ANNOUNCEMENT
26 April 2023
MAKHADO PROJECT UPDATE
MC Mining Limited (MC Mining or the Company) is pleased to provide an update on its fully licensed,
shovel ready Makhado hard coking coal project (Makhado Project or the Makhado).
The salient features of the Makhado Project are:
• JORC Code compliant Coal Resources of 296 mineable tonnes in situ (MTIS)1 in the Measured and
Indicated categories
• JORC Code compliant run of mine (ROM) Coal Reserves of 69.3 million tonnes (Mt) in the Proved
and Probable categories, which is expected to increase following completion of the
implementation plans for Scenario 2
• Creation of an estimated 650 permanent employment positions when in full production
The Bankable Feasibility Study (BFS) was completed in April 2022 by independent mining consultancy
Minxcon (Pty) Ltd and was followed by two alternative development scenarios that significantly
improved the baseline BFS economic outcomes, as announced by the Company on 30 August 2022 and
were supplementary chapters to the BFS. The alternative scenarios were assessed at pre-feasibility
level and would require additional capital expenditure compared to the BFS base case scenario (Base
Case). While the Base Case scenario was feasible and economically robust, the alternative scenarios
resulted in improved project economics. The Base Case comprised the mining of the West Pit, followed
by the East and Central Pits, the crushing and screen of the ROM coal to Makhado and the
transportation of the screened material 135km to the modified Vele Colliery plant for processing.
Scenario 2, included as part of the BFS, was selected by the Board for implementation and included
the initial mining of the East Pit, followed by the Central and West Pits, and the construction of a coal
handling and processing plant (CHPP) at Makhado, rather than at the existing Vele facility, with an
annual CHPP throughput capacity of two million tonnes per annum (Mtpa). Following this, the
Company appointed Erudite (Pty) Ltd (Erudite) to complete the detailed study work for a full process
plant design of the Makhado CHPP for Scenario 2.
1 Makhado Resources per the Company’s 30 June 2022 Resources & Reserves Statement
The Company completed various studies in Q4 CY2022, enhancing the development plans for Scenario
2, including an optimization study on the Makhado CHPP. This optimisation study increases the
Makhado CHPP annual run of mine feed capacity from 2.0Mtpa to 4.0Mtpa. The mine plans have been
revised, as has the detailed CHPP and infrastructure design work which was completed by Erudite.
Implementation Plan completed
The Company has also made notable progress towards the completion of a detailed implementation
plan (Implementation Plan) for the first five years of mining and processing operations. The Company
has limited technical execution capacity and with a strategy to limit fixed overhead costs, has secured
this execution capacity by contracting an outsourced owner’s team and has also engaged key service
providers to manage the Implementation Plan.
The Implementation Plan includes a detailed execution plan for the construction of the East Pit,
Makhado CHPP, related infrastructure and a detailed mine plan for the first five years of operations.
The key inputs of the Makhado Project were independently peer reviewed, and the Implementation
Plan has been value-engineered improving the accuracy of the studies from the pre-feasibility study’s
±30% accuracy to an estimated accuracy of ±10%. In addition, the noteworthy improvements to
Scenario 2 under the Implementation Plan include:
• Revision of the mine plan resulting in the ROM from 3.2Mtpa to 4.0Mtpa, facilitating improved
volume efficiencies and the planned ROM coal feed to the CHPP has increased by 30%. Previous
development plans incorporated a crushing and screen plant that would have removed 1.2Mtpa
of discard material prior to processing in the CHPP;
• The full ROM feed stream (4.0Mtpa) will now be processed through the CHPP to maximise coal
yields, in contrast to the BFS’s Base Case and Scenario 2 plans where the ROM coal was pre-
screened and 2.0Mtpa crushed and screened coal was planned to be processed;
• Improved accuracy in interpreting the depth of oxidation to the top of the target coal seams from
recent supplementary diamond core drilling. The limit of oxidation in the East Pit occurs at an
average of 28 metres (m) below surface, compared to an average of 17m estimated for the West
Pit which, in the BFS, was scheduled to be mined first. As a result, the strip ratio for the first five
years of mining has increased from 2.7 to 3.0 (waste BCM: ROM tonne);
• The East Pit has higher compensating coal yields and is expected to have a life-of-mine (LOM) in
excess of 13 years. The mining of the higher yielding East Pit and project enhancements results in
hard coking coal (HCC) yields in the first five years of mining increasing from 19.4% as per the BFS,
to 22.6%, a 16% improvement, in Scenario 2. Thermal coal yields increase by 9% (from 16.1% to
17.6%); and
• As a result of the above, Makhado would produce an average of 880,000t per annum (tpa) of HCC,
compared to 540,000tpa in the BFS (an increase of 63%), while thermal coal production increases
from 570,000tpa to an average of 650,000tpa (an increase of 14%) during the first five years of
operation.
