Wrap Text
March 2023 Quarterly Activities Report
Orion Minerals Limited
Incorporated in the Commonwealth of Australia
Australian Company Number 098 939 274
ASX share code: ORN
JSE share code: ORN
ISIN: AU000000ORN1
March 2023 Quarterly Activities Report
HIGHLIGHTS
Strategic equity funding package secured by Orion to accelerate the development of its portfolio of
advanced base metals projects in the Northern Cape Province, South Africa:
• Firm commitments received for a two-tranche Share Placement to raise ~A$13 million, with tranche
one completed, being A$10.66 million, and tranche two subject to shareholder approval. The
placement also offered participants four free attaching options for each Share issued under the
Placement, exercisable at 1.7 cents (ZAR20 cents) and expiring on 30 November 2023. The total
value of the equity funding package, assuming all Placement Options are ultimately exercised, is
~A$73 million.
• Clover Alloys (SA), a privately-owned South African mining group, becomes a cornerstone investor
in Orion by subscribing for ~A$6.7 million.
• Clover Alloys has extensive experience in the development of modular processing plants, which
will be of significant strategic value to Orion as it brings its key base metal projects into production.
• The capital raise puts Orion in a strong position to access the previously announced US$87 million
funding package from Triple Flag Precious Metals and a ZAR250 million funding facility secured
from the Industrial Development Corporation (IDC).
• Clover Alloys CEO, Philip Kotze, takes up a seat on the Orion board as a Non-Executive Director.
Definitive agreement signed with the IDC for the advance of ZAR250 million (~A$21 million) as a senior
secured convertible loan facility to fund early works at the Prieska Copper-Zinc Mine (PCZM):
• The IDC convertible loan, together with the US$87 million Triple Flag funding package, will underpin
Orion’s early production strategy at Prieska, including the completion of a Feasibility Study for early
mining and the commencement of mine dewatering.
Orion’s Managing Director and CEO, Errol Smart, said:
“The March Quarter has been a game-changer for Orion. Our efforts to secure the right partners and the
necessary funding to progress our core base metal projects in South Africa’s Northern Cape culminated
in the March 2023 announcement of a strategic share placement which saw the introduction of Clover
Alloys as a cornerstone shareholder.
“Securing the support of this highly regarded South African investor and mining group as a key part of this
broad funding package puts Orion in an outstanding position to realise our vision to become a major
new near-term South African base metals producer – and is testament, not only to the quality of our assets
but also to the extremely capable and experienced development and operations team we have
assembled.”
”We are very pleased that the key elements of our overarching strategic funding package have now
come together and – despite being a junior miner – we have been able to secure total funding of almost
ZAR2.5 billion, more than double our current ZAR900 million market cap. Our ability to raise this capital
clearly reflects the fact that Orion is now poised for a rapid transformation from explorer to developer
and, ultimately, operating mining company of a premium portfolio of copper focussed, base metal
mines.
”The combined pre-development funding being provided by Triple Flag and the Industrial Development
Corporation of South Africa (IDC) will allow us to progress our development plans both for the flagship
Prieska Copper-Zinc Project and the Okiep Copper Project.
”It has been six years since Orion exercised its option to acquire the Prieska Copper-Zinc Project and the
progress that we have made in that time is testament to the quality of the asset and the team on the
ground. We have taken our first base metals project, closed over thirty years ago, to its current status as
a fully-permitted, ready-to-mine project with a long life of mine. We have also expanded our business to
include other base metal hubs within the Northern Cape.
”Orion is now in a strong position to become a rapidly growing supplier of future-facing metals to global
markets, at a time when demand for these metals is anticipated to surge as a result of global efforts to
decarbonise.”
Commodity Markets
The 2023 outlook for base metals hinges on the interplay between a slowing global economic outlook
and the green energy transition. Future-facing commodities like copper had a subdued start to the year,
as tightening central bank monetary policies, the strengthening US dollar and weak demand from China
resulted in price volatility.
Copper prices opened the year at US$8,386/t and started an early ascent to reach a seven-month high
of US$9,436/t by 20 January 2023. The bellwether metal then spent the rest of the first quarter trying to
return to this peak, but after failing to scale its January heights, closed at US$8,933/t. As Kitco has pointed
out, copper has become a long-term critical metal, as the world upgrades its energy infrastructure and
transitions to green renewable energy. The metal of electrification, copper is essential to all energy
transition plans.
