Fourth quarter and full year production report for the year ended 30 September 2019
Tharisa plc
(Incorporated in the Republic of Cyprus with limited liability)
(Registration number HE223412)
JSE share code: THA
LSE share code: THS
A2X share code: THA
ISIN: CY0103562118
('Tharisa' or the 'Company')
Fourth quarter and full year production report for the year ended 30 September 2019
Strong quarterly performance demonstrates ability to deliver on Vision 2020
Salient features for the quarter ended 30 September 2019
- Quarterly operational improvement with reef tonnes mined up 8.0% to 1 248.2 kt and tonnes milled
up 6.9% to 1 291.2 kt
- Platinum Group Metals ('PGMs') recovery was 84.7% with production up 11.4% to 38.0 koz (Q3 2019:
34.1 koz)
- Chrome recovery at 61.0% (Q3 FY 2019: 65.5%) with production up 2.4% to 341.9 kt (Q3 334.0 kt)
- Third party chrome concentrate production at 69.4 kt, up 17.4% from Q3 2019
- Stripping ratio quarter on quarter has increased by 24.1% to 10.3 m3:m3 (Q3 2019: 8.3 m3:m3)
- Continued investment in fleet capacity and upgrades with second Caterpillar 6050 to be
commissioned in Q1 of financial year 2020
Salient features for the year ended 30 September 2019
- Reef tonnes mined and milled at 4 627.1 kt and 4 836.0 kt respectively
- PGMs recovery at 82.1% with production of 139.7 koz
- Chrome recovery at 62.0% with chrome production at 1 290.0 kt
- Third party chrome concentrate production of 241.1 kt
- PGM price of US$1 081/oz, an increase of 17.1% from 2018
- Chrome price received down 12.9% to US$162/t
- Pit layout substantially complete with pit design optimisation now underway
Commenting on the production results, Tharisa CEO Phoevos Pouroulis, said:
“In the year under review Tharisa significantly reset its mining operations, with a revised pit layout, an
improvement in waste stripping, and the debottlenecking of the production plants. Though this translated
into lower production than last year’s record performance, the significant work done provides Tharisa with
a clear path to delivering on our Vision 2020 strategy. The key remaining investment to achieve our
production goal, the Vulcan plant, is under construction and remains firmly on track for commissioning in
calendar Q4 2020. We have focussed our energy in the right places and have invested in both our workforce
and machinery, which will ensure we have the right tools to achieve our targets. Extremely pleasing is our
Zimbabwean development pipeline, especially with Karo Platinum completing phase one of the exploration
programme with positive results apparent at this early stage.”
Safety
Safety is one of Tharisa's core values and the Company continues to strive for zero harm at its operations.
An LTIFR of 0.27 per 200 000 man hours worked was recorded at the end of the quarter.
Production update
The production update for the quarter and year ended 30 September 2019 is as follows:
Quarter Quarter Quarter on Quarter Year Year
ended ended quarter ended ended ended
30 Sep 30 Jun movement 30 Sep 30 Sep 30 Sep
2019 2019 % 2018 2019 2018
Reef mined kt 1 248.2 1 155.4 8.0 1 179.7 4 627.1 4 875.0
Stripping ratio m3: m3 10.3 8.3 24.1 7.2 8.3 7.9
Reef milled kt 1 291.2 1 207.3 6.9 1 216.7 4 836.0* 5 105.3
PGM flotation feed kt 965.2 889.1 8.6 892.8 3 605.9 3 718.1
PGM rougher feed grade g/t 1.44 1.45 (0.7) 1.48 1.47 1.51
PGM recovery % 84.7 82.1 3.2 84.1 82.1 84.1
6E PGMs produced koz 38.0 34.1 11.4 35.7 139.7 152.2
Average PGM contained US$/oz 1 211 1 064 13.8 928 1 081 923
metal basket price
Average PGM contained ZAR/oz 17 792 15 297 16.3 13 067 15 531 12 038
metal basket price
Cr2O3 ROM grade % 18.3 17.8 2.8 18.3 18.1 18.2
Chrome recovery % 61.0 65.5 (6.9) 64.5 62.0 66.0
Chrome yield % 26.5 27.7 (4.3) 27.9 26.7 28.4
Chrome concentrates kt 341.9 334.0 2.4 339.2 1 290.0 1 448.0
produced (excluding
third party)
Metallurgical grade kt 252.4 259.4 (2.7) 240.3 977.9 1 080.3
Specialty grades kt 89.5 74.6 20.0 98.9 312.1 367.7
Third party chrome kt 69.4 59.1 17.4 56.0 241.1 221.8
production
Metallurgical grade US$/t CIF 148 174 (14.9) 164 162 186
chrome concentrate China
contract price
Metallurgical grade ZAR/t CIF 2 203 2 525 (12.8) 2 313 2 525 2 415
chrome concentrate China
contract price
Average exchange rate ZAR:US$ 14.7 14.4 2.1 14.1 14.4 13.1
* includes the processing of 99.0 kt of commissioning tails through the processing plants for the year ended 30 September 2019
Mining
Reef tonnes mined continued the trend of steady improvement at the Tharisa Mine with an increase of
8.0% as compared to the previous quarter, to 1 248.2 kt (Q3 2019: 1 155.4 kt), bringing total tonnes mined
for the 2019 year to 4 627.1 kt, slightly down from the previous year’s 4 875.0 kt. Reef tonnes milled saw
an improvement of 6.9% for the quarter to 1 291.2 kt (Q3 2019: 1 207.3 kt) resulting in total reef milled
of 4 836.0 kt (2018: 5 105.3 kt) for the year under review.