Key metrics for the Implementation Plan (first five operating years of the Makhado Project) compared
to Scenario 2 of the BFS are summarised in the table below:
Implementation
Parameter Units Scenario 2 Variance Variance
Plan
Nominal annual Mtpa 4.01 3.22,3 +0.8 +25%
throughput (annual)
Strip ratio (five Waste (BCM): 3.01 2.52 +0.9 +42%
years/LOM) RoM (t)
Yield – mid-vol 64 HCC % 22.61 19.42 +3.2 +16%
(five years/LOM)
Yield – thermal Coal % 17.61 16.12 +1.5 +9%
(five years/LOM)
Saleable Coking Coal Mt 4.04 3.15 +0.9 +30%
(first five years)
Saleable Thermal Coal Mt 3.14 2.65 +0.5 +21%
(first five years)
1 Production for the first five years from the East Pit in terms of the Implementation Plan
2 The mining plan envisaged 3.2Mtpa ROM mined that would have been crushed and screened and only 2.0Mtpa processed in the Makhado
processing plant
3 Average for the 21-year LOM which included the mining of the West, East and Central Pits
4 Saleable coal production for the first five years of mining the East Pit
5 Saleable coal production for the first five years of mining the West Pit and early mining of the East Pit
Project expenditure
The higher volume of coal mined as well as CHPP processing capacity is anticipated to result in higher
capital expenditure. Erudite has completed the detailed designs for the mine infrastructure and CHPP
and is in the process of obtaining detailed execution quotes for the construction of the CHPP. This
process is expected to be finished in July 2023 and will also cater for the enlarged mining and
processing footprint. EHL Engineering (Pty) Ltd (EHL) has been engaged to design and construct the
bulk power supply infrastructure, a process on the construction critical path. Enprotech (Pty) Ltd
(Enprotech) has commenced the design and procurement of the flotation and filtration plant, a key
part of the CHPP required to extract the HCC. The flotation and filtration plant is expected to cost R155
million (US$8.6 million) and the Company has agreed in-principle with Enprotec that this part of the
plant will be constructed on a build, own, operate, transfer (BOOT) basis.
The Makhado Project will be contractor-operated and, following the revised 4.0Mtpa mine plan, the
Company has commenced an open tender process to select a mining contractor. The Company also
anticipates commencing the processes to identify and appoint an outsourced CHPP operating
contractor and analytical laboratory operator. These processes are expected to be completed in early
Q3 CY2023. First coal production is expected 18 months from commencement of construction, which
is expected to occur in H2 CY2023.
Commencement of early works
Early works associated with the Implementation Plan commenced in February 2023, as planned, and
these workstreams consist of activities with long lead times or to ensure that social and regulatory
licenses are complied with. This includes the commissioning of the power line works, order placements
for key long lead CHPP items and equipment, construction of the main access road and bridge, as well
as accommodation and administration upgrades and fencing to secure the mine site. As previously
announced, during November 2022 the Board approved an expenditure budget of ZAR71.3 million
(US$4.1 million) for Makhado early works. The Board also approved the commitment of a further R45.0
million (US$2.5 million) for the long lead time items.
