To view the PDF file, sign up for a MySharenet subscription.

ORION MINERALS LIMITED - Results Announcement: Annual Report for the year ended 30 June 2024

Release Date: 20/09/2024 09:26
Code(s): ORN     PDF:  
Wrap Text
Results Announcement: Annual Report for the year ended 30 June 2024

Orion Minerals Limited
Incorporated in the Commonwealth of Australia
Australian Company Number 098 939 274
ASX share code: ORN
JSE share code: ORN
ISIN: AU000000ORN1


RESULTS ANNOUNCEMENT: ANNUAL REPORT FOR THE YEAR ENDED 30 JUNE 2024


Orion Minerals Ltd (ASX/JSE: ORN) (Orion or the Company) is pleased to advise shareholders and investors
that it has today published its Annual Report for the year ended 30 June 2024, providing a comprehensive
overview of project development, exploration, corporate and ESG activities across its business for the 2024
financial year. The Annual Report can be accessed on the Company's website, www.orionminerals.com.au
and at the JSE cloudlink https://senspdf.jse.co.za/documents/2024/jse/isse/orne/ye24.pdf

HIGHLIGHTS:

•  Prieska Copper Zinc Mine (PCZM) development continued to advance on several fronts:

    o   An updated Mineral Resource Estimate was completed for the +105m Level Crown Pillar Block, with an
        increase in both tonnes and grade to 2.3Mt at 1.7% Cu and 1.6% Zn, including an increase in the +105
        Indicated Resource to 1.9Mt at 1.82% Cu and 1.70% Zn. The Prieska Copper Zinc Mine Total Mineral
        Resource has increased to 31Mt grading 1.2% Cu and 3.6% Zn.

    o   Trial mining of the Supergene orebody was successfully completed, providing key inputs for the
        updated Bankable Feasibility Study (BFS) for PCZM which is on track for completion in the December
        2024 quarter.

    o   Development of key infrastructure to support mining operations at PCZM is progressing on schedule:

        -   Upgrade of the Cuprum electrical sub-station completed for the supply of 15MVA to PCZM,
            providing sufficient power for dewatering and early mining operations to run simultaneously;

        -   Key underground portions of the PCZM mine dewatering mechanical and electrical infrastructure
            were successfully installed in June 2024, with the dewatering rate from the pump station at the
            178m Level achieving in excess of the required 500m3/hour; and

        -   All blasting required to construct the lined 13ha water storage dam/future tailings storage facility
            at PCZM was completed, with installation of key infrastructure to the water storage dam well
            advanced.

    o Phased development underway to facilitate early production and generate cash-flow, with the
      potential to reduce peak funding requirements and underpin a staged build-up towards achieving
      full-scale commercial production.

    o The Company received the Australia Africa Minerals & Energy Group (AAMEG) Emerging ESG Leader
      Award during the reporting period, which recognises Australian companies performing exemplary ESG
      work on the African continent. The award recognises the Group's work in successfully developing a
      host community service provider, Quebar Electrical and Civil Construction, which through mentorship
      and guidance from Orion, was able to increase the scope and complexity of its work and transitioned
      to become a core service provider in the fields of electrical and civil construction at PCZM, in both the
      surface infrastructure and underground mining environments.

    o PCZM achieved 50% host community representation in its labour force at the end of June 2024,
      employing a total of 103 community members out of a total of 206 on-site employees. Host community
      employees come from the communities of Prieska, Marydale, Vanwyksvlei and Niekerkshoop, filling
      various roles at the operation.

    o A significant proportion of PCZM's goods and services and subcontracting opportunities were
      awarded to local suppliers, with 69% of contracts awarded to businesses that are either based in, or
      employ labour from, the host communities of Siyathemba and Vanwyksvlei, and 31% to businesses
      located elsewhere in the Northern Cape.

•   Okiep Copper Project (OCP):

    o The first draft of the Flat Mines Project Bankable Feasibility Study Report was completed and submitted
      for independent expert (IE) review during the reporting period and is on track for completion in the
      December 2024 quarter.

    o In consultation with the IE review team, Orion drilled additional diamond drill holes into the Flat Mines
      East and South deposits to prove the reliability of the legacy exploration data to a standard which
      would be satisfactory to lenders.

    o Acquisition of 12,156 hectares of surface rights at the OCP, opening up new opportunities for
      exploration and validation drilling to materially enhance the OCP BFS.

    o Mineral Resource for the Flat Mines Area of OCP increased to 12Mt at 1.4% Cu for 160,000 tonnes of
      contained copper.

    o A zone of spectacular high-grade copper mineralisation previously reported by Goldfields was
      confirmed at Flat Mine East, with an intersection of 49.35m at 5.05% Cu.

    o The Integrated Water Usage Right for the Okiep Mine was granted in July 2024, making the Okiep Mine
      the second fully permitted copper mine development project in Orion's asset portfolio.

