To view the PDF file, sign up for a MySharenet subscription.

ORION MINERALS LIMITED - September 2022 Quarterly Activities Report

Release Date: 28/10/2022 07:49
Code(s): ORN     PDF:  
Wrap Text
September 2022 Quarterly Activities Report

Orion Minerals Limited
Incorporated in the Commonwealth of Australia
Australian Company Number 098 939 274
ASX share code: ORN
JSE share code: ORN
ISIN: AU000000ORN1


September 2022 Quarterly Activities Report


HIGHLIGHTS

-  Funding terms agreed with South Africa’s Industrial Development Corporation (IDC), and recorded in
   a non-binding term sheet, in terms of which the IDC will advance ZAR250 million (~A$22 million) as a
   senior secured, convertible debt facility to fund early works at the Prieska Copper-Zinc Project.

-  The proceeds of the facility will be applied to mine dewatering and trial mining operations in order to
   complete the previously announced Early Production Plan for Prieska to Bankable Feasibility accuracy.

-  The IDC funding package also satisfies a key condition to the previously announced A$10 million Triple
   Flag Early Funding Arrangement, unlocking additional funding to support pre-development activities.

-  Innovative Electrosoftner/RotowinnerTM electrochemical water treatment and mineral extraction field
   trials commenced at Prieska.

-  The IDC agreed to become a strategic partner in the New Okiep Mining Company by funding ZAR34.6
   million (A$3.0 million) share of the pre-development costs and facilitating meaningful economic
   participation by Historically Disadvantaged South Africans, marking a key development milestone for
   the Okiep Copper Project.

-  Mining Right granted for the Flat Mines Area at the Okiep Copper Project, paving the way for the
   commencement of confirmation drilling and metallurgical sampling required to complete an
   advanced stage Feasibility Study.

-  A$6 million capital raising and A$1.35 million Share Purchase Plan (SPP) completed to fund the
   advancement of the Early Production Plan at Orion’s South African base metal projects. The SPP
   attracted strong support from shareholders, particularly those in South Africa.

Orion’s Managing Director and CEO, Errol Smart, said:
“Despite a challenging macro-economic backdrop, Orion has taken some important steps towards its
goal of establishing two world-class future-facing metals production hubs in South Africa’s Northern Cape.
The key highlight has been the strategic funding arrangements we have secured with South Africa’s
Industrial Development Corporation, both at our flagship Prieska Project and at our Okiep Copper Project
in the Northern Cape.

“Securing a strategic partnership with a quality partner such as the IDC represents a major vote of
confidence in Orion, the quality of our assets and the team we are building to take these projects to
production. It also helps secure our funding position over the next two years.

“The Prieska funding arrangement will allow us to finally get critical path pre-development work underway
– including the all-important mine dewatering project and a trial mining program on the +105-crown pillar,
to support the Bankable Feasibility Study on the Early Production Plan. Together with the previously
announced Triple Flag Funding Agreement, this represents a huge breakthrough for the Prieska Project,
and is welcome news for all our stakeholders. I would like to take this opportunity to thank the IDC for their
support, which is pivotal to our efforts to unlock both of our high-quality base metal hubs.”

“Orion is focused on the supply of future-facing metals to help the global transition to a lower carbon
future and we are striving to deliver ESG-certified metals that can be tracked via blockchain from
exploration to sale. It is this overarching vision that drives our activities and informs our decision-making.

“We are very pleased that, despite turbulent conditions in global markets, we have been able to attract
investment and support, both from existing shareholders and from new investors and strategic partners
who have underpinned our fund-raising efforts this Quarter.

“It is these investors who share our view that this is the right time to build new copper mines to meet the
surging demand requirement over the next decade and beyond as the world transitions to a low-carbon
future.

“As Orion moves ahead with its development and production plans, we have also begun the all-
important process of building our mining and operations team, with the addition of some high-quality
individuals that will drive our Company into the future.

“I am very pleased to see the huge progress that is being made across the business as we kick off
important pre-development activities. The Company is very quickly maturing from explorer-developer to
operating mining company and I’m excited to see what we can deliver in the months ahead.”


Commodity Markets

Base metals edged higher in the September Quarter as a number of positive trends re-emerged after the
challenging period experienced in the June Quarter which was dominated by inflationary pressures and
concerns over rising interest rates and the strengthening US Dollar.

Base metals’ bellwether, copper, was volatile with LME copper official prices ranging from US$7,000 per
tonne to US$8,315 per tonne during the Quarter which was well below its all-time high of US$10,700 per
tonne reached in March 2022. Copper started the Quarter at US$7,975 and closed at US$7,646 per tonne.
Zinc prices reached a three-month peak of US$3,877 per tonne in mid-August amid supply concerns and
nickel started and ended the Quarter at around US$22,000 per tonne after failing to break through
US$25,000 per tonne which it tested in the latter part of September 2022.

The longer-term outlook for base metals prices remains strong. Fitch Ratings noted that the higher metal
intensity of a green economy will result in a significant demand for energy transition metals like copper
and nickel. This has been echoed by the International Energy Agency, which estimates that a transition
to net-zero emissions by 2050 would require six times more metal inputs than today.

LME COPPER PRICES JULY 2022 – SEPTEMBER 2022
Source: London Metal Exchange

                                                                                                           
LME ZINC PRICES JULY 2022 – SEPTEMBER 2022
Source: London Metal Exchange


LME NICKEL PRICES JULY 2022 – SEPTEMBER 2022
Source: London Metal Exchange


Operations Report


Health and Safety, Environmental Management and Community Engagement

Health and Safety

No injuries were recorded during the Quarter. The hours worked for the Quarter and financial year to date
are shown below:

Table 1: Hours worked at the Group’s Areachap and Okiep Copper Projects (South Africa).