Godfrey Gomwe, Managing Director and Chief Executive Officer, commented:
“Substantial progress has been made to convert the previous mining studies into an Implementation
Plan for the first five years of mining operation that is sufficiently detailed for the project execution
with attractive economics. We are also pleased to now have an owner’s team in place, as well as a
reputable and expert Engineering, Procurement & Construction Manager in Erudite. The peer-reviewed
studies completed in late CY2022 and Q1 CY2023 have resulted in increased processing capacity
leading to higher production of hard coking coal as well as the thermal coal by-product. The increase
in product yields is also very pleasing and enhances the project economics.
The Company anticipates that the funding arrangements will be concluded in early Q3 CY2023 with the
tender adjudication for major contractors, notably the mining contractor and CHPP operator, in early
Q3 2023, followed by the final investment decision soon thereafter, ensuring that the Makhado Project
execution processes are broadened from early works to include full scale implementation. First coal
production is expected 18 months from CHPP construction start-date.
The appointment of EHL to proceed with the design and construction of the 14 km power line ensures
that the supply of electricity to Makhado is in place for prior to the commencement of operations.”
Godfrey Gomwe
Managing Director and Chief Executive Officer
For more information contact:
Tony Bevan Company Endeavour Corporate +61 8 9316 9100
Secretary Services
James Harris / James Nominated Strand Hanson Limited +44 20 7409 3494
Dance Adviser
Rory Scott Broker (AIM) Tennyson Securities +44 20 7186 9031
Marion Brower Financial PR (SA) R&A Strategic +27 11 880 3924
Communications
BSM Sponsors Proprietary Limited is the nominated JSE Sponsor
This announcement has been approved by the Company's Disclosure Committee.
This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) No. 596/2014, as it forms part
of UK domestic law by virtue of the European Union (Withdrawal) Act 2018, as amended.
About MC Mining
MC Mining is an AIM/ASX/JSE-listed coal exploration, development and mining company operating in South Africa. MC Mining’s key projects
include the Uitkomst Colliery (metallurgical and thermal coal), Makhado Project (hard coking coal), Vele Colliery (semi-soft coking and thermal
coal), and the Greater Soutpansberg Projects (coking and thermal coal).
Glossary
Term Definition
CHPP Coal handling & processing plant
HCC hard coking coal
JORC Australasian Code of Reporting of Exploration Results, Mineral Resources and
Ore Reserves, 2012 Edition
Indicated Coal Maximum distance between points of observation of 1,000 metres (m) and a
Resource maximum Halo radius of 500m
Inferred Coal Maximum distance between points of observation of 4,000m and a maximum
Resource Halo radius of 2,000m
Measured Coal Maximum distance between points of observation of 500m and a maximum
Resource Halo radius of 250m
MTIS mineable tonnes in situ
LOM life of mine
Probable Coal A Probable Coal Reserve is the economically mineable part of an Indicated, and
Reserves in some circumstances, a Measured Coal Resource. The confidence in the
modifying factors applying to a Probable Coal Reserve is lower than that
applying to a Proved Coal Reserve.
Proved Coal A Proved Coal Reserve is the economically mineable part of a Measured Coal
Reserve Resource. A Proved Coal Reserve implies a high degree of confidence in the
Modifying Factors.
ROM run of mine
SAMREC South African Code for the Reporting of Exploration Results, Mineral Resources
and Mineral Reserves
Statements of intention
Statements of intention are statements of current intentions only, which may change as new information becomes available or circumstances change.
MC Mining has ensured that the mineral resources quoted are subject to good governance arrangements and internal control. The Company has
engaged external independent consultants to update the mineral resource in accordance with the JORC Code 2012 and SAMREC 2016. The units
of measure in this report are metric, with Tonnes (t) = 1,000kg. Technical information that requires subsequent calculations to derive subtotals,
totals and weighted averages may involve a degree of rounding and consequently introduce an error. Where such errors occur MC Mining does
not consider them to be material.
The Company’s principal competent person is Mr J.C.H.K. Sparrow who is in full time employ of MC Mining as the Group Geologist. Mr Sparrow,
who is a registered professional scientist of good standing with the South African Council for Natural Scientific Professions (SACNASP) (400109/03)
and acts the Competent Person under the AIM Rules - Note for Mining and Oil & Gas Companies, he has read and approved the technical
disclosures in this announcement.
Date: 26-04-2023 11:16:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.