Commenting on copper’s outlook, analysts at ING said: "Longer-term, we believe copper demand will
improve amid the accelerated move into renewables and electric vehicles (EV). In EVs, copper is a key
component used in the electric motor, batteries and wiring, as well as in charging stations. Copper has
no substitutes for its use in EVs, wind and solar energy, and its appeal to investors as a key green metal
will support higher prices over the next few years."
Analysts at S&P Global expect global demand for copper to double by 2035. Demand growth will,
however, be suppressed into 2023, causing the refined market surplus to widen. “We expect the supply response
to lag, however, on a thinning pipeline caused by dwindling exploration budgets and a dearth of significant
discoveries,” S&P said.
Zinc prices followed copper’s example, scaling to US$3,509/t at the end of January 2023 after starting the
year at US$3,025/t. In 2022, zinc experienced its highest price volatility for a decade and analysts at Wood
Mackenzie expect heightened volatility to remain a feature throughout the year. Moody’s Investor
Service noted that while zinc prices will be supported by tight supply, low inventories and higher energy
costs will displace high-cost producers.
Regarding nickel, the ratings agency foresees a surplus of nickel in 2023 but points out that incremental
growth in demand from the electric vehicle market will create supply deficits. While nickel prices rallied
late in 2022, prices declined in the first quarter of 2023. Rising to US$32,100/t a day after the market opened
in 2023, nickel declined to close US$23,050/t by the end of March 2023 on expectations of easing supply
tightness. Data from the International Nickel Study Group shows a massive 22% year-on-year jump in
global nickel production in January 2023.
LME COPPER PRICES JANUARY 2023 – MARCH 2023
Source: London Metal Exchange
LME ZINC PRICES JANUARY 2023 – MARCH 2023
Source: London Metal Exchange
LME NICKEL PRICES JANUARY 2023 – MARCH 2023
Source: London Metal Exchange
Operations Report
Health and Safety, Community Engagement and Environmental Management
Health and Safety
No injuries were recorded during the Quarter and the hours worked for the Quarter and financial year to
date are shown in the table below:
Table 1: Hours worked at the Group’s Areachap and Okiep Copper Projects (South Africa).
Hours Worked
Category of Work
Quarter FY2023 YTD Total
Exploration --- 8,375
Surface 3,053 3,053
U/G Construction 8,880 29,892
Contractors 7,778 26,487
Total 19,711 67,807
The Lost-Time Injury Frequency Rate (LTIFR) per 200,000 hours worked is 0.0 for the Quarter.
At the end of the Quarter, the Prieska Copper-Zinc Mine (PCZM) team celebrated 153 shifts without an
injury and the Lost Time Injury (LTI) free days as at Quarter end was 1,327.
Community and Stakeholder Engagement
Orion community participation
The Siyathemba PCZM Task Team (Task Team) has developed a roadmap for the achievement of socio-
economic development and, more specifically, the aspirational host community employment and
procurement targets agreed at a Bosberaad in October 2021.
The Task Team was established to bring together PCZM and stakeholders in a spirit of collaboration, and
to foster good working relationships so that all stakeholders could collectively identify areas of socio-
economic development that would maximise value creation for all.
Comprised of host community representatives and business forums in the Siyathemba Local Municipality
and Vanwyksvlei areas, the Task Team met throughout 2022 to assess the capacity of the available host
community businesses and skill-sets, and to compare these to the future needs of PCZM during both its
construction and operational phases.
The roadmap is the bridge between what will be required by the mine and what host communities can
offer. It sets out the procurement, employment, training and development policies that will be
implemented by PCZM to facilitate the ultimate target of enabling community participation of 50% in
employment, 30% in the procurement of goods and services and 40% in sub-contracting opportunities at
the mine.
The resultant Task Team report was completed during the Quarter and has subsequently been distributed
to stakeholders including the attendees of the October 2021 Bosberaad, the Department of Mineral
Resources and Energy (DMRE), the office of the Premier of the Northern Cape Province, the Siyathemba
Local Municipality, the Orion management team and the Orion Siyahamba Stakeholder Engagement
Forum.
Orion remains committed to reaching the aspirational targets for host community participation and
upliftment.
Stakeholder Engagement Forum Site and Underground Visit
The Orion Siyathemba Stakeholder Engagement Forum participated in a visit to the PCZM site where they
were given firsthand insight into the plans and preliminary work completed in preparation for the early
dewatering and trial mining.