                                                            Hours Worked
                  Category of Work
                                                 Quarter                   FY2023 Total
                  Exploration                     8,039                       8,039
                  Mine Re-Entry                   12,666                     12,666
                  Contractors                     11,154                     11,154
                  Total                           31,859                     31,859


                                                                                                                
The Lost-Time Injury Frequency Rate (LTIFR) per 200,000 hours worked is 0 for the Quarter. The Company
continues to manage the risks from the COVID-19 pandemic in the workplace in line with government
and industry guidelines. During the Quarter, no COVID-19 cases or hospitalisations were reported.


Community and Stakeholder Engagement

Prieska Project - Task Team update: Focused workstreams

The Prieska Copper-Zinc Mine (PCZM) Task Team continued to engage during the Quarter and prepare
the roadmap of how Orion Minerals and host community businesses and other stakeholders will
collaborate to promote the increased participation of local businesses and the creation of more
employment opportunities in the Siyathemba Local Municipality and Vanwyksvlei areas.

It was agreed that the PCZM Task Team will be split into two focused work groups: one that will
concentrate on promoting local procurement and the other on promoting the employment of residents.
These work groups are assessing the capacity of host community businesses and available skill-sets and
comparing these to the future needs of the mine, both during its construction and operational phases.

They will then develop methods and interventions to bridge the gap between what will be required by
the mine and what the host communities have to offer. Orion remains committed to achieving the
aspirational targets for host community participation.


Okiep Project - Consultations continue with the Nama Khoi community

Community liaison and consultation has continued in the Nama Khoi District Municipality to inform the
community of the Company’s progress and intended work plans. The second meeting between Orion
and the Nama Khoi Stakeholder Engagement Forum (SEF) was held in September 2022, where the terms
of reference – which outline the rules that will govern how the Forum functions – were adopted.

The concept of the SEF being constituted from the officially elected community ward councillors only,
has been successful in managing the numerous approaches from business forums and other organisations
claiming to represent sectors of the Community

The Community Liaison Office in the town of Springbok, one of the key economic hubs in the municipality,
reopened in October 2022. Since the granting of the SAFTA Mining Right, there has been a sharp increase
in inquiries and interest in Orion Minerals and the community liaison office provides an important channel
for communication with host community stakeholders.


Orion keeps the wheels turning in its “Scholar Mobility” project

Orion continues to provide financial support to five locally based mechanics who conduct regular
maintenance and inspections on the pre-loved bicycles that were donated to schools across the Prieska,
Siyathemba and Vanwyksvlei areas.

The bicycles were donated by Bicycles for Humanity Western Australia (B4H) and were brought to Prieska
by Orion.

In collaboration with the principals of the nine schools, Orion is also currently monitoring the impact and
benefits that the bicycle project has had for the beneficiary scholars.


Environmental Management

Orion recognises that its environmental performance is a critical component of its success.

The Company strives to deliver the highest level of environmental compliance, with a commitment to
monitoring and managing the environmental impacts of its activities during and beyond the life of its
operations.

There were no environmental incidents recorded during the September Quarter.

                                                                                                         
Prieska Mine Development and Exploration

Prieska Copper-Zinc Project Development

A number of key workstreams progressed during the Quarter as part of formulating the Early Production
Plan for the Prieska Copper-Zinc Project (Prieska Project). The new plan is to bring forward revenue
generation and potentially reduce the upfront external peak funding requirements by phasing the mine
build while retaining the ability to scale up to a full-scale project as sufficient funding becomes available.

Leveraging off the information gathered, and material assumptions made in Orion’s 2020 Bankable
Feasibility Study (BFS-20), and supplemented by additional information obtained from recent drilling
campaigns and planned trial mining exercise, the Early Production Plan will comprise:

   •   A revised mine sequence to extract the mine’s crown pillar (+105 Level Crown Pillar), which
       currently sits above the accumulated water level, first using underground mining methods.
       Extraction of the +105 Level Crown Pillar was originally planned to occur at the end of the mine
       life using open pit mining. Mining the crown pillar upfront offers the potential advantage of earlier
       concentrate production and allows for dewatering to be undertaken at lower pumping rates and
       concurrently with early revenue generation from crown pillar mining;

   •   The potential opportunistic extraction of the mineralised pillars left behind from previous mining
       and located above the accumulated water level. Production from the remnant pillars could
       supplement the early mining and defer the need to access the Prieska Deeps Deposit;

   •   Commencing with dewatering of the underground workings using a modular configuration, with
       the first modules being commissioned in CY2022, at a third of the full-scale pumping rate proposed
       in the BFS-20 Plan and ahead of the project being fully-funded to commence full-scale
       construction; and

   •   Appending the deeper deposits, below the previously mined area, as a future expansion phase.

Orion is planning to proceed with trial mining as early as December 2022, targeting the +105-level Crown
Pillar first and developing into the remnant pillars starting in Q1 CY2023. Whilst preparations for early
dewatering are already under way, the whole pumping and water discharge system would be
commissioned by March 2023, subject to funding being in place. The Early Production Plan Bankable
Feasibility Study could then be ready by mid 2023, paving the way for a Final Investment Decision (FID)
and securing project funding.


Operational Readiness

During the Quarter, increased focus was placed on commencing the restructuring and recruitment of
personnel as part of augmenting the Company’s in-house expertise to include execution and operational
capabilities in preparation for the imminent migrating of both the Prieska and Okiep Copper Projects to
construction and operational phases.

An Executive Operations role has been created and filled, along with extensive recruitment of key roles
for the project operational team at the Prieska Project, including a Mining Manager, Engineering
Manager, Engineering Overseer, Safety Officer, Procurement and Logistics Coordinator, as well as
Finance and Administration support. Recruitment is being undertaken in line with the Company’s
uncompromising focus on a strong Environmental, Social and Corporate-governance focus,
capacitating for 4IR-enabled workforce and promoting host-community participation in employment
and enterprise opportunities.

