Eastern Platinum Limited publishes CEO letter to shareholders

EASTERN PLATINUM LIMITED
(Incorporated in Canada)
(Canadian Registration number BC0722783)
(South African Registration number 2007/006318/10)
Share Code TSX: ELR ISIN: CA2768555096
Share Code JSE: EPS ISIN: CA2768555096
("Eastplats" or the "Company")

Trading Symbol: ELR (TSX); EPS (JSE)

                                                NEWS RELEASE

             EASTERN PLATINUM LIMITED PUBLISHES CEO LETTER TO SHAREHOLDERS

VANCOUVER, British Columbia, January 23, 2024 — Eastern Platinum Limited (TSX: ELR, JSE: EPS)
("Eastplats" or the "Company"), a developer and producer of chrome and PGMs assets located in the Bushveld
Complex in the Republic of South Africa, today issues the following letter to shareholders from Eastplats CEO
Wanjin Yang.

Dear Eastplats Stakeholders, Investors, and Friends:

Eastplats made progress on key corporate and operational initiatives in 2023, continuing to operate and optimize
the tailings storage facility ("TSF") retreatment project at the Crocodile River Mine ("CRM"), raising capital to
restart the Zandfontein underground mine (one of the three mines at CRM), initiating the restart of the Zandfontein
underground project and successfully completing its special committee investigation into whistleblower
allegations initiated during the year. These milestones came to pass amidst evolving financial and commodity
markets.

On-Going Chrome Market Support

The Company continued to operate and optimize the TSF retreatment project at the CRM, producing both chrome
concentrates and platinum group metals ("PGM") ounces during the year. This retreatment project is the only
large-scale magnetic separation application in South Africa, returning an annual average of 38.6% chrome
concentrate grades since beginning operation in 2019. Though PGM ounces are expected to account for 65% of
Eastplats revenue by 2025-2026, chrome production made up most of the production mix in 2023. PGM
production is expected to account for roughly 80% of 2024 revenue as the soft restart of the underground mining
will target high grade PGM ounces and metallurgical grade chrome byproducts within the Zandfontein section.

The increase in revenue derived from chromes sales during the year was primarily due to higher tonnages sold
to third parties at market prices. Low chrome supply at ports (in China) as well as fluctuations in Chinese yuan
exchanges rates against the US dollar is also believed to have supported robust chrome pricing in 2023. i

Eastplats' TSF retreatment project is expected to result in record annual revenues for 2023 of US$100 million
and will continue operating into late 2024.

Volatility in PGM Market

The volatility in the PGM market has offset the buoyed performance from chrome concentrate volumes and
prices. By December 2023, PGM prices, on average, fell approximately 40% year-over-year, with PGM price
volatility impacting operations of PGM producers, decreasing margins, resulting in operational restructuring (and
job cuts) and widening of the global supply deficit for the basket of precious and industrial metals. However,
despite the fall in PGM prices, it is important to remember that "the PGM basket price has not traded materially
below the 70th percentile of the cost curve on an annual basis."ii

Eastplats has not been impacted from these larger PGM price effects in 2023 for a number of reasons. First, a
large part of operational efforts has focused on the Company's retreatment project, the majority of which produces
chrome concentrate. Second, Eastplats' soft restart of the Zandfontein underground section at the CRM, that
focuses on PGM mining and eventually PGM production, will be executed in phases. The initial "soft restart"
phase, which began in Q4 2023, involves blasting and stockpiling of ore to begin processing in Q1 2024. At a
normalized run rate, this soft restart phase is expected to produce 40,000 tons of PGM ore a month by the end
of 2024. The next phase will see operations ramp up to 70,000 tons of PGM ore a month at the end of 2025,
operating at a steady state rate in between 70,000 and 80,000 tons monthly in 2026.

Last, over the last couple of years, the Company has been implementing operational efficiency initiatives
investing in support, development and infrastructure design to increase operational flexibility, reduce logistics and
material handling costs.

Corporate and Financing Activities

At the corporate level, the management team has been active strengthening the balance sheet and resolving site
issues. In May 2023, Eastplats completed a $7 million rights offering to invest in the Zandfontein underground
and portfolio growth opportunities. The pipeline finance facility with Investec Bank Limited continues to be utilized,
strongly supporting the CRM TSF retreatment project and as well the Zandfontein underground mine business.

More recently, the Company announced the completion of a special committee (the "Committee") investigation.
The Committee reviewed and analyzed unproven whistleblower allegations, including allegations of undisclosed
related party transactions pertaining to the sale of chrome concentrate at discounted prices. With assistance
from independent counsel engaged and a third-party e-discovery specialist to assist with the investigation, the
Committee found allegations advanced by the whistleblowers to be unsubstantiated, and the Committee did not
find evidence to establish that the Company entered into any related party transaction pertaining to the sale of
chrome concentrate and further concluded that the prices of the contracts in respect of the sale of chrome
concentrate described in the allegations were within a reasonable range of market price, particularly in the
challenging circumstances Eastplats faced in the latter half of 2022 and taking into account delivery terms and
the grade of chrome concentrate.