PCZM donates pecan nut trees to Prieska High School
PCZM has agreed to donate 200 pecan nut trees to Prieska High School to help promote agricultural
studies and education in the community. Over 20 trees were handed over in the first phase of the
donation. This will help to sustain funding at the school and educate the learners on the pecan nut value
chain. The school needs ZAR5 million just to sustain themselves and this will contribute to the critical
funding needed by the school.
The intention is that treated water from PCZM will be used for similar agricultural projects in the
communities immediately surrounding the mine.
Prieska High School is the only school in the area to offer agricultural studies as a subject and Orion is
committed to continuing its support for the advancement of education within its host communities.
PCZM installs a generator connection for the Siyathemba Local Municipality water pumps
PCZM has assisted the Siyathemba Local Municipality by providing technical support and the equipment
needed to connect a power generator to the local water pumps and reclamation plant.
The pumps require an uninterrupted power supply to ensure continuous water delivery. The connection
of the generator ensures that the community has access to running water during power outages and
load-shedding.
Orion is proud to assist its surrounding communities to ensure they have access to clean running water.
Orion facilitates sponsorship for community NPO to flourish
The Australian Trade and Investment Commission (Austrade), in collaboration with Orion, has facilitated
the sponsorship by Qantas of a return flight to Australia for Niekerkshoop community member, Zelna
Barends.
Zelna founded Zenisha’s Play and Learning Centre (ZPLC) in January 2017 to help children with Downs
Syndrome, Fetal Alcohol Syndrome and other intellectual disabilities by creating a supportive learning
environment where they can flourish.
Zelna, who has had very limited financial resources, has kept the centre running on donations and a
social grant. Together with a group of volunteers, she provides care for 8 children (5 of whom have
disabilities), runs an after-school program for 29 underprivileged learners, holds workshops for 22 adults
with disabilities, facilitates parent support sessions and runs outreach groups from a converted 12 metre
cargo container in her backyard.
State care for children with intellectual and learning difficulties, particularly those born with Fetal Alcohol
Syndrome, is virtually non-existent in towns outside of the major South African cities. In the Northern
Cape’s Siyathemba Municipality, ZPLC is still the only centre supporting children and adults with
intellectual and learning disabilities.
During her visit to Australia, Zelna will be given the opportunity to get exposure to community-based Fetal
Alcohol Syndrome centres and care programs, where she will share learnings and best practice and raise
funds in support of ZPLC and its expansion plans.
Orion is a previous donor to ZPLC and believes that Zelna’s work is truly inspirational and is something that
could be replicated in communities throughout Africa.
Orion publishes its Social and Labour Plan (SLP) for the SAFTA Mining Right
Orion has published the SLP for the SAFTA Mining Right covering the Flat Mines Project, part of the Okiep
Copper Project (OCP), near Nababeep. The SLP outlines Orion’s human resources, skills development and
local economic development plans for the mine.
Hard copies of the SLP are available for viewing at the Orion community liaison office in Springbok, as
well as at the public library and municipal office in Nababeep. The SLP can be downloaded via the Orion
website.
Environmental Management
Orion recognises that its environmental performance is a critical component of its success. The Company
strives to deliver the highest level of environmental compliance, with a commitment to monitoring and
managing the environmental impacts of its activities during and beyond the life of its operations.
There were no environmental incidents recorded during the March 2023 Quarter.
Prieska Mine Development and Exploration
Prieska Copper-Zinc Project Funding
Orion’s flagship Prieska Copper-Zinc Project (PCZM or Prieska Project) is transitioning to the mine
development and construction phase following the conclusion of the key elements of an overarching
strategic funding package. In March 2023, Orion announced a A$13 million two-tranche Share
placement, which led to the introduction of a new cornerstone investor, Clover Alloys (refer to ASX/JSE
release 15 March 2023).
Clover Alloys is a highly regarded mining group with significant mine development and operational
expertise, including a strong track record in the successful development and operation of modular,
capital efficient metal processing plants at its chrome mines in South Africa. This expertise will be
invaluable as Orion advances the development of its Prieska Project and OCP towards production. Orion
has also received support from existing long-term shareholders, the Delphi Group and Tembo Capital
Mining Fund II LP (Tembo Capital).
The placement includes a significant options package and, assuming all placement options are
ultimately exercised, the total value of the equity funding package amounts to ~A$73 million. This equity
funding, together with previously announced funding including the US$87 million funding package from
Triple Flag (refer ASX/JSE release 13 December 2022) and the ZAR250 million funding facilities secured
from the IDC (refer ASX/JSE release 8 February 2023), puts Orion in a strong position to execute its
accelerated development strategy in the Northern Cape.