The revised pit layout has been largely completed and the previously mined in-pit material has been
removed. The stripping ratio quarter on quarter has increased by 24.1% to 10.3 m3:m3 (Q3 2019: 8.3
m3:m3) resulting in an annualised stripping ratio of 8.3 m3:m3.
A second Caterpillar 6050 face shovel is scheduled to be operational before the end of December 2019,
with various other capital items ordered or delivered, resulting in further improvements in the overall
fleet age profile, capacity and efficiency.
Processing
PGM production increased by 11.4% to 38.0 koz (6E basis) (Q3 2019: 34.1 koz) compared to the previous
quarter with recoveries increasing by 3.2% to 84.7% (Q3 2019: 82.1%). Annualised PGM recoveries were
steady at 82.1% (2018: 84.1%). PGM grade for the quarter was maintained at 1.44 g/t (Q3 2019: 1.45 g/t)
resulting in a rougher feed grade of 1.47 g/t for the year.
Chrome concentrate production quarter on quarter increased by 2.4% to 341.9 kt (Q3 2019: 334.0 kt)
delivering overall production of 1 290.0 kt (2018: 1 448.0 kt) for the year. Chrome recoveries were down
quarter on quarter at 61.0% (Q3 2019: 65.5%) with recoveries for the year at 62.0% (2018: 66.0%) as a
result of instability in the average feed grade into the plant which is being rectified as the mine increases
its run of mine stockpile ahead of the crushing circuit. Quarterly grade improved by 2.8% from 17.8% to
18.3%, giving an annualised CR203 ROM grade of 18.1% compared to 18.2% in the previous year. Of the
total chrome concentrate produced for the quarter 252.2 kt was metallurgical grade, while specialty grade
production increased by 20.0% to 89.5 kt.
The chrome production for the quarter from the K3 chrome plant was 69.3 kt (Q3 2019: 59.1 kt) with total
K3 production for the year being 241.1 kt (2018: 221.8 kt).
Market update
The average PGM contained metal basket price for the quarter was US$1 211/oz (ZAR17 792/oz), an
increase of 13.8% in US$ terms and 16.3% in ZAR terms, while year on year average PGM prices received
were up by 17.1% to US$ 1 081/oz (2018: US$ 923/oz) and 29.0% up to ZAR 15 531/oz (2018: ZAR
12 038 /oz).
The average chrome price received for the quarter was down 14.9% at US$148/t (Q3 2019: US$174/t)
with an annualised 12.9% decrease in price received to US$162/t (2018: US$186/t). Disappointingly, spot
prices have thus far failed to rise above US$160/t.
Outlook
Construction on the Vulcan Plant has commenced, with civil works due to be completed before Christmas.
Orders for long lead items have been placed and the construction schedule is on track for cold
commissioning in calendar year 2020.
Tharisa is on track to achieve its Vision 2020 targets of 2 Mt chrome concentrate and 200 koz of PGMs on
an annualised basis by the end of calendar year 2020.
Tharisa’s FY2020 production guidance is 155 koz to 165 koz PGMs (6E basis) and 1.45 Mt to 1.55 Mt of
chrome concentrates.
The above information has not been reported on or reviewed by Tharisa's auditors.
Paphos, Cyprus
09 October 2019
JSE Sponsor
Investec Bank Limited
Investor relations contacts:
Ilja Graulich (Head of Investor Relations and Communications)
+27 11 996 3500
+27 83 604 0820
igraulich@tharisa.com
Daniel Thöle (Investor Relations and Communications)
+27 11 996 3500
Financial PR contacts:
Bobby Morse / Augustine Chipungu
+44 020 7466 5000
tharisa@buchanan.uk.com
Broker contacts:
Peel Hunt LLP (UK Joint Broker)
Ross Allister / James Bavister / David McKeown
+44 207 7418 8900
BMO Capital Markets Limited (UK Joint Broker)
Jeffrey Couch / Thomas Rider
+44 020 7236 1010
Berenberg (UK Joint Broker)
Matthew Armitt / Detlir Elezi
+44 20 3207 7800
Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)
Shabbir Norath
+27 11 295 6575
Date: 09/10/2019 07:10:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.