2nd Quarter Production Report: 3 months ended 31 March 2015
Tharisa plc
(Incorporated in the Republic of Cyprus with limited liability)
(Registration number HE223412)
JSE share code: THA
ISIN: CY0103562118
('Tharisa')
Second quarter production report: 3 months ended 31 March 2015
Safety
Safety remains our utmost priority and we strive for zero harm at our operations. The Lost Time
Injury Frequency Rate at the Tharisa Mine for the twelve month period to 31 March 2015 (per
200 000 man hours) was 0.07.
New Record PGM production in March 2015
The Tharisa Mine produced 12 874 6E contained PGM ounces during March 2015, the previous
record was 10 593 6E contained PGM ounces achieved during January 2015.
Production update
The table below details the production summary for the Tharisa Mine:
Quarter Quarter Half year Half year Financial year
ended 31 Mar ended 31 Dec ended 31 Mar ended 31 Mar ended 30 Sep
2015 2014 * 2015 2014 2014
Reef mined kt 1 042.1 905.9 1 948.0 1 957.8 3 908.5
Stripping ratio m³ waste/m³
reef 9.8 10.1 10.0 9.2 10.6
Reef milled kt 1 167.1 1 031.6 2 198.7 1 919.0 3 913.1
PGM rougher feed grade g/t 1.65 1.67 1.65 1.68 1.63
6E PGMs produced koz 33.0 24.4 57.4 38.4 78.2
PGM recovery % 68.6 56.9 63.1 47.7 48.8
Average PGM contained
metal basket price US$/oz 935 956 945 1 079 1 103
Cr2O3 RoM grade % 18.8 18.5 18.7 20.1 19.4
Chrome concentrates
produced kt 305.5 257.8 563.3 569.4 1 085.2
42% metallurgical
grade kt 283.6 232.3 515.9 500.0 937.0
Chemical and
foundry grades kt 21.9 25.5 47.4 69.4 148.2
Chrome yield % 26.2 25.0 25.6 29.7 27.7
42% metallurgical grade
chrome concentrate US$/t CIF
contract price China 155 159 156 151 158
Average exchange rate ZAR:US$ 11.7 11.1 11.5 10.5 10.6
*Loss of plant production time of 12% for the quarter, following the tragic fatality on 5 November 2014 and the
Section 54
Commenting on the production, Phoevos Pouroulis, Tharisa CEO said:
“We had an excellent quarter, producing 33 koz of PGMs and 305 kt of chrome concentrates with
markedly improved mining following the changes made in Q1 and continued progress in optimising
our processing to improve PGM recoveries and deliver higher margin chrome concentrates. The
improvement in mining has enabled the Genesis plant to process mined ore as well as re-processing
commissioning tails. The processing of 100% mined ore through the Genesis plant is now planned
for Q3 2015. The Voyager plant continues to operate on 100% mined ore.
Both process and mechanical reliability optimisation projects have been successful during the
period. Given continued depressed commodity prices, the focus has been on maximising PGM
recoveries and higher value add chemical and foundry grade chrome concentrates. It is pleasing to
report that the PGM recoveries surpassed expectations at the Voyager plant with a recovery of
78.8% being achieved in March 2015. The combined PGM production in March 2015 equates to
12 874 contained PGM ounces on a 6E basis which demonstrates that we are on track to achieve our steady
state production.”
Pouroulis added. “The Tharisa team has worked hard to prove our large-scale, long-life, open pit
PGM and chrome co-product mine to be a viable and attractive business. I thank all those who have
contributed during this period and look forward to reporting on even better results in the future.”
The above information has not been reported on or reviewed by Tharisa’s auditors.
The financial results for the six months ended 31 March 2015 are expected to be released on or
about 17 June 2015.
Paphos, Cyprus
14 April 2015
Sponsor
Investec Bank Limited
Date: 14/04/2015 11:36:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.