Refer to the Corporate Section for further detail.
This funding package allows Orion to progress the development of PCZM, including the commencement
of trial mining and processing of ore, mine dewatering and the completion of feasibility studies for the
PCZM Early Production Scenario.
The PCZM Early Production Scenario, which was first announced in January 2022 (refer ASX/JSE release 20
January 2022), brings forward revenue generation and potentially reduces the upfront external peak
funding requirements by phasing the mine build while retaining the option to scale-up to the full-scale
project (as outlined in the Bankable Feasibility Study published in 2020, refer ASX/JSE release 26 May 2020)
as sufficient funding becomes available.
The recent capital raising, combined with other funding arrangements, also allows Orion to progress the
Feasibility Study, permitting and acceleration of early production at the OCP, the Company’s second,
advanced, near-term production asset in the Northern Cape. It also contributes to advancing
metallurgical processing and refining test work and feasibility studies for the Jacomynspan nickel-copper-
cobalt-PGE project, the Company’s third key asset in the Northern Cape.
Prieska Copper-Zinc Project Development
With its continued focus on operational readiness, Orion started small-scale dewatering at PCZM late in
2022 and plans are in place for the dewatering of the underground workings to start in Q2 CY2023 with
the commissioning of the first modules of its scalable system. The dewatering setup consists of a mine
dewatering and water treatment network, with a pumping rate that will build up from 120m 3/hr to
500m3/hr over time.
Small-scale dewatering, while limited to an average of 13m3/hr, has allowed Orion to conduct a series of
field trials for the treatment of mine water at PCZM. Using Rotowinner water treatment technology and
reverse osmosis, Orion aims to extract sodium hydroxide and iron oxide which are used in the chemical
industry. Calcium and magnesium could also be extracted and made available for use as agricultural
nutrients using the Rotowinner technology.
Construction of additional underground water storage in the form of water reticulation dams was
completed during the Quarter. This water will be used to mine the 105 Level when trial mining begins.
Trial mining will first target the +105 Level Crown Pillar using underground mining methods; with
development then moving into the remnant pillars. Trial mining support services were completed,
enabling equipment to be re-fuelled and serviced underground, close to the working ends.
Orion is in the process of procuring the required equipment and processing plant. The Company has been
engaging with various technical and turnkey process plant service providers for the supply of a 30ktpm
process plant to treat ore from the trial mining phase at PCZM.
Orion is also investigating the viability of sourcing and commissioning a low-capacity ore processing plant
(with crushing, milling, flotation concentration capacity) as part of the trial mining and processing
exercise. Several new and second-hand plants have been identified and are being assessed for suitability
and availability.
Orion and PCZM continue to engage with South Africa’s power utility, Eskom, and during the Quarter,
resubmitted an application for a 15MVA supply to support the first phase of PCZM development.
Prieska Copper-Zinc Project Exploration
An updated JORC, +105-level Crown Pillar Mineral Resource is expected in Q2 CY2023 after in-fill drilling
confirmed the presence of enriched copper mineralisation in the previously drilled supergene sulphide
mineralisation (refer ASX/JSE release 11 July 2022).
The interpretation of the mineral resource model has been updated, and the Mineral Resource will be re-
estimated and re-classified in terms of JORC Code (2012) where appropriate.
Okiep Copper Project Development and Exploration
Okiep Project Development
The bulk of the technical studies required for the OCP Feasibility Study were completed in 2022. Drafting
of the Feasibility Study report document and the completion of a few remaining technical studies were
the major workstreams undertaken during the Quarter. The finalisation of the Tailings Storage Facility
Design Report is the only remaining technical study outstanding and is nearing completion.
Environmental Management
Water Use Licence Application (WULA)
The Water-Use-Licence application Public Participation Process (in which participation in, and comment
on the draft Water and Waste Management Plan is invited from Interested and Affected Parties (I&AP))
closed during the Quarter in accordance with the specified timetable.
Comments and concerns were received from various parties which will be addressed by the
environmental consultants. Objections or additional concerns that were raised will be assessed and
mitigated in the final Water and Waste Management Plan and a section 21 application will be required
to be submitted. Of the concerns raised, a number had already been considered in the draft document
provided to the I&AP’s.