•   Jacomynspan Nickel-Copper-PGE Project (JMP):

    o Discussions are advancing with electric vehicle manufacturers as potential end-users of the metal
      vapour powder products to be produced using the innovative metal vapour refining technology
      (MVR).

    o Test work and desktop studies into application of MVR continued.

COMMENTARY:

During the reporting period, Orion successfully navigated a pivotal developmental stage, transitioning from
the exploration and feasibility study stage to become a mining company that is actively developing an
operational underground mine at the flagship Prieska Copper-Zinc Mine (PCZM).

The composition of the management and operations teams has evolved, with core mining, engineering,
technical services, logistics and administration teams assembled and operational contractor teams
successfully mobilised to site. Trial mining has commenced at PCZM, with copper ore from trial mining
currently being stockpiled on surface.

Orion reported an updated Mineral Resource Estimate for the +105 Block at PCZM early in the reporting
period. This Mineral Resource includes supergene and hypogene sulphides of 1.3m tonnes with a grade of
2.4% Cu and 2.1% Zn, for 30,000 tonnes of contained Cu and 27,000 tonnes of contained Zn. The +105 Block
Resource lies above the current water level of 269m and has been identified as an attractive early mining
opportunity focused on high-grade sulphide mineralisation. This will underpin the Company's near-term
mining development.

The first funding drawdown from the Industrial Development Corporation (IDC) and Triple Flag funding
facilities, which collectively total AUD33 million (~ZAR370M) for site establishment and trial mining, was
completed in early August 2023 and the final drawdown was received in September 2024.

Site preparation and site establishment for trial mining of the +105 Block commenced in August 2023 and the
program was completed in June 2024. The first development blast occurred in November 2023, with the
access ramp reaching the +105 Block at the 95m level in January 2024. Ore development is continuing to test
strike and dip extensions within the +105 Block.

Ore sourced from the trial mining will be used for metallurgical optimisation tests and the detailed design of
a modular sulphide concentrator plant. The data and results will feed into the Early Production Plan and
revised Life of Mine Bankable Feasibility Study, which is on-track for completion in the December 2024 Quarter.

Significant progress was achieved for site establishment works, including site offices, workshops, roadways,
laboratory, and sampling crusher, with bulk diesel storage of 90,000 litres installed and commissioned. Blasting
of the 13ha water storage dam was completed in June 2024 and construction of the embankment walls has
commenced.

At the Okiep Copper Project (OCP), Orion is finalising the Bankable Feasibility Study for the Flat Mines Area,
with ongoing review by independent experts appointed by the debt advisor. The Bankable Feasibility Study
is on-track for completion in the December 2024 Quarter Land access negotiations were concluded in
January 2024 resulting in Orion acquiring 12,156ha of key surface rights including the intended initial mining
area at Flat Mines. This provided Orion with access to previously inaccessible sites to undertake a validation
drilling program, to verify the historical data that underpinned the Mineral Resource Estimates at the Flat
Mines East (FME), North (FMN) and South (FMS) deposits and to further de-risk the study.

The initial diamond drilling program commenced in the Flat Mines Area of OCP in February 2024, comprising
five holes at FME, four holes at FMS and two holes at FMN. All holes included a deflection (or wedge) drilled
through the mineralisation to provide additional material for confirmatory metallurgical test work.

Results from diamond drilling at FME included 49.35m at 5.05% Cu including 21.66m at 9.41% Cu in OFMED153
and 9.27m at 3.01% Cu and 15.00m at 4.80% Cu within 78.00m at 1.57% Cu in OFMED154 (refer ASX/JSE
releases 22 April 2024 and 24 June 2024).

A second confirmation diamond drilling program commenced during June 2024, with seven holes planned
at Flat Mine Nababeep.

The Integrated Water Usage Right for the Okiep Mine was granted in July 2024, making the Okiep Mine fully
permitted and ready for mine development.

At the Jacomynspan Nickel-Copper-Cobalt-PGE Project (JMP), planning for a trial mining program to support
pilot scale metallurgical test work programs is progressing well. Laboratory scale test work to confirm
amenability of the Jacomynspan sulphide concentrate to Metal Vapour Refining Technology is delivering
pleasing results.

