To view the PDF file, sign up for a MySharenet subscription.

ANGLOGOLD ASHANTI LIMITED - AngloGold Ashanti Provides Update on Resumption of Underground Ore Mining at Obuasi

Release Date: 30/09/2021 08:30
Code(s): ANG     PDF:  
Wrap Text
AngloGold Ashanti Provides Update on Resumption of Underground Ore Mining at Obuasi

AngloGold Ashanti Limited
(Incorporated in the Republic of South Africa)
Reg. No. 1944/017354/06
ISIN: ZAE000043485 – JSE share code: ANG
CUSIP: 035128206 – NYSE share code: AU
(“AngloGold Ashanti”, “AGA” or the “Company”)

NEWS RELEASE

AngloGold Ashanti Provides Update on Resumption of Underground Ore Mining at
Obuasi

(JOHANNESBURG) – PRESS RELEASE - AngloGold Ashanti announces that underground
ore mining at the Obuasi Gold Mine in Ghana is expected to resume by mid-October.

For the remainder of this year, underground ore will be used only to replenish the Run-of-Mine
stockpile. Gold production from underground ore sources is therefore expected to re-
commence only in January 2022. The safe ramp up to the full mining rate of 4,000 tons per
day is expected to be achieved by the end of the first half of the 2022.

Underground mining activities at Obuasi were voluntarily suspended following a sill pillar
failure on 18 May 2021 which resulted in the tragic loss of one of our colleagues. A detailed
review of the mining and ground management plans has been conducted by a cross-functional
internal team and supported by independent third-party, Australian Mining Consultants (AMC).

Following this review, a comprehensive series of protocols has been introduced to supplement
existing operating procedures. The full suite of procedures ahead of the mining front now
include the existing systematic probe drilling procedure, extensive use of technology, including
Cavity Monitoring Systems and Cavity Auto Laser System, augmented with visual inspections
to confirm the position and status of backfill in previously mined areas. The new paste-fill plant
has been commissioned and its reticulation system is expected to be completed by the end of
this year.

These protocols, which have been integrated into the Mine Operating System, will be bolstered
by scheduled audits to ensure the accuracy and diligence in probe drilling, and the intended
implementation of the revised plan. AMC will continue its review of future mining areas.
During the review period, underground development and work related to the Obuasi
Redevelopment Project continued to progress, with Phase 2 construction substantially
complete at the end of June 2021.

Phase 3 of the project, which relates principally to extended capital expenditure to refurbish
existing infrastructure around the KMS Shaft, as well as to service the mine in deeper
production areas, has progressed during this period and will continue as planned through to
the end of 2023.

AngloGold Ashanti’s annual revised guidance for 2021 remains unchanged and assumes no
gold production contribution from Obuasi for the remainder of this year. It is estimated that the
supplementary operating procedures introduced following the review will add about $10 to $20
per tonne to the mine’s operating costs, or about $50/oz. There is no material change to the
mine plan or to Obuasi’s published Ore Reserve and Mineral Resources.

Production for 2022, as the mine ramps up, is estimated to be about 240,000oz – 260,000oz
at an all-in sustaining cost of approximately $1,250/oz to $1,350/oz, and with cash costs of
$900/oz to $1,000/oz.*

We estimate that in the fourth quarter of next year, the annualized production rate will be about
320,000oz to 350,000oz a year, and we expect that the annual production will remain at
around that level in 2022 and 2023 until the completion of Phase 3 in Q4 2023, which we
estimate will allow the mining rate to achieve the planned step-up to 5,000 tonnes per day.

With all three phases of the project complete, production from 2024 to 2028 is anticipated to
average 400,000oz to 450,000oz at an all-in sustaining cost of $900/oz to $950/oz.

About Obuasi

Obuasi Gold Mine is one of the world’s largest gold ore bodies, with 29.5Moz of Mineral
Resource, at an average grade of 7.64 grams per tonne and 8.7Moz of Ore Reserve at an
average grade of 8.6 grams per tonne.

Obuasi, an underground operation, mining to a depth of 1,500m, is in the Ashanti region,
approximately 60km south of Kumasi. The mine currently employs 850 staff and 3,360
contractors, with about 97.5% of all positions filled by Ghanaians.

Obuasi was in limited operations in 2015, and on care and maintenance from 2016 to the start
of its redevelopment in mid-2018, following the receipt of the requisite approvals from the
Government of Ghana. The first face blast took place in February 2019 with first gold poured
in December 2019.

Phase 1 of the redevelopment project was completed by end September 2020 and began
commercial production on 1 October 2020. Phase 2, construction and mine development was
substantially completed at the end of June.

The Company has an active youth apprenticeship programme, with graduated 55 young
artisans last year and another 80 enrolled in 2021. In addition, 13 people are currently enrolled
in its graduate trainee programme. AngloGold Ashanti facilitated the opening in 2019 of the
Obuasi campus of Ghana’s renowned Kwame Nkrumah University of Science and Technology
(KNUST), through the provision of campus buildings and accommodation for staff and
students. The satellite campus now has 1,000 students enrolled in a number of Bachelor of
Science courses.

Local businesses are prioritised in Obuasi’s supply chain, with more than 80% of the total
investment in the mine’s redevelopment spent in Ghana, split evenly between wholly
Ghanaian owed businesses and multinationals registered in Ghana. The support of local
businesses is a key strategic objective for the Company, and 100 small and medium sized
businesses have been trained and certified through the Company’s Enterprise Development
Programme.