Phase II of the WULA process is in progress and Department of Water and Sanitation (DWS) officials are
now required to conduct a site visit early in April 2023 to conclude Phase II. Thereafter, the DWS will list the
technical documents that must be submitted with the WULA. Preparation of the documents typically
required is already at an advanced stage.
Results from the Radiological Risk Classification of flotation tailings and development waste rock have
confirmed no significant radiological risks exists.
Tailings Storage Facility (TSF)
As previously reported, the TSF is planned on an area previously impacted by prior mining operations.
Comprehensive geotechnical and geohydrological work has been undertaken on the TSF basin with a
view to installing an unlined TSF, as the tailings to be deposited in the TSF are benign in terms of the
leachable concentration thresholds for various elements as detailed in the Waste Management
Regulations. Recent decisions made by DWS in the permitting of unlined TSF designs for other mining
projects require that clarity be sought on the criteria for the approval of unlined facilities.
A meeting was held with DWS to discuss the TSF design options. Subsequent to this discussion, it was
concluded that the design of a partially lined facility would have a high probability of being permitted,
whereas a totally unlined design could be at risk of not being approved. This has resulted in additional
design work to accommodate the partial lining of the TSF basin. In parallel, additional test work has been
commissioned to investigate the option of neutralising the legacy paddy material and the suitability of
fine tailings for use in the inverted liner design. This additional work will be completed in Q2 CY2023.
Although the partial liner design is a compromise on the original design, the improved certainty in the
permitting of this design should result in the lowest permitting time required.
New Okiep Mining Company Permitting
No change in the status of the Mining and Prospecting Rights occurred in the Quarter:
• The SAFTA Mining Right application over the Flat Mines mining area was granted in July 2022. The
execution of the Mining Right was completed and registered in December 2022;
• SAFTA prospecting right applications over the areas contiguous to the Mining Right area are still
in process and no further news of these has been received from the authorities; and
• Land access discussions or negotiations with the landowners on the Mining Right and adjacent
prospecting right areas are continuing.
Mine Planning
Mining layouts and schedules have been finalised, taking into account recommendations from the
geotechnical engineer. The backfill study was updated to incorporate backfilling of the Flat Mine East
stopes following the finalised layouts.
Detailed capital and operating cost requirements for the Flat Mines Project have been completed and
the final mining study report is due for completion during Q2 CY2023.
Metallurgical Processing Plant
The conceptual design and costing of the processing plant to feasibility-level accuracy was completed
in the December 2022 Quarter. No further work in this area was undertaken during the Quarter.
Infrastructure
As reported in the December 2022 Quarter, plans for the provision of power and water to the Flat Mines
operations have been finalised and incorporated in the Feasibility Study Report. Layouts and cost
estimates for all the required offices, stores, change-houses, etc. for the mining operations have also been
concluded.
The mine has been collaborating with municipal leadership in efforts to rehabilitate the Nababeep
Wastewater Works, with the commitment that the mine will use the effluent water in the processing plant.
The Nama Khoi Municipality has secured funding from the National Government to undertake this project
which is due to commence in July 2023. The mine will take a keen interest in the refurbishing works to
ensure the effluent water will meet the required quality.
Land Access
As reported previously, access to the land on which the bulk of the surface mining infrastructure will be
located has been secured through a lease agreement with the local municipality. The Rezoning
application for mining use is in progress, subject to the completion of the Engineering Services Report. This
report can now be completed following the completion of the power supply design and resolution of the
Sewage Treatment Works Refurbishment Plan.
Negotiations with other key landowners are ongoing. Orion continues to negotiate in good faith with all
affected landowners to seek positive outcomes for all parties.
Community Liaison
Communications with the Nama Khoi Municipality Executive team continue to be regular and cordial.
Good progress has been made in forging common ground, particularly in the area of shared
infrastructure, as outlined above.
A Stakeholder Engagement Forum (SEF) meeting was held in March 2023, where the mine presented the
progress on planning for the roll-out of the Social and Labour Plan commitments (linked to the Mining
Right) for the first year, 2023.
Okiep Copper Project Exploration
Exploration activities continued with ongoing target generation over the OCP area. This included digital
compilation of historical drilling information over various old mines and prospects together with
remodelling of the mineralisation aimed at re-estimating the mineral resources. The current focus of this
work has been on the SAFTA Mining Right and contiguous prospecting right application areas, with the
objective of including additional prospects as JORC Mineral Resources in Q2 CY2023.
Notification of the grant by the DMRE of the prospecting right application to Orion Exploration No.6 (Pty)
Ltd, for an area north-east of the SAFTA Mining Right and prospecting right applications, was received
during the Quarter.