Orion strives at all times to achieve a sustainable balance between intense operational effort and
maintaining a strong focus on safety, environment and community.

In addition, the following information is provided in accordance with paragraph 3.46 of the JSE Listings
Requirements:

•   Operating loss decreased to a loss of AUD7.94 million (30 June 2023: operating loss of AUD17.13 million).

•   Basic loss per share improved by AUD0.22 cents to AUD0.09 cents (30 June 2023: basic loss per share of
    AUD0.31 cents).

•   Headline loss per share improved by AUD0.22 cents to AUD0.09 cents (30 June 2023: headline loss per
    share of AUD0.31 cents).

The operating loss for the reporting period was primarily driven by exploration expenditure of AUD4.24 million
(which, under Orion's deferred exploration, evaluation and development policy, did not qualify to be
capitalised and was expensed), contractor, consultants and advisor expenses of AUD2.4 million, a net
unrealised foreign exchange loss of AUD2.0 million, and finance income of AUD4.37 million, principally related
to interest receivable on the Company's investment in preference shares issued to the Company (through its
subsidiary Agama Exploration & Mining (Pty) Ltd) by Prieska Resources (Pty) Ltd. The operating loss for the
previous corresponding period reflected an unrealised foreign exchange loss of AUD9.37 million and
exploration expenditure of AUD4.13 million.

RESULTS ANNOUNCEMENT:

This results announcement is the responsibility of the directors and is only a summary of the information in the
Annual Report.

Orion Minerals Limited has a primary listing on the Australian Securities Exchange (ASX) and a secondary
listing on the Main Board of the Johannesburg Stock Exchange (JSE).

Any investment decisions by investors and/or shareholders should be based on a consideration of the Annual
Report as a whole (which includes the full unmodified auditor's report and going concern opinion from Forvis
Mazars Audit & Assurance Pty Ltd, setting out, inter alia, the key audit matters) and investors and shareholders
are encouraged to review the Annual Report, which is available as detailed herein. Copies of the Annual
Report may also be requested from the Company via email at info@orionminerals.com.au or from the sponsor
at sponsorteam@merchantec.com, at no charge.


For and on behalf of the Board.


Errol Smart
Managing Director & CEO

20 September 2024


ENQUIRIES

Investors                                    Media                                       JSE Sponsor
Errol Smart – Managing Director & CEO        Nicholas Read                               Monique Martinez
Denis Waddell – Chairman                     Read Corporate, Australia                   Merchantec Capital
T: +61 (0) 3 8080 7170                       T: +61 (0) 419 929 046                      T: +27 (0) 11 325 6363
E: info@orionminerals.com.au                 E: nicholas@readcorporate.com.au            E: monique.martinez@merchantec.com




 Disclaimer

 This release may include forward-looking statements. Such forward-looking statements may include, among other things,
 statements regarding targets, estimates and assumptions in respect of metal production and prices, operating costs and
 results, capital expenditures, mineral reserves and mineral resources and anticipated grades and recovery rates, and are
 or may be based on assumptions and estimates related to future technical, economic, market, political, social and other
 conditions. These forward-looking statements are based on management's expectations and beliefs concerning future
 events. Forward-looking statements inherently involve subjective judgement and analysis and are necessarily subject to
 risks, uncertainties and other factors, many of which are outside the control of Orion. Actual results and developments
 may vary materially from those expressed in this release. Given these uncertainties, readers are cautioned not to place
 undue reliance on such forward-looking statements. Orion makes no undertaking to subsequently update or revise the
 forward-looking statements made in this release to reflect events or circumstances after the date of this release. All
 information in respect of Exploration Results and other technical information should be read in conjunction with
 Competent Person Statements in this release (where applicable). To the maximum extent permitted by law, Orion and
 any of its related bodies corporate and affiliates and their officers, employees, agents, associates and advisers:
 •     disclaim any obligations or undertaking to release any updates or revisions to the information to reflect any change
       in expectations or assumptions;
 •     do not make any representation or warranty, express or implied, as to the accuracy, reliability or completeness of
       the information in this release, or likelihood of fulfilment of any forward-looking statement or any event or results
       expressed or implied in any forward-looking statement; and
 •     disclaim all responsibility and liability for these forward-looking statements (including, without limitation, liability for
       negligence).

Date: 20-09-2024 09:26:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.