To view the PDF file, sign up for a MySharenet subscription.

PAN AFRICAN RESOURCES PLC - Operational update for the quarter ended 30 September 2018

Release Date: 06/11/2018 09:00
Code(s): PAN     PDF:  
Wrap Text
Operational update for the quarter ended 30 September 2018

Pan African Resources PLC
("Pan African" or “the company" or “the group”)
(Incorporated and registered in England and Wales under Companies Act 1985 with registered number
3937466 on 25 February 2000)
Share code on AIM: PAF
Share code on JSE: PAN
ISIN: GB0004300496

OPERATIONAL UPDATE FOR THE QUARTER ENDED 30 SEPTEMBER 2018

Pan African is pleased to provide an operational update for the first quarter of the 2019 financial year (“this
quarter” or “first quarter”), and further information on the performance of the Elikhulu Tailings Retreatment
Plant (“Elikhulu”).

Pan African CEO Cobus Loots commented:
“Pan African recorded a commendable safety and production performance for the first quarter of the 2019
financial year. The group produced 37,729oz of gold during the quarter, and with Elikhulu now commissioned
and running at design capacity, we are confident of achieving our production guidance of approximately
170,000oz for the 2019 financial year.

Elikhulu ramped-up to its design capacity of 1-million tonnes per month during October 2018, ahead of the
original schedule and on budget. Average gold recoveries achieved were consistent with our forecasts, with
further optimisation of recoveries expected in the short term. The incorporation of the Evander Tailings
Retreatment Plant (“ETRP”) into Elikhulu, which will increase Elikhulu’s capacity to 1.2-million tonnes per
month, is progressing on schedule, with full commissioning expected to be completed by January 2019.

Barberton Mines is on track to meet its full-year production guidance of 100,000oz, with the underground
operations’ production benefitting from Fairview Mine’s high-grade 272 and 358 platforms, and the newly
installed regrind mill at the Barberton Tailings Retreatment Plant (“BTRP”) performing as anticipated.

At Evander Mines, we have commenced mining and vamping of the remnant high-grade stopes as part of
the phased closure of the underground mining operations as an initiative to supplement Evander Mines’
production, while commencing with the equipping and preparatory work to advance the mining of the 8 Shaft
pillar and high-grade areas in proximity to the pillar. The first phase of the equipping and preparatory work
is expected to be completed in the third quarter of the 2019 financial year.

The drilling programme on Barberton Mines’ Royal Sheba prospect has been completed, and we look
forward to updating shareholders on the progress of this exciting growth project in the coming months with
an updated resource statement to be released by the end of November 2018, and the feasibility study still
on schedule for release in February 2019.”

Safety

The group has significantly improved its safety performance in the first quarter, and we remain committed
and focussed to ensuring the safety of all our employees, while we continue to strive towards a zero harm
environment.

-     Fairview Mine achieved its one-million fatality-free shift milestone during July 2018;
-     The group had no fatalities in this quarter (2018 Q1: no fatalities);
-     The group’s lost-time injury frequency rate improved significantly to 0.57 (2018 Q1:3.64);
-     The reportable injury frequency rate improved significantly in this quarter to zero (2018 Q1: 0.91); and
-     The group is implementing recommendations from independent safety experts, following reviews of the
      respective mining operations’ safety systems and controls.

Elikhulu

-     As previously communicated, Elikhulu was successfully commissioned during September 2018, ahead
      of the original project schedule and on budget;
-   During October 2018, the plant attained steady-state production with a throughput of 1-million tonnes
    per month. The average gold recoveries achieved were consistent with our forecasts, with further
    optimisation of recoveries expected in the next months; and
-   The incorporation of the existing ETRP throughput into Elikhulu’s processing capacity, which will result
    in an increased processing capacity of 1.2-million tonnes per month, is on track with full commissioning
    expected to be completed by January 2019.

Barberton Mines Proprietary Limited (“Barberton Mines”)

-   Barberton Mines produced 27,201oz for this quarter, with underground mining operations contributing
    21,278oz, and the BTRP contributing 5,923oz. Barberton Mines remains on track to deliver its annual
    production guidance of approximately 100,000oz for the 2019 financial year.
-   Barberton Mines’ underground operations are benefitting from increased underground mining flexibility
    due to, inter alia, both the high-grade 272 and 358 platforms being available at the Fairview Mine
    operation. The BTRP is also benefiting from the commissioning of the regrind mill during May 2018,
    which has improved throughput and recoveries.
-   Barberton Mines has increased development rates to further improve Fairview Mine’s mining flexibility
    at the 11-block by developing towards an additional high-grade platform (256 platform), below the
    existing 272 and 358 platforms. This platform is expected to be in production by the end of the 2019
    financial year.

Evander Gold Mines Proprietary Limited (“Evander Mines”)

-   Evander Mines has implemented the following initiatives to maximise Evander Mines’ underground gold
    production:
     1) Mining and vamping of the remnant high-grade stopes as part of the phased closure of the
         underground mining operations, which contributed 3,815oz during this quarter; and
     2) While the above operations are ongoing, the mine has commenced equipping and preparatory
         work to advance mining of the 8 Shaft pillar and high-grade areas in proximity to the pillar, following
         a comprehensive review on the technical merits thereof. The first phase of the equipping and
         development of the 8 Shaft pillar and surrounding areas is estimated to be completed in the third
         quarter of the 2019 financial year.
-   The ETRP and surface-source operations produced 3,819oz for this quarter, and the operation is
    investigating new sources of feed for the Kinross plant, once the ETRP operation is integrated into
    Elikhulu.


The financial information contained in this announcement has neither been reviewed nor audited by the
company’s auditors and is the responsibility of the directors of Pan African.

For further information on Pan African, please visit the company’s website at www.panafricanresources.com



6 November 2018


Contact information


Corporate Office                        Registered Office

The Firs Office Building                Suite 31

2nd Floor, Office 201                   Second Floor

Cnr. Cradock and Biermann Avenues       107 Cheapside

Rosebank, Johannesburg                  London

South Africa                            EC2V 6DN

Office: + 27 (0) 11 243 2900            United Kingdom

Facsimile: + 27 (0) 11 880 1240         Office: + 44 (0) 20 7796 8644

                                        Facsimile: + 44 (0) 20 7796 8645


Cobus Loots                             Deon Louw

Pan African Resources PLC               Pan African Resources PLC

Chief Executive Officer                 Financial Director

Office: + 27 (0) 11 243 2900            Office: + 27 (0) 11 243 2900



Phil Dexter                             John Prior / Paul Gillam

St James's Corporate Services Limited   Numis Securities Limited

Company Secretary                       Nominated Adviser and Joint Broker

Office: + 44 (0) 20 7796 8644           Office: +44 (0) 20 7260 1000



Sholto Simpson                          Ross Allister/James Bavister/David McKeown

One Capital                             Peel Hunt LLP

JSE Sponsor                             Joint Broker

Office: + 27 (0) 11 550 5009            Office: +44 (0) 20 7418 8900



Julian Gwillim                          Jeffrey Couch/Thomas Rider

Aprio Strategic Communications          BMO Capital Markets Limited

Public & Investor Relations SA          Joint Broker

Office: +27 (0)11 880 0037              Office: +44 (0) 20 7236 1010



Bobby Morse

Buchanan

Public & Investor Relations UK

Office: +44 (0)20 7466 5000

Email: PAF@buchanan.uk.com


Website: www.panafricanresources.com

Date: 06/11/2018 09:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story