RESOURCE GENERATION LIMITED - Shareholder Update

Release Date: 04/05/2017 07:05
Code(s): RSG     PDF:  
Wrap Text
Shareholder Update

Resource Generation Limited
Registered in Australia under the Corporations Act, 2001 (Cth) with
registration number ACN: 059 950 337
ISIN: AU000000RES1
Share Code on the ASX: RES
Share Code on the JSE: RSG
(“Resource Generation” or the “Company”)
4 May 2017
ASX Announcement



                                                              Shareholder Update
Dear fellow shareholders
Project Funding
A meeting of the board was held in Johannesburg on Wednesday 26 April 2017 with the Australian
resident directors attending through a conference call. The CEO provided a report detailing the
progress made with the project funding since my last report to shareholders on 2 March 2017. I am
pleased to report that tangible progress continues to be made on most fronts. In what is a complex
process, multiple contracting agreement are being negotiated in parallel thereby providing greater
efficiency savings, de-risking interdependent contracts and providing greater certainty to all parties.
As detailed below, most major contracts are now substantially agreed clearing the way for us to
finalise outstanding matters at an all party meeting (all party meeting) planned for mid-May 2017.
On this basis, we are confident that we will be in a position to report to the lenders by end May
2017 that all material contracts are sufficiently completed thereby enabling their credit
approval processes to take place during June/July 2017.


Items completed or substantially completed
      .      Base Case Financial Model (BCFM): completed in June 2016 has been audited by Ernst &
             Young with no flaws identified. The BCFM will require a final update shortly before the credit
             approval stage commences (see below).
      .      Debt Club Project Finance Term Sheet: agreed in July 2016 and will require only minimal
             update in order to accommodate any changes flowing from the update of the BCFM.
      .      Independent Technical Reports:
                o Technical report completed in December 2016 (apart from commentary on material
                    contracts promised for early May 2017)
                o Environmental report completed in September 2016
                o Marketing report completed in December 2016
Resource Generation Australia (ACN 059 950 337)
c/o Level 1, 17 Station Road, Indooroopilly, QLD, 4068
GPO Box 126, Albion QLD 4010. Phone +27 12 345 1057 Fax +27 (012) 345 5314
Directors: Denis Gately (Chairman), Lulamile Xate (Deputy Chairman), Robert Croll, Dr. Konji Sebati,
Colin Gilligan, Leapeetswe Molotsane                                                                   www.resgen.com.au
CEO: Rob Lowe
Company secretary: Mike Meintjes
       o   Legal due diligence report substantially completed with a small number of issues to
           be resolved at an all party meeting planned for mid-May 2017.
    All of the above independent technical reports are considered to be satisfactory and
    meet the requirements of the project and lenders.


.   EPC contracts:
      o CHPP contract: the design and construction contract with Sedgman was completed
          in January 2017. The lenders’ lawyers have now provided their comments on the
          contract and we do not believe they contain anything of serious impact or concern. It
          is intended to finalise all outstanding matters at the all party meeting.
      o CHPP Operations and Maintenance contract: the operations and maintenance
          contract with Sedgman was completed in January 2017. The lenders’ lawyers have
          now provided their comments on the contract, again without anything of serious
          impact or concern. It is intended to finalise all outstanding matters at the all party
          meeting.

.   Logistics:
       o Commercial terms relating to quantum, tariff and port destination (Richards Bay)
           have been agreed with Transnet Freight Rail (TFR).
       o Transportation of Coal Agreement was completed on schedule by 28 February 2017
           and was submitted to the lenders for review shortly thereafter. The lenders’ lawyers
           have now provided their comments on the contract and we do not believe they
           contain anything of serious impact or concern. It is intended to finalise all outstanding
           matters at the all party meeting.
       o Coal Line Service Level Agreement was completed on schedule by 28 February
           2017 and was submitted to the lenders for review shortly thereafter. The lenders
           lawyers have now provided their comments on the contract, without anything of
           serious impact or concern. It is intended to finalise all outstanding matters at the all
           party meeting.
       o Process for the allocation of port capacity at Richards Bay Coal Terminal (RBCT) has
           been agreed with TFR and we are advised that the public process will be
           commenced in the very near future. To the extent our export capacity requirement
           cannot be accommodated at RBCT it will be channelled through Richards Bay
           Grindrod Terminal.

.   Mining Contract:
       o Binding Term Sheet
          ? A binding term sheet containing all of the primary commercial terms, sufficient for
            the lenders’ credit approval processes (see below), is at an advanced stage and
            due for completion by end May 2017.
       o Mining Contract
          ? A first draft of the mining contract has been prepared and commented on by the
            preferred mining contractor Stefanutti Stocks Mining Services. It is intended to
            finalise the mining contract by end July 2017 and to use the time between now and
            then to further optimise costs and productivity.

.   Ancillary Works Contract:

                                                                                              PAGE 2
           o   A first draft of the contract has been prepared and submitted to the preferred
               contractor Sedgman for comment. Discussions are currently taking place with
               Sedgman with the objective of finalising the ancillary works contract by end May
               2017.


   .   Off-take Contracts:
           o ICML 2 million tons per annum export off-take contract completed and signed
           o Valu 1 million tons per annum export off-take contract completed and signed
           o Noble 500,000 tons per annum export off-take contract completed and signed
           o Noble domestic off-take contract 750,000 tons per quarter completed and signed

As reported to the market on 14 March 2017 the Noble domestic off-take and marketing agreements
were restated and executed as a condition precedent to the extension of the Noble facility agreement.
The first draw down under this facility has been successfully completed.