Work has also progressed to enable the Company to initiate activities constituting the commencement
of mining operations during December 2022. This timetable will also be in line with Mining Right grant
conditions timing stipulations.

All requisite permits and licences to commence with mining operations are in place, though a number of
additional permissions are being sought to further improve the sustainability credentials of the project.
Amendments to the Integrated Water Use Licence (WUL) was applied for to facilitate the incorporation
of improved water treatment and secondary usage solutions to the current grant conditions. A decision
from the Department of Water and Sanitation is imminent. The amendments will allow for the
incorporation of solutions like the RotowinnerTM electrowinning process into the water management plan
that will result in water for agricultural use, valuable bi-products, and zero waste being generated from
mine dewatering and water treatment activities.

The Company has also applied for permission to allow for continuous operations if required, which will
provide more operational flexibility and rosters to better accommodate the various lifestyles of
employees, whilst running 24/7 operations.


Early Dewatering

Preparations to commence with early dewatering continued with underground dams now constructed,
the platform for staging pumps in the vertical shaft is in place, and surface preparations to receive the
pumped water are continuing. Commissioning of the full setup is planned for Q1 CY2023, subject to
funding availability.

The Early Dewatering setup, referred to as Project Metsi-ka-Pela (‘Water in-front’), consists of a mine
dewatering and water treatment network, with a pumping rate that will build up from 120m 3/hr to
500m3/hr over time. Full-scale dewatering in the original feasibility study was planned at 1,500m 3/hr. The
Early Dewatering setup is to be established in a modular form that allows the system to be scaled up
should the need arise, and sufficient funding becomes available.

The Metsi-ka-Pela underground pumping system will consist of:

    •   An initial working platform at the 178L, with pumps suspended from the 178L shaft station, down
        the Hutchings Shaft to a depth of 375m below surface;

    •   A newly constructed dam at the 163L as an underground reservoir; and

    •   Pipe reticulation up the Marais Shaft to the surface, to transfer water from the 163L dam into a
        system of storage tanks constructed from existing, re-purposed concrete thickener tanks.


The surface reticulation setup will consist of:

    •   A reverse osmosis (RO) plant or the RotowinnerTM electrosoftener system of water treatment before
        being discharged for evaporation or irrigation, dependent on the water qualities achieved from
        the water treatment;

    •   A purpose-built effluent storage pad to store RO concentrate (brine);

    •   Three options of discharging the treated water, these being:
            o   the historical TSF evaporation paddocks – for evaporation;
            o   the Storm Water Attenuation Dam – for evaporation; and
            o   the farm irrigation pivots - for the growing of animal feed such as lucerne.


Figure 1: Photos of preparations for dewatering at Prieska Copper-Zinc Mine.


Processing Update

There has been no change to the process plant design from the BFS-20 plan for the hypogene sulphide
portions of the Prieska Deposit. Processing routes developed by Mintek in 2018 include hypogene milling,
sequential copper (Cu) flotation, zinc (Zn) flotation, and ultra-fine grinding. However, opportunities exist
to improve on the processing route for the supergene sulphide portions of the deposit (+105L Crown Pillar).
Test work conducted for the BFS-20 plan did not progress to assess the advantages of Locked Cycle
flotation for the supergene sulphide ores.

The Locked Cycle flotation testing for hypogene samples achieved copper recoveries in the range of
75%-90% at a final concentrate grade of approximately 20%-26% copper. Zinc recoveries were in the
range of 84%-90% at a final concentrate grade of approximately 45%-54% zinc. This is in line with historical
recoveries when previous owners of the mine achieved over 86% recovery for both Cu and Zn with Cu
concentrate grades above 28% and Zn at 53% (refer to ASX/JSE release 26 May 2020). Test work is now
being progressed to assess the supergene recoveries from Locked Cycle testing. Results of this test work
will be incorporated into the Early Mining Plan.

Investigations are also progressing to source and commission a low-capacity ore processing plant (with
crushing, milling, flotation concentration capacity) as part of the trial mining and processing exercise. A
number of second-hand plants have been identified and are being assessed for suitability and
availability.


Prieska Project Funding Arrangements

IDC Convertible Loan

On 21 October 2022, Orion announced that it has entered into a non-binding term sheet with the Industrial
Development Corporation of South Africa Limited (IDC) for a ZAR250 million (~A$22 million) senior secured
loan facility (Convertible Loan) to fund early mining works and key pre-development activities at Prieska.
The proceeds of the Convertible Loan will support the completion of the Bankable Feasibility Study (BFS)
on the Early Production Plan, while also allowing the Company to commence dewatering of the existing
underground mine.

The BFS for the mining of the crown and remnant pillars down to the 385m level at PCZM (Early Mining
Works BFS) and the simultaneous commissioning and operating of pumping and water treatment
facilities, to allow dewatering of the PCZM mine at a rate ramping up to 500m 3 per hour (Dewatering
Project), are key pre-development workstreams that are already well advanced.

Refer to the Corporate Section for further detail.

Triple Flag Funding Package

In May 2022, Orion announced that it had signed non-binding term sheets with TF R&S Canada Ltd. and
Triple Flag International Ltd. (together Triple Flag), for a combined US$87 million secured funding package
for PCZM.

In addition to a US$80 million Precious Metal Stream, Orion and Triple Flag also entered into a term sheet
for a A$10 million early Funding Arrangement, with such funding to be made available to Orion to
complete the Early Mining Works BFS and to commence the Dewatering Project (refer ASX/JSE release 9
May 2022 for details of the Triple Flag Precious Metal Stream and Funding Arrangement).

The Funding Arrangement draw-down is conditional on to the completion of due diligence, entering into
definitive agreements and Orion securing an additional A$20 million funding to execute the agreed work
focused on the Dewatering Project and the Early Mining Works BFS.