Areachap Near Mine Exploration
Areachap is an under-explored belt with multiple copper-zinc and nickel-copper-cobalt-PGE-gold
intrusive targets within Orion’s tenements. Chief among these are:
• The Prieska copper-zinc near mine, open pit and underground targets with high-grade
intersections;
• The Jacomynspan Project, with potential for sulphide nickel-copper-cobalt-PGE-gold open pit
and shallow underground mining. The Namaqua Nickel Mining Right, which was granted by the
DMRE in September 2016, was notarially executed with the DMRE in December 2022. The right has
been lodged for registration with the Mineral and Petroleum Titles Registration Office;
• Several high-grade copper-gold targets with historical and recent drill hole intersections; and
• Li, Be, Rare Earth Element opportunities are being investigated.
No exploration work was undertaken during the Quarter, however notifications of the grant by the DMRE
of three of the four Orion Minerals No. 5 (Pty) Ltd prospecting right applications in the ‘near-mine’ areas
adjacent to the PCZM project were received during the Quarter.
Australian Projects
Fraser Range – Nickel-Copper Projects (Western Australia)
The Fraser Range Project in Western Australia is highly prospective for high-value magmatic nickel-
copper-cobalt sulphide discoveries. Extending over a total strike distance of some 430km, the Fraser
Range Project tenements are held by IGO Limited (ASX: IGO), as well as through numerous joint ventures.
Orion maintains a sizeable tenement package in the Fraser Range under a joint venture with IGO. Under
the terms of the joint venture, IGO is responsible for all exploration of the tenements and provides regular
updates to Orion on activities and results. Orion is free-carried by IGO through to the first pre-feasibility
study on any of the tenements.
This allows Orion to maintain exposure to the ongoing exploration and development of the project,
without any ongoing financial commitment.
The mineral riches of the belt have been demonstrated at IGO’s Nova nickel-copper-cobalt operation
and other neighbouring discoveries including Silver Knight by the Creasy Group and Mawson by Legend
Mining.
During the Quarter, IGO undertook work on JV tenements E39/1653, E39/1654, E69/2379, E69/2707,
E28/2596, E28/2367, E28/2378 and E28/2462. Results were received for Pike North (E28/2367) and five
aircore holes totalling 507m were completed at Artemis target (E28/2367) with the sampling results also
received at Quarter end from the laboratory. The drilling program was planned to be eighteen holes, to
test the mafic and ultra-mafic intrusions however, due to weather conditions, difficulty in drilling and
potential risk during the seasonal bushfire period, the program was shortened.
IGO plans to undertake a moving-loop electromagnetic survey in the coming Quarter, to follow up on
the mafics intersected at the Artemis target.
Walhalla – Gold and Polymetals Project (Victoria)
While the Walhalla-Woods Point District is best known for gold mining, high-grade copper-nickel and PGE
mineralisation also occurs within the belt. Both the gold and copper-nickel-PGE mineralisation within this
district are hosted within dykes from the Woods Point Dyke Swarm, a series of ultramafic to felsic dykes
occurring over a 75km long north-south belt.
No field or exploration work was carried out on the Walhalla Project during the reporting period. During
the Quarter, the Company received notification of grant of two exploration licence applications in the
Walhalla area.
Corporate
Cash and Finance
Cash on hand at the end of the Quarter was A$12.18 million. Payments made to related parties and their
associates during the Quarter was A$158k for director fees and consulting fees, as listed in Section 6 of
the Company’s Quarterly Cash Flow Report (Appendix 5B).
Capital Raising
On 15 March 2023, Orion announced a capital raising of up to A$13 million through a two-tranche
placement to sophisticated and professional investors, pursuant to Section 708A of the Corporations Act
2001 (Cth) (Placement), comprising the issue of up to 882 million fully-paid ordinary shares (Shares) at an
issue price of 1.5 cents (ZAR18 cents) per Share, together with four free attaching options for each Share
issued on the principal terms set out below (Options).
