First quarter production report for the period ended 31 December 2016
Tharisa plc
(Incorporated in the Republic of Cyprus with limited liability)
(Registration number HE223412)
JSE share code: THA
LSE share code: THS
ISIN: CY0103562118
('Tharisa')
First quarter production report for the period ended 31 December 2016
Another quarter of solid production from Tharisa
Highlights for the three months ended 31 December 2016
- Reef mined continues to exceed the required run rate of 4.8 Mtpa on an annualised basis
- PGM production of 34.8 koz and chrome concentrate production of 322.2 kt
- Specialty chrome production at 23.9% of total chrome production
- PGM recoveries above target at 80.5% and chrome recoveries improve to 64.3%
- Contracted metallurgical chrome prices up 59.2% quarter-on-quarter
Safety
Safety remains a top priority and Tharisa continues to strive for zero harm at its operations. We are
pleased to report that there were no LTI’s during the quarter.
Production update
The production update for the quarter ended 31 December 2016 is as follows:
Quarter Quarter Quarter on Quarter Year
ended ended quarter ended ended
31 Dec 30 Sep movement 31 Dec 30 Sep
2016 2016 % 2015 2016
Reef mined kt 1 229.9 1 243.3 (1.1) 1 124.4 4 837.2
Stripping ratio m³ waste/m³ reef 9.0 8.2 - 6.4 7.3
Reef milled kt 1 206.4 1 267.2 (4.8) 997.4 4 656.3
PGM flotation feed
tonnes kt 885.1 937.9 (5.6) 765.8 3 575.6
PGM rougher feed
grade g/t 1.52 1.61 (5.6) 1.61 1.65
6E PGMs produced koz 34.8 39.1 (11.0) 24.0 132.6
PGM recovery % 80.5 80.6 (0.1) 60.4 69.9
Average PGM
contained metal
basket price US$/oz 740 804 (8.0) 687 736
Average PGM
contained metal
basket price ZAR/oz 10 287 11 289 (8.9) 9 865 10 881
Cr2O3 RoM grade % 17.5 17.5 - 18.5 18.0
Chrome recovery % 64.3 63.5 1.3 61.5 62.7
Chrome yield % 26.7 26.2 1.9 27.3 26.7
Chrome concentrates
produced kt 322.2 332.2 (3.0) 272.1 1 243.7
Metallurgical
grade kt 245.1 250.1 (2.0) 238.7 974.3
Specialty grades kt 77.1 82.1 (6.1) 33.4 269.4
Metallurgical grade
chrome concentrate
contract price US$/t CIF China 250 157 59.2 124 120
Quarter Quarter Quarter on Quarter Year
ended ended quarter ended ended
31 Dec 30 Sep movement 31 Dec 30 Sep
2016 2016 % 2015 2016
Metallurgical grade
chrome concentrate
contract price ZAR/t CIF China 3 488 2 193 59.1 1 777 1 751
Average exchange
rate ZAR:US$ 13.9 14.1 - 14.2 14.8
Mining
Tharisa’s team mined consistently above the combined plant processing capacity of 400 ktpm,
bringing the total reef mined from the open pit to 1 229.9 kt for the quarter. The focus remained on
grade control and the optimal blend of material ahead of the operation’s two plants. During the
quarter a total of 3.0 Mm3 of waste (both interburden and overburden) was removed to expose ore
at a stripping ratio of 9.0 on a m3:m3 (waste:reef) basis. This is in line with the life of open pit
average stripping ratio of 8.9 on a m3:m3 basis.
Processing
During the quarter 1 206.4 kt tonnes were milled notwithstanding planned routine maintenance,
including annual mill relining.
PGM recoveries at 80.5% remained well above the targeted recovery of 70%, resulting in PGM
production of 34.8 koz on a 6E basis.
Total chrome concentrate production was 322.2 kt at a recovery rate of 64.3%, edging closer to the
targeted recovery of 65% for chrome. Of that 322.2 kt, 77.1 kt was higher-value specialty grade
material. Specialty grade material typically fetches a premium to metallurgical grade chrome.
Market update
The average PGM basket price for the three months ended December 2016 was US$740/oz
(ZAR10 287/oz), which is US$64/oz lower than the US$804/oz (ZAR11 289/oz) price achieved in the
quarter ended September 2016.
Metallurgical grade chrome prices have risen almost 60% over the quarter with an average contract
price of US$250/t CIF main ports China achieved during the quarter. This represents an
improvement of US$93/t on the CIF contracted selling price concluded in the September 2016
quarter. Current market prices are significantly higher and while demand has eased ahead of the
Chinese New Year (end January 2017), market fundamentals and lower Chinese port stocks should
spur purchasing thereafter.
Outlook
PGM and chrome production remains on track to meet the FY2017 production guidance of 147.4 koz
PGMs and 1.3 Mt chrome concentrates, of which 300 kt will be specialty grade chrome concentrates.
“We are positive about the prospects for the year ahead and believe that, with the support of
buoyant chrome prices, 2017 will be a definitive year with reduced unit costs and increased operating
margins,” said Tharisa CEO Phoevos Pouroulis.
The above information has not been reported on or reviewed by Tharisa’s auditors.
Paphos, Cyprus
11 January 2017
JSE Sponsor
Investec Bank Limited
Investor Relations contact:
Sherilee Lakmidas
+27 11 996 3538
+27 79 276 2529
slakmidas@tharisa.com
Date: 11/01/2017 09:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.