Triple Flag has confirmed to Orion that draw-down of the IDC Convertible Loan will be sufficient for its
A$20 million funding condition to be satisfied. Orion and Triple Flag are advancing the definitive
agreements for the Precious Metal Stream and the Funding Arrangement and anticipate these being
finalised in Q4 CY2022.

The Convertible Loan, together with the Triple Flag A$10 million early Funding Arrangement, will enable
Orion to complete the Early Mining Works BFS and the commission and operate the Dewatering Project.
Orion and the IDC anticipate finalising and executing the definitive agreements for the Convertible Loan
in Q4 CY2022, with the IDC funding expected to be available for draw-down during late 2022, subject to
fulfilment of conditions precedent standard for such arrangements.

Refer to the Corporate Section for further detail.


Mine Water Treatment Trials – RotowinnerTM

Subsequent to Quarter-end, and as the Company advances the PCZM towards production, the
Company commenced a series of field trials for the treatment of mine water at PCZM, as preparations to
start dewatering of the underground mine and to implement other key elements of its Early Production
Plan continued.

The water treatment trials are being undertaken in collaboration with Free Radical Process Design (FRPD),
a South Africa-based technology company which has developed an innovative and proprietary process
and equipment for the continuous extraction of metals and other valuable minerals from water using
electrowinning via a rotating cathode (Electrosoftner).

The process has the potential to extract valuable products such as calcium and magnesium, for agri-
nutrient use from water pumped out of the underground mine at Prieska. In addition, other products with
potential for by-product sales in the chemicals industry will also be extracted by the process.

The Electrosoftner has the potential to extract iron hydroxide, hydrogen, calcium, magnesium and base
metals such as nickel, zinc and copper from contaminated mine waters. The ability to harvest the agri-
nutrients at the Prieska Project – which is located in a region where renewable energy is abundant and
where irrigation agriculture is a core industry – has the potential to offer important host-community
development opportunities.

The mine water treatment trials will advance Orion’s vision of establishing a ‘green’ footprint for the Prieska
Project, with broad stakeholder benefits as part of its objective to have a world-class ESG framework to
support its operations.

The commencement of the field trials follows the success of laboratory scale test work, where water
samples from PCZM were analysed and were passed through an Electrosoftner demonstration unit,
producing precipitates of iron hydroxide, calcium hydroxide/carbonate and magnesium hydroxide while
concentrating sodium hydroxide that can be bled off as a liquid from PCZM mine water.


Figure 2: Tailings remediation application of the RotowinnerTM process.


Additional sources of income and community support

While trial mining is underway, Orion also plans to investigate other sources of additional income with
some of these activities creating associated business opportunities for host communities to generate
income now and beyond the life of the mine.

Some potential income from products produced:

            •   Hydrogen, FeO, Ca/Mg & Ammonia (Green Fertilizer);

            •   Salvaging scrap from underground and surface;

            •   Running Alkantpan Lodge (accommodation);

            •   Growing lucerne using pumped water;

            •   Growing vegetables using pumped water;

            •   Fish farming (tilapia) using pumped water;

            •   Running stock feedlots;

            •   Production and sale of rock aggregate;

            •   Sell excess power from windfarm & solar; and

            •   Fuel station in Copperton for locals & farmers.


Prieska Copper-Zinc Project Exploration

105 Level Resource In-fill Drilling

Resource in-fill drilling of the +105 level crown pillar resource, required to support the Early Mining Scenario,
commenced in the March 2022 Quarter and was completed in July 2022. The drilling program was aimed
at providing enough data to upgrade the Inferred Mineral Resource portion of the +105 Level Crown Pillar
supergene sulphide Resource to Indicated classification (refer ASX/JSE release 20 January 2022).

Results have confirmed the presence of enriched copper mineralisation in the previously drilled
supergene sulphide mineralisation which is currently classified as an Inferred Resource due to the wider-
spaced drilling intersections (refer ASX/JSE release 11 July 2022).

The orebody model interpretation has been updated and the Resource will be re-estimated and re-
classified where appropriate with an anticipated updated JORC Resource in the December 2022
Quarter.

The updated Mineral Resource estimate will be used for optimisation of the mining plan and updated
Reserve estimation. Originally planned for mining by open pit after completion of the Deeps underground
mining, the +105 crown pillar Resource is now being evaluated for early mining from underground,
concurrent with the dewatering of the Deeps.


Okiep Copper Project Development and Exploration

Environmental Management

Water Use Licence Application (WULA)

The metallurgical test work program was completed in the Quarter, with the necessary flotation tailings,
ore sorting discard material and development waste samples available for further analysis.

Radiological Risk Classification of flotation tailings and development waste rock is now in progress and
results are expected in the December 2022 Quarter. The waste classification of the flotation tailings,
development waste rock and ore sorting discard material have been received, and recommendations
by the Environmental consultants are being drafted.

The additional percussion drilling downstream of the proposed tailings storage facility (TSF) embankment
wall requested by the hydrologist has been completed, with the aquifer testing Contractor expected on
site in the December 2022 Quarter. Further soil samples of the evaporation paddies from prior mining
operations have also been submitted for analysis to support the motivation for an unlined tailings facility,
in terms of the “risk-based approach” mentioned in earlier reports.

Tailings Storage Facility

The preliminary design of the TSF embankment wall constructed of waste rock from development and
ore sorting discard material has been completed. Geotechnical analysis of these materials is still
underway to confirm the compaction requirements during construction.

The testing of groundwater below the proposed TSF has shown that elevated sulphate levels exist in the
groundwater below the evaporation paddies placed in this area by prior mining operations understood
to be from around the 1950s. Early results from additional percussion drilling indicate that the extent of the
sulphate plume is limited, which supports our motivation for an unlined facility.

A small, lined storage facility is being investigated for the removal and storage of the paddy material to
prevent any further sulphate contamination of the groundwater from these, which will be seen as a
positive impact of the proposed TSF by the Water Affairs Authority.