The Placement will occur in two stages, being:
• Tranche 1: in March 2023, the Company issued 710 million Shares at an issue price of 1.5 cents
(ZAR18 cents), to raise A$10.7 million (Placement One). The Shares issued under Placement One
were issued without shareholder approval, using the Company’s 15% placement capacity under
ASX Listing Rule 7.1;
• Tranche 2: the Company has received commitments from investors to raise A$2.6 million through
the issue of 171 million Shares at an issue price of 1.5 cents (ZAR18 cents) per Share, including A$0.5
million from Orion non-executive Director Tom Borman, A$0.25 million from Orion’s Chairman Denis
Waddell, A$30k from Orion’s Managing Director & CEO Errol Smart and A$0.77 million from Tembo
Capital (which will be issued at the deemed offer price, in satisfaction of amounts to be repaid
by Orion under the Loan Facility (refer below)) (Placement Two). The issue of Shares under
Placement Two is subject to shareholder approval; to be sought at the General Meeting of
shareholders to be held on 19 May 2023 (refer below); and
• Placement Options: for every Share issued under the Placement, each investor shall receive four
free attaching Options. The issue of 3.5 billion Options to investors is also subject to shareholder
approval, to be sought at the General Meeting. The Placement Options have an exercise price
of 1.7 cents (ZAR20 cents) and an expiry date of 30 November 2023. The Options are not
transferrable and will not be quoted on the ASX or the JSE.
Tembo Capital – Convertible Loan Facility
On 3 January 2023, Orion announced that substantial shareholder Tembo Capital had continued its
strong support of Orion by providing a new unsecured convertible loan facility of US$0.50 million (~A$0.73
million) (Loan Facility). Under the terms of the Loan Facility, the amount outstanding (including capitalised
interest and fees) of ~A$0.77 million will be repaid by the issue of Shares to Tembo Capital at a deemed
issue price of the price per Share payable by investors under the Placement and on the same terms as
the Placement (including Placement Options) (subject to receipt of shareholder and regulatory
approvals).
Orion will also seek shareholder approval at the upcoming General Meeting for the issue of the Shares
under Tranche 2 of the Placement (together with the attaching Placement Options).
Prieska Project Funding
IDC - Convertible Loan
On 21 October 2022, Orion announced a pivotal non-binding term sheet with the IDC for a ZAR250 million
(~A$22 million) senior secured loan facility (IDC Convertible Loan) to fund early mining works and key pre-
development activities at the Prieska Project. Orion, Agama Exploration & Mining Proprietary Limited (a
wholly-owned subsidiary of Orion) (Agama) and PCZM (a majority-owned subsidiary of Orion) reached
agreement with the IDC on the key terms of the IDC Convertible Loan, which were recorded in a non-
binding term sheet (Term Sheet), with IDC Executive Committee approval.
Under the Term Sheet, the IDC will provide the ZAR250 million (~A$22 million) IDC Convertible Loan to
Agama, or its wholly-owned subsidiary, which will be on-lent to PCZM on similar terms to fund the
completion of the Feasibility Study for the previously-articulated Early Production Plan at Prieska (refer
ASX/JSE release 20 January 2022), while also allowing the Company to commence dewatering of the
existing underground mine – a critical path activity required for the broader long-term development of
the project. The Early Production Plan Feasibility Study and the Dewatering Project are key pre-
development workstreams that are already well advanced.
Definitive agreements were signed with the IDC in February 2023. The IDC Convertible Loan funding is
expected to be available for draw-down in Q2 CY2023, subject to fulfilment of conditions precedent and
draw-down conditions standard for such arrangements. Draw-down of the ZAR250 million Convertible
Loan will be in tranches and will be pro rata matched by the draw-down requests that Orion will make
under the A$10 million Triple Flag Funding Arrangement (refer ASX/JSE release 13 December 2022). A
summary of the material terms of the definitive agreement is provided in Appendix 1 of the 8 February
2023 ASX/JSE release.
Anglo American sefa Mining Fund - Loan
In November 2015, PCZM (a 70% owned subsidiary of Orion) and Anglo American sefa Mining Fund
(AASMF) entered into a ZAR14.25 million loan agreement for the further exploration and development of
the Prieska Project (Loan Facility). Under the terms of the Loan Facility, on 1 August 2017, AASMF
advanced ZAR14.25 million to PCZM. The key terms of the Loan Facility are:
• Loan amount: ZAR14.25 million (~A$1.19 million);
• Interest rate: Prime lending rate in South Africa; and
• Security: 29.17% of the shares held in PCZM by Agama (a wholly owned subsidiary of Orion), have
been pledged as security to AASMF for the performance by PCZM of its obligations in terms of the
Loan Facility.
As at 31 March 2023, the balance of the Loan Facility was ZAR23.6 million (~A$1.97 million) (including
capitalised interest). Funds received from the Placement will enable Orion to settle the outstanding
amount of the Loan Facility, thereby satisfying one of the key conditions precedent to draw-down of the
A$10 million Triple Flag early funding arrangement and the ZAR250 million IDC convertible loan facility.
