To view the PDF file, sign up for a MySharenet subscription.

DIAMONDCORP PLC - Lace Mine development activities commence

Release Date: 24/01/2013 09:00
Code(s): DMC     PDF:  
Wrap Text
Lace Mine development activities commence

 DiamondCorp plc
 JSE share code: DMC & AIM share code: DCP
 ISIN: GB00B183ZC46
(Incorporated in England and Wales)
(Registration number 05400982)
(SA company registration number 2007/031444/10)
("DiamondCorp", “the Group” or "the Company")

Lace Mine development activities commence

    •   Company fully financed for Lace Mine development
    •   Group cash in accounts £5.5m
    •   First diamonds from kimberlite expected Q3 2014
    •   Peak funding for 47 level block cave estimated at £20.3m
    •   Investment in 1.2 mtpa plant and underground development to date c.£18m
    •   Estimated resource contains 13.4m cts of diamonds, open at depth

DiamondCorp, the Southern African diamond development and exploration company, is
pleased to announce that development activities have commenced for the 47 level block cave
at the Lace mine, following receipt of the first US$3 million (£1.9 million) tranche of loan funds
from Laurelton Diamonds, Inc., a wholly-owned subsidiary of Tiffany & Co.

The second US$3 million tranche is scheduled to be paid on 10 April 2013. The combination
of funding through the Tiffany loan, £4.2 million of convertible bonds (issued in December
2012) and R220 million (£15.6 million) from the Industrial Development Corporation of South
Africa (as announced on 21 September 2012) completes the R320 million (£23 million) Lace
project financing package.

The Main Pipe at the Lace mine contains 33.1 million tonnes of kimberlite indicated and
inferred to a depth 855m containing approximately 13.4 million carats in both resource
categories at an average grade of 40.1 carats per hundred tonnes. The resource has an in-
ground value in excess of $2 billion at $160 per carat.

The deposit will be mined by block cave mining, with three caves planned over the 25 year life
of mine on the 47, 67 and 85 levels (at depths of 470m, 670m and 850m respectively). The
kimberlite is open at depth, and also contains a significant bulge between 250m and 360m
depth with the potential to add additional tonnage and diamonds not currently included in the
resource statement.

The SRK Independent Engineering Report on the 47 level block cave development published
in March 2012 estimated the total development cost (including working capital and a 15%
contingency on capital and development costs) at R384 million (£27 million). The first
diamonds from development are expected to be recovered in Q3 2014, and the peak funding
requirement (including working capital) is expected in April 2015 at R286 million (£20.3
million) when blasting of the slot drive and doming starts to deliver significant tonnage of
kimberlite. The costs of establishing the block cave thereafter are offset by revenues from the
sale of diamonds recovered from kimberlite mined during development.

Approximately 600,000 tonnes of kimberlite is expected to be extracted and processed during
this period. Anticipated revenue from the mine is forecast at R421 million (£30 million) during
the 43 months of development before full production of 100,000 tonnes per month is
achieved. The 1.2 million tonne per annum Lace mine is expected to produce more than
500,000 carats of diamonds per annum at peak production.

Investment to date

DiamondCorp has invested approximately £18 million into the Lace project with equity raised
from shareholders since it acquired the project in 2005. These funds have been advanced as
shareholder loans from the parent company to the 74%-owned South African operating
subsidiary Lace Diamond Mines (Pty) Limited. The funds have been used for construction of
a 1.2 mtpa processing plant, the underground mining fleet and tunnel development to the
260m level.

The shareholder loans and accumulated interest represent an asset to the Company of
approximately 6.6p per share as they must be repaid from mine cashflow before any dividend
distributions to the Company and its broad-based black economic empowerment partners,
Shanduka Resources (Pty) Limited (13%) and Sphere Investments (Pty) Limited (13%).

Development activities scheduled over the next four months include:

    •   Excavation of a new 66,000 bank cubic metre boxcut providing the surface entrance
        to the twin conveyor belt and men and materials declines for the life of mine (LOM).
    •   Completion of a vent raise from the 16 level to provide sufficient interim ventilation for
        continuous blasting decline development until LOM vent shafts are raise bored.
    •   Installation of a tipping arrangement on the 24 level to allow loading of waste
        generated from the twin decline development down to the 47 level. Until 2.6 km of
        conveyors are installed, development waste will be hauled out of the mine by low
        profile dump trucks.
    •   Complete rebuild of another underground loader and two dump trucks required to
        meet the scheduled development ramp up.
    •   Essential upgrades to the dense media separation plant to alleviate front-end
        bottlenecks in the re-crush circuit at full-scale production. Completion of these
        upgrades will also allow tailings retreatment to recommence.
    •   Completion of detailed design drawings for the underground conveyor belts.
    •   Definition drilling of the bulge from within the kimberlite bulk sampling area on the
        260m level.

DiamondCorp's CEO, Paul Loudon said: “We are delighted to be underway with the 47 block
cave development which will mark the transition of DiamondCorp from explorer to
underground diamond producer. Diamond production from tailings re-treatment will
recommence during Q2, initially on one shift while the upgraded processing plant is re-
commissioned. We will then have the capacity to ramp up to three shifts in the second half of
the year if diamond prices strengthen for small goods.”


Contact details:

DiamondCorp plc
Paul Loudon, Chief Executive
Tel: +44 20 3151 0970
     +27 82 824 6897

SP Angel Corporate Finance LLP
AIM Nomad and Broker
Ewan Leggat/Laura Littley
Tel: +44 207 598 5368

Ocean Equities Limited
Guy Wilkes
Tel: +44 207 786 4370

PSG Capital (Pty) Limited
John-Paul Dicks
Tel: +27 21 887 9602

Russell & Associates
Charmane Russell/Marion Brower
Tel: +27 11 880 3924

24 January 2013

NOT FOR DISTRIBUTION IN OR INTO AUSTRALIA, CANADA, JAPAN OR THE UNITED
  STATES OR ANY OTHER JURISDICTION IF TO DO SO WOULD CONSTITUTE A
             VIOLATION OF THE LAWS OF SUCH JURISDICTION

Date: 24/01/2013 09:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story