Mine Planning

Optimisation of the mine layouts and scheduling has resulted in a significant reduction in waste
development requirements. Mining fleet selection has been completed and final development layouts
have been approved, allowing ventilation modelling for determination of main fan duties and exhaust
ventilation airway dimensions to get underway. Stope designs and sequencing have been submitted for
rock engineering evaluation and approval.

Decline development drilling, blasting and equipping have been defined and costed. Discussions are in
progress with explosives suppliers for the design of blasting systems applicable to the planned Vertical
Crater Retreat mining method envisioned.

Infrastructure

A 10 MVA Electricity supply point cost-estimate-letter from Eskom was received during the Quarter. The
letter outlines the cost of the next phase of Eskom Studies, the “Budget Quote” as well as the cost of the
connection and guarantees required by Eskom should the Eskom Option be selected. Although the long-
term cost of Eskom power to the project would be lower than from the Nama Khoi Municipality, the time
required for Eskom to process applications and approve “self-build” projects is a high risk to the
commencement of the Project, particularly for construction.

In parallel, discussions with the Nama-Khoi Municipal (NKM) leadership have been encouraging. A
steering committee including Orion and NKM Technical staff has been constituted and consultants
appointed to evaluate the upgrading requirements and design a supply solution. Eskom has been invited
to participate in the committee, which should benefit all parties.


Metallurgical Processing Plant

The metallurgical test work program, including milling and flotation of diamond core samples, has been
completed. Samples from Flat Mine North and Flat Mines South ore bodies were pre-sorted in a full-scale
sorter to simulate the upgraded material which will report to milling and flotation once production is
underway.

Milling and flotation optimisation tests indicated Copper recoveries of over 90% at concentrate grades
over 30% Cu are achievable. Milling Work-index-analysis on multiple samples produced Bond work indices
varying between 14 and 24 kWh/t. A design Bond Work Index of 24 has been adopted and an optimum
milled discharge particle size distribution of 80% minus 106 microns has been established. The necessary,
but relatively small alterations to the Process flow diagrams and Mill input power, have been made in
response to the test results.

Three dimensional plant layout drawings have been completed which formed the basis for requests for
quotations being submitted to selected OEM’s and engineering construction companies. Costs have
been received which has led to a review of portions of the Plant design in the interest of optimising the
design to reduce capital costs where possible.


Pre-development funding

In September 2022, Orion announced that the Industrial Development Corporation of South Africa (IDC)
would become a strategic partner in the development of OCP with the two parties anticipating the
finalisation of definitive agreements regarding the IDC share acquisition and pre-development funding
arrangements before the end of 2022 (refer ASX/JSE release 7 September 2022).

The strategic partnership will see the IDC take an initial 43.7% of the New Okiep Mining Company, which
holds the OCP assets, by funding ZAR34.6 million of OCP’s pre-development costs. Orion has already
advanced ZAR44.5 million in funding to New Okiep Mining Company.

The IDC will thereafter facilitate the attainment of Mining Charter BEE compliance, with the sale of a
22.22% stake to a corporate entity consisting of 100% Historically Disadvantaged Individuals led by Mr
Lulamile Xate, as the largest shareholder.

Orion’s aspiration, with project partners the IDC and BEE partners, is the early re-establishment of mining
operations on the brownfields SAFTA site while conducting the required work and engineering studies to
support the long-term aspiration of achieving production from the OCP at a similar scale to past owners
Newmont and later Goldfields under the Okiep Copper Company.

Refer to the Corporate section for further detail.


New Okiep Mining Company Permitting

Mining Right granted for Flat Mines area

The Mining Right over the Flat Mines Project area was granted to Southern African Tantalum Mining
(SAFTA) by the Department of Mineral Resources and Energy during the Quarter (refer ASX/JSE release 29
August 2022) (Figure 3). Orion is in the process of acquiring all of SAFTA’s mineral rights following exercise
of option in July 2021 to acquire certain assets in the selling companies. The Mining Right is valid for an
initial 15 years and can be renewed for a further period of up to 30 years.

The Mining Right will now need to be executed, which is an administrative process expected to be
completed within the December 2022 Quarter. The grant of the SAFTA Mining Right represents a major
step towards the development of the OCP and clears the way for final engineering studies, Mineral
Resource upgrade, drilling and bulk sampling for metallurgical optimisation.

Feasibility studies upgrading the 2021 scoping feasibility study (refer ASX/JSE release 2 August 2021) for
the OCP are well advanced, with targeted completion in early 2023.


Figure 3: Location of the OCP mineral rights and NOM - SAFTA Mining and Prospecting Rights.


The status of other permitting pertinent to the NOMC operations are as follows:

   •   Land access negotiations with the landowners in the Mining Right and adjacent Prospecting Right
       Areas are continuing; and

   •   SAFTA Prospecting Right Applications over the areas contiguous to the MRA area are still in
       progress.


Okiep Copper Project Exploration

Exploration activities continued with ongoing target generation over the Okiep Copper Project (OCP)
area using SKYTEM™ magnetic and EM data together with geological and structural interpretive work.

Digital compilation of historical drilling information over various old mines and prospects has continued,
together with the remodelling of the mineralisation with the aim of re-estimation the resources. The
current focus of this work has been on the SAFTA Mining Right and Prospecting Right areas with the aim
of inclusion of additional prospects as JORC resources in the December 2022 Quarter.


Areachap Near-Mine Exploration

Areachap is an under-explored belt with multiple Cu-Zn and Ni-Cu-Co-PGE-Au intrusive targets within
Orion’s mineral rights. Chief among these are:

   •   The Prieska Cu-Zn near the mine, open pit and underground targets with high-grade intersections;

   •   The Jacomynspan Mining Right with potential for sulphide Ni-Cu-PGE-Au open pit & shallow
       underground mining;

   •   Several high-grade Cu-Au targets with historical and recent drill intersections; and

   •   Several Li, Be, REE occurrences & old diggings to be investigated.