Items not yet completed (and status)
    . ESKOM:
      A number of discussions have been held with ESKOM and, as a result, we are encouraged
      to believe that there are solid grounds on which to conclude a coal supply agreement.
      Further discussions are currently on hold pending the outcome of internal enquiries taking
      place within ESKOM unconnected with the negotiation of this coal supply agreement.
    . Rail Link:
         o Rail Link Funding
             ? Discussions with Development Bank of South Africa (DBSA) concerning the
                 funding of the rail link are now at an advanced stage with DBSA planning on
                 submitting its application for first stage credit approval in the first week of May
                 2017. If approval is granted there will follow a short due diligence and, subject to a
                 satisfactory outcome, a binding term sheet will be prepared for approval by the
                 Board. DBSA is targeting financial close by September 2017.
         o Rail Link EPC Contract
             ? Negotiations with the three preferred contractors have been concluded:
                 ? RCE Consultants (engineering, procurement and construction management
                    services)
                 ? Stefanutti Stocks Roads and Earthworks (rail earthworks and bridges)
                 ? Transnet Freight Rail RME (ballast, track and signalling)
           Our lawyers are currently drafting the appropriate contracts for internal review before
           submission to the contractors for comment. Our target date for completion of the Rail Link
           EPC is end July 2017.
    . Credit Approvals:
      The lenders have confirmed that they will be in a position to begin their respective credit
      approval processes at the point of “Contract Finalisation” (CF). CF has been identified as
      completion of all the material contracts, excepting that demonstrable progress towards a rail
      link funding solution and coal supply agreement will suffice for credit approval purposes.


                                                                                                  PAGE 3
         However, financial close of the rail link funding and a coal supply MOU or agreement with
         ESKOM will be conditions precedent to financial close of the project finance.


IPP
Together with our advisers, Waterbourne Capital, we have been actively preparing for our
submission for a 300MW IPP towards the end of 2017. In particular, we have undertaken the
following since the last report to shareholders:

      1. We submitted a full response to the Department of Energy’s public request for information,
         detailing the mine’s current status and the work done to date on the IPP. The Department
         has acknowledged our submission and has undertaken to take our comments into
         consideration;
      2. We have concluded a beauty parade of leading law firms with the intention of making
         appointments as legal counsel to the bid and as legal counsel to the lenders. We have
         identified our preferred firms;
      3. Once appointed, the first task of the legal firm appointed to advise the bid will be the
         preparation of the Joint Development Agreement (JDA);
      4. In parallel with the preparation of the JDA we are identifying local partners to join our
         consortium, subject to board approval
      5. We have invited various insurance firms to pitch for the appointment as Insurance Advisor to
         the bid;
      6. We have invited various environmental firms to pitch for the appointment as Environmental
         Advisor to the bid;
      7. A project information memorandum is currently being prepared and will be used to introduce
         the local commercial banks and developmental funding institutes to the project during
         meetings scheduled in May;
      8. To date, Rand Merchant Bank, Investec Bank, IDC, DBSA and PIC have all verbally
         expressed an interest in engaging

Once the JDA has been completed, we will commence with the process of selecting an EPC partner
again subject to board approval. It is expected that the partner will be Japanese or South Korean as
both countries have well-established credentials that are most likely to comply with the Request for
Proposal (RFP) when issued by the Department. We are expecting the RFP to be released towards
the end of 2017.

Other

The Board has noted with concern the recent downgrade of South Africa’s foreign credit ratings and
the potential in the near future for a downgrade of its domestic ratings. The Board believes these
downgrades are not likely to impact the availability of funding for our project but may result in an
increase in the cost of borrowing.

The next scheduled board meeting is to be held in the week commencing 19 June 2017. I intend to
provide you with a further report at that time.


Yours sincerely




                                                                                                PAGE 4
Denis Gately
Chairman
For and on behalf of the Board
About Resgen:
Resource Generation Limited (the “Company” or “Resgen”) is an emerging ASX and JSE-listed
energy company, currently developing the Boikarabelo Coal Mine in South Africa’s Waterberg region.
The Waterberg accounts for around 40% of the country’s currently known coal resources. The Coal
Resources and Coal Reserves for the Boikarabelo Coal Mine, held through the operating subsidiary
Ledjadja Coal, were recently updated based upon a new mine plan and execution strategy. The
Boikarabelo Coal Resources total 995Mt and the Coal Reserves total 267Mt applying the JORC Code
2012 (ASX Announcement 23 January 2017). Stage 1 of the mine development targets saleable coal
production of 6 million tonnes per annum. Ledjadja Coal is a Black Economic Empowerment
subsidiary (BEE) operating under South Africa’s Broadbased Black Economic Empowerment Act,
Section 9(5): Codes of Good Practice.
Resgen’s primary shareholders are the Public Investment Corporation of South Africa (PIC), Noble
Group and Altius Investment Holdings.


For further information please contact:

Mike Meintjes, Company Secretary on mmeintjes@resgen.com.au or +61 413 706 143

Media enquiries:

Australia: Martin Debelle on + 61 282 340 102

South Africa: Charmane Russell/Thembisa Kotobe on +27 11 880 3924

JSE Sponsor: Deloitte & Touche Sponsor Services (Pty) Ltd




                                                                                             PAGE 5

Date: 04/05/2017 07:05:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.