OCP Okiep Copper Project Funding
IDC Shareholder Loan
In November 2022, Orion and the IDC entered into definitive agreements in terms of which the IDC
acquired 43.75% of the issued ordinary shares in New Okiep Mining Company Proprietary Limited (NOM)
and triggered pre-development funding arrangements for the Flat Mines area (Flat Mines Project) (refer
ASX/JSE release 7 September 2022).
Under the terms of the NOM memorandum of incorporation, the IDC funding of pre-development costs
in the aggregate amount of ZAR34.58 million will be advanced to NOM as a shareholder loan on the
same terms as the pre-development funding amount of ZAR44.46 million that Orion had already
advanced to NOM, including that the loan is unsecured, interest free until such time as the Flat Mines
Project commences commercial production and will be repaid when NOM is in a financial position to
make repayment.
Pursuant to the definitive agreements having been implemented and the IDC becoming a shareholder
in NOM, during the Quarter, the IDC advanced ZAR12.67 million (~A$1.06 million) of its pre-development
funding commitment and at Quarter end, the IDC had advanced ZAR34.58 million (~A$2.9 million) in
total.
General Meeting
A General Meeting of shareholders of the Company will be held at the offices of Clayton Utz,
Level 27, QV1 Building, 250 St Georges Terrace, Perth, Western Australia on Friday 19 May 2023,
commencing at 3:00 p.m. (Perth time).
At the General Meeting, the Company will seek the required shareholder approvals for the issue of Shares
under Tranche 2 of the Placement, the issue of all Placement Options, and the issue of Placement Shares
and Placement Options to Tembo.
Tenement Table
Ownership Change in
Tenement Project Joint Venture Partner
Interest Quarter
South Africa
NC30/5/1/1/2/11850PR
Bartotrax 100% --- ---
NC30/5/1/1/2/13528PR1
NC30/5/1/2/2/10138MR Prieska Copper-Zinc Mine 70% --- ---
NC30/5/1/2/2/10146MR Prieska Copper-Zinc Mine 70% --- ---
NC30/5/1/1/2/12258PR Prieska Near Mine 100% Granted ---
NC30/5/1/1/2/12287PR Prieska Near Mine 100% Granted ---
NC30/5/1/1/2/12405PR Prieska Near Mine 100% Granted ---
NC30/5/1/1/2/11840PR Doonies Pan 70% --- ---
NC30/5/1/2/2/10032MR Namaqua-Disawell 25% --- Namaqua Nickel Mining (Pty) Ltd
NC30/5/1/1/2/12216PR Namaqua-Disawell 25% --- Namaqua Nickel Mining (Pty) Ltd
NC30/5/1/1/2/10938PR
Namaqua-Disawell 25% --- Disawell (Pty) Ltd
NC30/5/1/1/2/13397PR1
NC30/5/1/1/2/11010PR
Namaqua-Disawell 25% --- Disawell (Pty) Ltd
NC30/5/1/1/2/13398PR1
NC30/5/1/1/2/12292PR Masiqhame 50% --- Masiqhame 855 (Pty) Ltd
NC30/5/1/1/2/12197PR Boksputs North 70% --- ---
NC30/5/1/1/2/11125PR
Okiep 100% --- ---
NC30/5/1/1/2/13395PR1
NC30/5/1/1/2/12357PR Okiep 100% --- ---
NC30/5/1/1/2/12897PR Okiep 70% Granted ---
Industrial Development Corporation
NC30/5/1/2/2/10150MR Okiep 56.25% ---
of South Africa Limited (IDC)
Western Australia
E28/2367 Fraser Range 30% --- IGO Limited
E28/2378 Fraser Range 30% --- IGO Limited
E28/2462 Fraser Range 30% --- IGO Limited
E28/2596 Fraser Range 30% --- IGO Limited
IGO Limited & Geological Resources
E39/1653 Fraser Range 35% ---
Pty Ltd
E39/1654 Fraser Range 10% --- IGO Limited & NBX Pty Ltd
Victoria
EL6069 Walhalla 100% Granted ---
EL5042 Walhalla 100% Granted ---
1 Renewal application reference number
This Quarterly Report is authorised by the Board.
26 April 2023
JSE Sponsor
Merchantec Capital
Date: 26-04-2023 09:03:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.