Jacomynspan Project and Metal Refining

The Jacomynspan Nickel-Copper-PGE Project (South Africa) (Jacomynspan Project) has the potential to
be a significant metals producer and Orion’s third strategic future metals project alongside the PCZM and
OCP.

Jacomynspan hosts a Mineral Resource of 65Mt at 0.28% Ni, 0.19% Cu, 0.02% Co, 0.2g/t 2PGE+Au using a
cut-off of 0.2% Ni. The Project has a granted Mining Right over a proven Ni-Cu-Co-PGE+Au Intrusive
Complex.

Orion sees compelling potential for a large scale, near surface bulk mining operation at Jacomynspan,
with drilling confirming the presence of shallow sulphide nickel-copper-cobalt-PGE mineralisation within
the ultramafic intrusive.

This work is being progressed in parallel with a metallurgical test work program to produce battery
precursor products and other critical metal micro-powders from Jacomynspan ore.
Orion signed an exclusivity agreement with Stratega Metals to undertake amenability test work on a
250kg sample of Ni-Cu-Co-PGE-Au concentrates from the Jacomynspan Project in the previous quarter
(refer ASX/JSE release 9 May 2022).

The amenability test work commenced during the Quarter, with positive visual observations during
laboratory tests indicated strong reaction kinetics and good mass recoveries to separated metal and
sulphur powders. Definitive results and detailed report are imminent with assay results expected to confirm
expectations of recoveries >95% of each metal to refined metal powder form.


Australian Projects

Fraser Range – Nickel-Copper Projects (Western Australia)

The Fraser Range Project in Western Australia extends over a total strike distance of some 430km. The
Project area is highly prospective for high-value magmatic nickel-copper-cobalt sulphide discoveries.

Orion maintains a sizeable tenement package in the Fraser Range Province of Western Australia in a joint
venture with IGO Limited (ASX: IGO). Under the terms of the joint venture, IGO is responsible for all
exploration of the tenements and provides regular updates to Orion on activities and results.

Importantly, Orion maintains exposure to the ongoing exploration and development of the Fraser Range
Project without the additional financial commitment, given that Orion is free-carried through to the first
pre-feasibility study on any of the tenements.

In the previous financial year, IGO developed several key targets at the Fraser Range Project, with work
including diamond and reverse circulation drilling (RC drilling) at more than 25 key targets.

IGO has budgeted $75 million to pursue its brownfields and greenfield projects with Fraser Range among
them (refer IGO presentation 30 August 2022).

During the Quarter, IGO completed 2km of rehabilitation works across E28/2367 and E28/2378, while
clearing and preparing track access for upcoming aircore program at Artemis (E28/267).

In the December Quarter 2022, IGO plans to undertake the following work (Figure 4):

   •   Drilling the Pike North diamond hole on E28/2367 (Kanandah Station):
        o   The Pike North diamond drill program is designed to test a 5000S 800m x 400m discrete
            conductor identified by MLEM in 2019. The conductor sits in a magnetic low, with aircore
            drilling in the area defining a broad geochemically anomalous zone, with the results
            indicating potential VMS and magmatic Ni sulphide anomalism. This target is offset and
            adjacent to the Boonderoo Shear Zone;

   •   Geological logging & DHEM;

   •   MLEM survey of CE, Pennor North and Porpoise target areas; and

   •   18 AC holes to be drilled at Artemis target on E28/2367 (Kanandah Station).


Figure 4: Future work to be completed on Orion JV tenure in Q2 FY23.


Walhalla – Gold and Polymetals Project (Victoria)

No field or exploration work was carried out on the Walhalla Project during the Quarter. During the
Quarter, the Company continued to progress its licence applications over prospective areas of Walhalla.


Corporate

Cash and Finance

Cash on hand at the end of the Quarter was $3.55 million. Payments made to related parties and their
associates during the Quarter was $99k and relates to Director fees and consulting fees, as listed in Section
6 of the Company’s Quarterly Cash Flow Report (Appendix 5B).

In order to preserve the Company’s cash reserves, the Company's Non-Executive Directors have agreed,
subject to Shareholder approval to be sought at the Annual General Meeting to be held on 24 November
2022, to receive their Director fees in ordinary fully paid shares (Shares), in lieu of cash. The deemed issue
price at which the Shares will be issued (subject to Shareholder approval) will be 2.0 cents, being the
same price as the Shares issued under the capital raising and SPP announced on 22 June 2022 (refer
below).


Prieska Project Funding

Industrial Development Corporation of South Africa Convertible Loan

On 21 October 2022, Orion announced that it has entered into a pivotal non-binding term sheet with the
Industrial Development Corporation of South Africa Limited (IDC) for a ZAR250 million (~A$22 million)
senior secured loan facility (Convertible Loan) to fund early mining works and key pre-development
activities at the Prieska Project. Orion, Agama Exploration and Mining Proprietary Limited (a wholly-
owned subsidiary of Orion) (Agama) and PCZM (a majority-owned subsidiary of Orion) have reached
agreement with the IDC on the key terms of the Convertible Loan, which have been recorded in a non-
binding term sheet (Term Sheet), with IDC Executive Committee approval.

Under this Term Sheet, the IDC will provide the ZAR250 million (A$22 million) Convertible Loan to Agama,
or its wholly-owned subsidiary, which will be on-lent to PCZM on similar terms to fund the completion of
the Bankable Feasibility Study (BFS) on the previously articulated Early Production Plan at Prieska (refer
ASX/JSE release 20 January 2022), while also allowing the Company to commence dewatering of the
existing underground mine – a critical path activity required for the broader long-term development of
the project. The Early Mining Works BFS and the Dewatering Project are key pre-development
workstreams that are already well advanced. The Dewatering Project is a critical long-lead item for the
development of the Prieska Project, given that total dewatering of the mine to facilitate access to the
main sulphide VMS orebody will take approximately three years.

