Bakubung platinum mine processing plant progress update
WESIZWE PLATINUM LIMITED
(Incorporated in the Republic of South Africa)
(Registration number: 2003/020161/06)
Share code: WEZ
ISIN: ZAE000075859
(the “Company”)
BAKUBUNG PLATINUM MINE PROCESSING PLANT PROGRESS UPDATE
Shareholders are referred to the announcement released on SENS on 30 May 2023 advising
that hot commissioning of the Bakubung Platinum Mine (“BPM”) processing plant
(“BPM Processing Plant”) would commence on 31 May 2023. Due to faults in the ring gear
of the ball mill and the feeding mixing tanks of the tailing filter press, the hot commissioning
process could not ensue on the aforementioned date.
The Company hereby advises shareholders that the hot commissioning of the BPM
Processing Plant will now commence on 5 June 2023, and that production at the BPM is
expected to commence as soon as possible after the commissioning process of the BPM
Processing Plant has been completed.
The Company will update shareholders and investors on the progress at the BPM, and further
announcements will be made in this regard, as and when appropriate.
The board of directors of the Company would like to extend its appreciation and thanks to
shareholders for their continued investment and interest in the Company.
Johannesburg
2 June 2023
Sponsor
PSG Capital
Date: 02-06-2023 05:07:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.