AngloGold Ashanti’s malaria control programme in the Obuasi area is one of the continent’s
most successful public health initiatives, with a 90% reduction in malaria cases since the
intervention started in 2005. We work with the Global Fund on this malaria programme,
extending to 16 districts in Ghana, protecting more than one million people. This has led to a
significant drop in related school as well as work absenteeism and creates more than 1,300
seasonal community jobs each year.
The mine has played a key role in the fight against COVID-19 in the Obuasi area, providing
healthcare facilities for the community as well as personal protective equipment, sanitiser,
handwashing facilities and public education to help contain the virus outbreak.

ENDS

Johannesburg
30 September 2021

JSE Sponsor: The Standard Bank of South Africa Limited

 Contacts
 Media
 Chris Nthite                +27 83 301 2481                                 cnthite@anglogoldashanti.com
 Julie Bain                  +27 663 640 038                                 jbain@anglogoldashanti.com
 General inquiries                                                           media@anglogoldashanti.com

 Investors
 Sabrina Brockman            +1 646 880 4526/ +1 646 379 2555 sbrockman@anglogoldashanti.com
 Yatish Chowthee             +27 11 637 6273 / +27 78 364 2080 yrchowthee@anglogoldashanti.com
 Fundisa Mgidi               +27 11 637 6763 / +27 82 821 5322 fmgidi@anglogoldashanti.com


*Production and cost forecast ranges are expressed in nominal terms. In addition, production and cost estimates
assume neither operational nor labour interruptions and have not been reviewed by our external auditors. Other
unknown or unpredictable factors could also have material adverse effects on our future results and no assurance
can be given that any expectations expressed by AngloGold Ashanti will prove to have been correct. Measures
taken at our operations together with our business continuity plans aim to enable our operations to deliver in
line with our production targets. We, however, remain mindful that the COVID-19 pandemic, its impacts on
communities and economies, and the actions authorities may take in response to it, are largely unpredictable.
Actual results could differ from guidance and any deviation may be significant. Please refer to the Risk Factors
section in AngloGold Ashanti’s annual report on Form 20-F for the year ended 31 December 2020 filed with the
United States Securities and Exchange Commission (SEC).

Certain statements contained in this document, other than statements of historical fact, including, without
limitation, those concerning the economic outlook for the gold mining industry, expectations regarding gold
prices, production, total cash costs, all-in sustaining costs, all-in costs, cost savings and other operating results,
return on equity, productivity improvements, growth prospects and outlook of AngloGold Ashanti’s operations,
individually or in the aggregate, including the achievement of project milestones, commencement and
completion of commercial operations of certain of AngloGold Ashanti’s exploration and production projects and
the completion of acquisitions, dispositions or joint venture transactions, AngloGold Ashanti’s liquidity and
capital resources and capital expenditures and the outcome and consequence of any potential or pending
litigation or regulatory proceedings or environmental health and safety issues, are forward-looking statements
regarding AngloGold Ashanti’s operations, economic performance and financial condition. These forward-
looking statements or forecasts involve known and unknown risks, uncertainties and other factors that may cause
AngloGold Ashanti’s actual results, performance or achievements to differ materially from the anticipated
results, performance or achievements expressed or implied in these forward-looking statements. Although
AngloGold Ashanti believes that the expectations reflected in such forward-looking statements and forecasts are
reasonable, no assurance can be given that such expectations will prove to have been correct. Accordingly, results
could differ materially from those set out in the forward-looking statements as a result of, among other factors,
changes in economic, social and political and market conditions, the success of business and operating initiatives,
changes in the regulatory environment and other government actions, including environmental approvals,
fluctuations in gold prices and exchange rates, the outcome of pending or future litigation proceedings, any
supply chain disruptions, any public health crises, pandemics or epidemics (including the COVID-19 pandemic),
and other business and operational risks and other factors, including mining accidents. For a discussion of such
risk factors, refer to AngloGold Ashanti’s annual report on Form 20-F for the year ended 31 December 2020, filed
with the United States Securities and Exchange Commission (SEC). These factors are not necessarily all of the
important factors that could cause AngloGold Ashanti’s actual results to differ materially from those expressed
in any forward-looking statements. Other unknown or unpredictable factors could also have material adverse
effects on future results. Consequently, readers are cautioned not to place undue reliance on forward-looking
statements. AngloGold Ashanti undertakes no obligation to update publicly or release any revisions to these
forward-looking statements to reflect events or circumstances after the date hereof or to reflect the occurrence
of unanticipated events, except to the extent required by applicable law. All subsequent written or oral forward-
looking statements attributable to AngloGold Ashanti or any person acting on its behalf are qualified by the
cautionary statements herein.
The information contained in this announcement has not been reviewed or reported on by AngloGold Ashanti’s
external auditors.
Non-GAAP financial measures
This communication may contain certain “Non-GAAP” financial measures. AngloGold Ashanti utilises certain
Non-GAAP performance measures and ratios in managing its business. Non-GAAP financial measures should be
viewed in addition to, and not as an alternative for, the reported operating results or cash flow from operations
or any other measures of performance prepared in accordance with IFRS. In addition, the presentation of these
measures may not be comparable to similarly titled measures other companies may use.

Website: www.anglogoldashanti.com

Date: 30-09-2021 08:30:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story