A summary of the material terms of the Term Sheet are provided in Appendix 1 of the 21 October 2022
ASX/JSE release.


Triple Flag Funding Arrangements

In May 2022, Orion took a pivotal step towards the development of its flagship Prieska Project in South
Africa’s Northern Cape Province after signing non-binding term sheets with TF R&S Canada Ltd. and Triple
Flag International Ltd. (together Triple Flag), for a US$87 million secured funding package. Non-binding
term sheets have been signed with Triple Flag and are now being advanced under exclusivity to definitive
agreements, with the funding package planned to underpin the Early Production Scenario for the Prieska
Project announced in January 2022 (refer ASX/JSE release 20 January 2022).

The contemplated funding package comprises two components, being a precious metal stream
(Precious Metal Stream) and additional early funding (Funding Arrangement).

The Precious Metal Stream comprises US$80 million of funding to be drawn down in tranches, alongside
other bank and/or third-party funding during mine development. Orion will also receive payments of 10%
of the value of delivered payable precious metal paid at spot LME pricing at the time of delivery.

The proposed stream rates for gold and silver to be delivered under the stream agreement are 84% of
“Payable Gold” until 94.3k ounces of gold are delivered under the stream agreement, and 84% of
“Payable Silver” until 5,710k ounces of silver are delivered, with each stream rate reducing to 50% after
the respective milestones.

Orion and Triple Flag have also entered into a term sheet for an additional $10 million Funding
Arrangement, with such funding to be made available to Orion to complete the current early mining
Feasibility Study (refer ASX/JSE release 20 January 2022) and to commence dewatering of the mine.

In addition to the completion of due diligence and entering into definitive agreements, the Funding
Arrangement draw-down is also conditional on Orion securing an additional A$20 million funding to
execute the agreed work focused on the Dewatering Project and the Early Mining Works BFS. Triple Flag
has confirmed to Orion that draw-down of the IDC Convertible Loan will be sufficient for its A$20 million
funding condition to be satisfied. Orion and Triple Flag are advancing the definitive agreements for the
Precious Metal Stream and the Funding Arrangement and anticipate these being finalised in Q4 CY2022.
A summary of the material terms of the Precious Metal Stream and Funding Arrangement are provided
in Appendix 1 and 2 of the 9 May 2022 ASX/JSE release.


Next Steps

The IDC Convertible Loan, together with the Triple flag A$10 million early Funding Arrangement, will
enable Orion to complete the Early Mining Works BFS and commission and operate the Dewatering
Project.

Orion and the IDC anticipate finalising and executing the definitive agreements for the Convertible Loan
in Q4 CY2022, with the IDC funding expected to be available for draw-down during late 2022, subject to
fulfilment of conditions precedent standard for such arrangements.

The Early Mining Works BFS for the Prieska Project are well advanced, with targeted completion mid 2023.
The Dewatering Project is also well advanced, with underground storage dams and pump site
construction completed and the shaft platform installed to facilitate pump installation.

Refer to the Prieska Mine Development and Exploration (Prieska Project Funding Arrangements) section
for further detail.


Okiep Copper Project Funding

IDC share acquisition and pre-development funding

On 7 September 2022, Orion announced that it has entered into non-binding term sheets with the IDC
and Lulamile Xate regarding the key principles of the funding and Historically Disadvantaged South
African (HDSA) ownership participation arrangements for New Okiep Mining Company (NOM).

Orion and the IDC anticipate finalising and executing the definitive agreements for the IDC share
acquisition and pre-development funding arrangements in Q4 CY2022, with the IDC funding to flow in
the same Quarter, subject to fulfilment of conditions precedent standard for such arrangements.

Orion, the IDC and Lulamile anticipate finalising and executing the definitive agreements for the HDSA
ownership arrangements also in Q4 CY2022, with the implementation of the HDSA ownership
arrangements being conditional on the transfer of the assets from SAFTA to NOM, per the terms and
conditions of the SAFTA Asset Acquisition Agreement (refer ASX/JSE releases 2 February 2021 and 2 August
2021).

The IDC funding of pre-development costs in the amount of ZAR34.58 million will be advanced to NOM
on the same terms as the pre-development funding amount of ZAR44.46 million already advanced by
Orion to NOM.


Capital Raising

Placement

On 22 June 2022, the Company announced a capital raising to raise up to $20 million at 2.0 cents per
Share, to underpin the next phase of development of its portfolio of advanced base metal assets in South
Africa’s Northern Cape Province.

Given the significant volatility experienced in global financial markets since the time the capital raising
was announced in June 2022, the raising is being undertaken in three tranches with first commitments
received for the first two tranches (~$6 million). The three tranches of the placement are summarised
below:

   •   Tranche 1: in June 2022 and July 2022, the Company issued a total of 156 million Shares at an issue
       price of 2.0 cents (being ZAR22 cents) to raise $3.1 million (together with one free attaching
       unlisted option for each two Shares issued, with an exercise price of 2.5 cents (being ZAR27.5
       cents) and an expiry date of 30 June 2023 (Options)), using the Company’s 15% placement
       capacity under ASX Listing Rule 7.1;

   •   Tranche 2: the Company raised $2.9 million through the issue of 145 million Shares at an issue price
       of 2.0 cents (being ZAR22 cents) per Share (together with one free attaching Option for each two
       Shares issued on the terms set out above), including $2 million from Orion non-executive Director
       Tom Borman and $0.2 million from Orion’s Chairman Denis Waddell; and

   •   Tranche 3: the Company may issue up to an additional 699 million Shares at an issue price of 2.0
       cents (being ZAR22 cents) per Share to raise up to $14 million (shareholder approval received at
       a general meeting held on 18 August 2022). There are no Options attaching to any Shares that
       comprise Placement Three.