The successful completion of these corporate activities has established a supportive base from which Eastplats
plans to execute its 2024 growth plans.

2024 Outlook

The Company's plans for 2024 and beyond are focused on its high-quality chrome and PGM portfolio. Over the
next 12 months, Eastplats plans to:

    •   Ramp-up the Zandfontein underground operations – process up to 235,000 tons of underground run-of-
        mine ("ROM") production per month.

    •   Complete the optimization of the chrome recovery plant for the retreatment project by focusing on
        improving the quality and quantity of chrome concentrate to improve the production yield.

    •   Confirm capital plans to support the full re-opening of Zandfontein underground operations at the CRM
        from external or internal sources.

    •   Complete the second phase of TSF capital works program and confirm the TSF dam space for new ROM
        tailings.

    •   Optimize Main Plant Circuit B for underground ROM operations.

    •   Renovate Circuit D to high energy flotation cells for better ROM processing recovery rate to 82% or
        higher.

    •   Advance the Mareesburg and Spitzkop project environmental work to complete the Environmental
        Impact Assessment and other environmental studies and amendments.

    •   Resolve the outstanding receivables from Union Goal Offshore Solution Limited.
    •   Continue prospecting and economic assessment work related to the Zandfontein, Crocette, and
        Kareespruit sections of the CRM and Kennedy's Vale and Spitzkop mines at the eastern limb of the
        Bushveld Complex.

About Eastern Platinum Limited

Eastplats owns directly and indirectly a number of platinum group metal ("PGM") and chrome assets in the
Republic of South Africa. All of the Company's properties are situated on the western and eastern limb (Crocodile
River Mine) and eastern limb (Kennedy's Vale/Spitzkop, Mareesburg) of the Bushveld Complex, the geological
environment that hosts approximately 80% of the world's PGM-bearing ore.

Operations at the Crocodile River Mine currently include re-mining and processing its tailings resource to produce
PGM and chrome concentrates from the Barplats Zandfontein tailings dam.

For further information, please contact:
 EASTERN PLATINUM LIMITED
 Wylie Hui, Chief Financial Officer & Corporate Secretary
 Phone : (604) 800-8200
 Email: whui@eastplats.com

Cautionary Statement Regarding Forward-Looking Information

This press release contains "forward-looking statements" or "forward-looking information" (collectively referred to
herein as "forward-looking statements") within the meaning of applicable securities legislation. Such forward-
looking statements include, without limitation, forecasts, estimates, expectations and objectives for future
operations that are subject to a number of assumptions, risks and uncertainties, many of which are beyond the
control of the Company. Forward-looking statements are statements that are not historical facts and are
generally, but not always, identified by the words "will", "plan", "intends", "may", "will", "could", "expects",
"anticipates" and similar expressions. Further disclosure of the risks and uncertainties facing the Company and
other forward-looking statements are discussed in the Company's Annual Information Form and Management's
Discussion and Analysis which are available under the Company's profile on www.sedarplus.ca.

In particular, this press release contains forward-looking statements pertaining to the expected revenue and
production mix of respective PGM ounces and chrome tonnages; expected annual revenues for 2023; potential
execution of the Zandfontein underground restart plan and ability to achieve and communicate key project
milestones and production tonnage rates by the end of 2024, 2025, and during 2026; the successful completion
of corporate activities to support the Company's plans to execute its 2024 growth plans; the Company's plans
and outlook for 2024; and forecasts, estimates, expectations, and objectives for future operations that are subject
to a number of assumptions, risks and uncertainties, many of which are beyond the control of the Company.
These forward-looking statements are based on assumptions made by and information currently available to the
Company. Although management considers these assumptions to be reasonable based on information currently
available to it, they may prove to be incorrect. By their very nature, forward-looking statements involve inherent
risks and uncertainties and readers are cautioned not to place undue reliance on these statements as a number
of factors could cause actual results to differ materially from the beliefs, plans, objectives, expectations, estimates
and intentions expressed in such forward-looking statements. These factors include, but are not limited to,
commodity prices, economic conditions, currency fluctuations, competition and regulations, legal proceedings
and risks related to operations in foreign countries.

The forward-looking statements in this press release are made as of the date they are given and, except as
required by applicable securities laws, the Company disclaims any intention or obligation to publicly update or
revise any forward-looking statements, whether as a result of new information, future events or otherwise.

No stock exchange, securities commission or other regulatory authority has approved or disapproved
the information contained herein.

The Company has a primary listing on the Toronto Stock Exchange and a secondary listing on the JSE Limited.

23 January 2024

JSE Sponsor
PSG Capital

i Fastmarkets: Dried and bagged chromite prices edge up; rising costs pressure producers.
https://www.fastmarkets.com/insights/chromite-prices-rising-costs-producers/
ii UBS Equity Research: South African PGM Sector: Scenario analysis under various downturns (20 October 2023)

Date: 23-01-2024 03:45:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story