milled up 2.0% and 5.4% respectively
- Stripping ratio at 8.3 (m3:m3) with pit redesign substantially completed
- Platinum Group Metals ('PGM') recovery at 82.1% with PGM production of 34.1 koz
- Chrome recovery at 65.5% with chrome production up 8.2% to 334.0 kt
- Investment in fleet capacity demonstrating volume capability and availability to meet future targets
- Karo Mining has completed the first phase of its drilling campaign on time and within budget

Commenting on the production results, Tharisa CEO Phoevos Pouroulis, said:



“The improvement in key production metrics sets the mine up for a strong finish to the 2019 financial year
and good momentum in to 2020. The pit redesign, which has been largely completed, and our ability to
move tonnage ensures that we develop a sustainable and viable large-scale open pit operation, capable
of producing volume output for the years ahead. The changes we made in the past quarters with regards
to mining fleet improvement and pit optimisations will benefit us into the future.”



Safety
Safety is one of Tharisa's core values and the Company continues to strive for zero harm at its operations.
An LTIFR of 0.22 per 200 000-man hours worked was recorded at the end of the quarter.




                                                                                                         
Production update
The production update for the quarter ended 30 June 2019 is as follows:

                                                             Quarter           Quarter         Quarter on            Quarter               Nine              Nine
                                                              ended             ended            quarter              ended             months            months
                                                              30 Jun           31 Mar          movement               30 Jun             ended             ended
                                                               2019              2019                  %               2018              30 Jun            30 Jun
                                                                                                                                          2019              2018
    Reef mined                          kt                     1 155.4            1 132.9                  2.0          1 244.1            3 378.9           3 695.3
    Stripping ratio                     m3: m3                     8.3                7.4              12.2                 8.0                7.5                 8.1
                                                                                         *                                                        *
    Reef milled                         kt                     1 207.3           1 145.0                   5.4          1 291.2           3 544.8            3 888.6
    PGM flotation feed                  kt                       889.1             850.3                  4.6             929.7           2 640.7           2 825.3
    PGM rougher feed grade              g/t                       1.45              1.46                (0.7)              1.54              1.48              1.53
    PGM recovery                        %                         82.1              85.5                (4.0)              85.6              81.2              84.0
    6E PGMs produced                    koz                       34.1              34.0                 0.3               39.5            101.7              116.5
    Average PGM contained               US$/oz                   1 064             1 048                  1.5               947             1 033                   922
    metal basket price
    Average PGM contained               ZAR/oz                 15 297             14 694                  4.1           11 947             14 690            11 721
    metal basket price
    Cr2O3 ROM grade                     %                         17.8              18.0                (1.1)              18.2              18.1              18.1
    Chrome recovery                     %                         65.5              62.9                 4.1               67.8              62.4              66.5
    Chrome yield                        %                         27.7              27.0                 2.6               29.1              26.7              28.5
    Chrome concentrates                 kt                       334.0             308.7                  8.2             376.3             948.1           1 108.8
    produced (excluding
    third party)
      Metallurgical grade               Kt                       259.4             232.6                11.5              281.1             725.5              840.0
      Specialty grades                  kt                        74.6              76.1                (2.0)              95.2            222.6              268.8
    Third party chrome                  kt                        59.1              60.3                (2.0)              59.6            171.6              165.8
    production
    Metallurgical grade                 US$/t CIF                  174               162                 7.4               193                166                  193
    chrome concentrate                  China
    contract price
    Metallurgical grade                 ZAR/t CIF                2 525             2 268                11.3              2 477             2 361              2 449
    chrome concentrate                  China
    contract price
    Average exchange rate               ZAR:US$                   14.4              14.2                 1.4               12.6              14.2              12.7
*  includes the processing of 23.1 kt and 99.0 kt of commissioning tails through the processing plants for the quarter ended 31 March 2019 and nine months ended
30 June 2019 respectively




                                                                                                                                                              
Mining
Reef tonnes mined continued to improve at the Tharisa Mine with an increase of 2.0% as compared to
the previous quarter, to 1 155.4 kt mined. Additional material available to the mine resulted in total reef
tonnes milled increasing by 5.4% to 1 207.3 kt in the quarter, bringing total tonnes mined to 3 378.9 kt
and total tonnes milled to 3 544.8 kt for the year to date. The mine recorded a pleasing 12.2%
improvement in stripping ratio, up from 7.4 m3:m3 in the March quarter to 8.3 m3:m3 in the June quarter
under review. As part of the ongoing pit redesign, the mine moved an additional 470 000 Mm3 of in-pit
material during the quarter to optimise the pit. When included in the stripping ratio calculation, the total
waste volume moved by the mining fleet in the second quarter achieved a ratio of 9.7 m3:m3 as compared
to 9.4 m3:m3 in Q2. The Tharisa Mine is continuing to create flexibility which will result in improvements
to the reef mix thereby improving plant feed grades.

Processing
PGM production increased by 0.3% to 34.1 koz (6E basis) over the previous quarter and recoveries were
maintained at 82.1%. The slight decrease compared to the previous quarter being due to the MG reef
horizon mix into the plant differing as a result of the planned mining.

Chrome concentrate production increased by 8.2% to 334.0 kt, with recoveries improving by 4.1% to
65.5% compared to the previous quarter. Of the total chrome concentrates produced, 259.4 kt were
metallurgical grade, an improvement of 11.2% versus the previous quarter and 74.6 kt were speciality
grade, versus 76.1 kt in the previous quarter,

The chrome production for the quarter from the Lonmin K3 chrome plant was 59.1 kt compared to 60.3 kt
in the previous quarter.

Market update
The average PGM contained metal basket price for the third quarter was US$1 064/oz (ZAR15 297/oz), an
increase of 1.5% in US$ terms from the last quarter and 4.1% in ZAR terms.

The average chrome price received, while slightly up in the June quarter at US$174/t compared to
US$162/t in the March quarter, is showing a downward trend on a nine month basis at US$166/t, with
current spot around US$140/t. This compared to an average of US$193/t for the comparable nine month
period in financial year 2018.

New Business
Karo Mining Holdings Limited has completed the first phase of its drilling campaign on time and within
budget, measuring a total of 30 km of diamond core drilling over 206 holes. Preliminary resource data will
be available in November 2019.

Tharisa has completed the value engineering and front-end engineering work undertaken on the data
used in the Definitive Feasibility Study for the Vulcan Plant. This, together with input from engineering
and cost consultants will be presented to the New Business Development Committee of the Tharisa Board
for approval.

Outlook
Tharisa’s FY2019 production guidance remains unchanged.

The above information has not been reported on or reviewed by Tharisa's auditors.


Paphos, Cyprus
09 July 2019


JSE Sponsor
Investec Bank Limited

Investor relations contacts:
Daniel Thöle / Ilja Graulich
+27 61 400 2939 / +27 83 604 0820

Financial PR contacts:
Bobby Morse / Augustine Chipungu
+44 020 7466 5000
tharisa@buchanan.uk.com

Broker contacts:
Peel Hunt LLP (UK Joint Broker)
Ross Allister / James Bavister / David McKeown
+44 207 7418 8900

BMO Capital Markets Limited (UK Joint Broker)
Jeffrey Couch / Thomas Rider
+44 020 7236 1010

Berenberg (UK Joint Broker)
Matthew Armitt / Detlir Elezi
+44 20 3207 7800

Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)
Shabbir Norath
+27 11 295 6575




                                                                                                   

Date: 09/07/2019 07:05:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story