Share Purchase Plan

In addition to the capital raising announced on 22 June 2022, Orion also announced a share purchase
plan (SPP) providing shareholders an opportunity to increase their shareholding in the Company at the
same offer price as the Shares issued under the capital raising (refer above).

Under the SPP, Eligible Shareholders could subscribe for new Shares in parcels starting from $2,000 (or
ZAR20,000), up to a maximum of $30,000 (approximately ZAR330,000), at an issue price of 2.0 cents (ZAR22
cents) per Share, without incurring brokerage or transaction costs. The SPP opened on 28 June 2022 and
closed on 12 August 2022 and on 22 August 2022, the Company issued 67.3 million Shares under the SPP
at an issue price of 2.0 cents per Share (ZAR22 cents), raising $1.35 million.

The SPP attracted strong support from shareholders, particularly those in South Africa, which was a
pleasing result given the volatility experienced in global financial markets and commodity prices during
the SPP offer period.


Anglo American sefa Mining Fund – Loan

In November 2015, PCZM (a 70% owned subsidiary of Orion) and Anglo American sefa Mining Fund
(AASMF) entered into a ZAR14.25 million loan agreement for the further exploration and development of
the Prieska Project (Loan Facility). Under the terms of the Loan Facility, on 1 August 2017, AASMF
advanced ZAR14.25 million to PCZM. The key terms of the Loan Facility are:

   •   Loan amount: ZAR14.25 million (~$1.27 million);

   •   Interest rate: Prime lending rate in South Africa; and

   •   Security: 29.17% of the shares held in PCZM by Agama (a wholly owned subsidiary of Orion), have
       been pledged as security to AASMF for the performance by PCZM of its obligations in terms of the
       Loan Facility.

As at 30 September 2022, the balance of the Loan Facility was ZAR22.42 million (~$1.91 million) (including
capitalised interest). PCZM and AASMF are continuing negotiations to agree and settle a repayment
plan in relation to the Loan Facility.


Jacomynspan Project

In September 2017, Orion entered into a binding earn-in agreement to acquire the earn-in rights over the
Jacomynspan Project (South Africa) from two companies, Namaqua Nickel Mining (Pty) Ltd and Disawell
(Pty) Ltd (Namaqua Disawell Companies), which hold partly overlapping prospecting rights and mining
right applications.

In July 2020, the Company entered into an agreement whereby Orion (or its nominated subsidiary) will
acquire the remaining minority interests in the Jacomynspan Project held by the Namaqua Disawell
Companies and in August 2020, the parties entered into a comprehensive formal written agreement
incorporating the principal terms and conditions set out in the initial agreement (Agreement). The
Agreement is subject to the satisfaction or waiver of specified suspensive conditions. While certain
suspensive conditions have been fulfilled, the Agreement remains subject to the satisfaction or waiver of
certain remaining suspensive conditions of the Agreement, including that, on or before 27 February 2022,
all regulatory approvals as may be required for the purposes of implementing the transaction have been
received.

The Company and the other current shareholders in the Jacomynspan Project reached agreement to
extend the date by which the Agreement must become unconditional from 27 February 2022 to 30
September 2022. The extension provided additional time for the parties to discuss a potential expanded
and revised transaction whereby additional prospective Southern African nickel projects will be
combined with the Jacomynspan Project.

Following Quarter end, negotiations are continuing with term sheets currently being drafted.


General Meeting

A General Meeting of shareholders of the Company was held on 18 August 2022, with all resolutions put
to shareholders passed by a poll.

Annual General Meeting

The Annual General Meeting of shareholders of the Company will be held at the offices of Clayton Utz,
Level 27, QV1 Building, 250 St Georges Terrace, Perth, Western Australia on Thursday 24 November 2022,
commencing at 3:00 p.m. (Perth time).

Tenement Table
                                                      Ownership   Change in
 Tenement                  Project                    Interest    Quarter    Joint Venture Partner
                                                         
 South Africa

 NC30/5/1/1/2/11850PR      Bartotrax                    100%          ---     ---
 NC30/5/1/2/2/10138MR      Prieska Copper-Zinc Mine     70%           ---     ---
 NC30/5/1/2/2/10146MR      Prieska Copper-Zinc Mine     70%           ---     ---
 NC30/5/1/1/2/11840PR      Doonies Pan                  70%           ---     ---
 NC30/5/1/2/2/10032MR      Namaqua-Disawell             25%           ---     Namaqua Nickel Mining (Pty) Ltd
 NC30/5/1/1/2/12216PR      Namaqua-Disawell             25%           ---     Namaqua Nickel Mining (Pty) Ltd
 NC30/5/1/1/2/10938PR      Namaqua-Disawell             25%           ---     Disawell (Pty) Ltd
 NC30/5/1/1/2/11010PR      Namaqua-Disawell             25%           ---     Disawell (Pty) Ltd
 NC30/5/1/1/2/12292PR      Masiqhame                    50%           ---     Masiqhame 855 (Pty) Ltd
 NC30/5/1/1/2/12197PR      Okiep – Boksputs North        70%          ---     ---
 NC30/5/1/1/2/11125PR      Okiep                        100%          ---     ---
 NC30/5/1/1/2/12357PR      Okiep                        100%          ---     ---
 NC30/5/1/2/2/10150MR      Okiep                        100%       Granted    ---

 Western Australia

 E28/2367                  Fraser Range                 30%           ---     IGO Limited
 E28/2378                  Fraser Range                 30%           ---     IGO Limited
 E28/2462                  Fraser Range                 30%           ---     IGO Limited
 E28/2596                  Fraser Range                 30%           ---     IGO Limited
 E39/1653                  Fraser Range                 35%           ---     IGO Limited & Geological
                                                                              Resources Pty Ltd
 E39/1654                  Fraser Range                 10%           ---     IGO Limited & NBX Pty Ltd



This Quarterly Report is authorised by the Board.


28 October 2022


JSE Sponsor
Merchantec Capital


Date: 28-10-2022 07:49:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.