Subscription of Shares in Nyanza Light Metals (Proprietary) Limited and Operation of the Business of Nyanza

Evraz Highveld Steel and Vanadium Limited
Registration number: 1960/001900/06
(Incorporated in the Republic of South Africa)
Share Code: EHS
ISIN Code ZAE000146171
("Evraz Highveld" or "the Company")

Voluntary Announcement: Subscription of Shares in Nyanza Light                          Metals
(Proprietary) Limited ("Nyanza") and Operation of the Business of Nyanza

Shareholders are advised that EVRAZ Highveld Steel and Vanadium Limited (“EVRAZ
Highveld”) has entered into an agreement to subscribe for 20% of the issued shares in
Nyanza. The remaining 80% of the issued shares in Nyanza will be held by Arkein Industrial
Holdings (Proprietary) Limited ("Arkein"), upon the agreement becoming unconditional in
accordance with its terms. The Company and Arkein have entered into this joint venture for
the purpose of conducting the business of Nyanza ("Business") as described below. The
Company and Arkein have further entered into a shareholders agreement to govern the
relationship among the parties in respect of Nyanza and its Business. The shareholders
agreement is subject to the fulfilment or waiver of several suspensive conditions by 31 July
2013.

The Company produces iron and steel products and vanadium-bearing slag at its steelworks
at eMalahleni, Mpumalanga from which it produces titanium dioxide rich waste slag ("Waste
Slag"). Nyanza shall perform the business of reprocessing the Waste Slag through the
construction and operations of a plant ("Reprocessing Plant") producing a rutile (“titanium
dioxide”) pigment, which plant shall be constructed on a site and location to be determined
by the parties during the feasibility studies detailed below.

Prior to the construction of the Reprocessing Plant, the parties will conduct a Scoping Study,
a Pre-Feasibility Study and a Bankable Feasibility Study. A Scoping Study was initially
conducted in order to ascertain the high-level viability of the Business and was completed in
March of 2012; the Pre-Feasibility Study (“PFS”) were the studies conducted in order to
ascertain a more detailed assessment of the Business as proposed in the Scoping Study
and was completed in May 2013. The Bankable Feasibility Study (“BFS”) is the extensive
technical and financial study to assess the commercial viability of the Business with sufficient
detail and integrity that it may be used to arrange project financing. The BFS is envisaged to
commence in July 2013 and take 18 months to complete. After the completion of the BFS
and subject to the approvals of the boards of the Company and Nyanza and/ or its
Shareholders, taking into account the results of the study, Nyanza shall proceed to construct
the Reprocessing Plant to conduct the Business.


eMalahleni
25 June 2013


Sponsor
J.P. Morgan Equities South Africa (Pty) Ltd.

Date: 26/06/2013 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story