To view the PDF file, sign up for a MySharenet subscription.

MC MINING LIMITED - Phase 1 of the Makhado Project approved

Release Date: 14/03/2019 09:00
Code(s): MCZ     PDF:  
Wrap Text
Phase 1 of the Makhado Project approved

MC Mining Limited
Previously Coal of Africa Limited
(Incorporated and registered in Australia)
Registration number ABN 008 905 388
ISIN AU000000MCM9
JSE share code: MCZ
ASX/AIM code: MCM




ANNOUNCEMENT                                                                      14 March 2019

PHASE 1 OF THE MAKHADO PROJECT APPROVED

MC Mining Limited ("MC Mining" or the “Company") is pleased to announce the development of its
flagship Makhado hard coking and thermal coal project (“Makhado Project” or “Makhado”) through
a phased approach. All numbers are in South African rand or United States dollars.


Key highlights
•   Phase 1
        o     Construction to commence in Q3 CY2019 if all conditions satisfied
        o     nine-month construction period
        o     commence mining at west pit producing ~3.0 million tonnes per annum (“Mtpa”) of run-
              of-mine (“ROM”) coal
        o     ROM coal partially beneficiated prior to despatch to the modified Vele Colliery for
              processing
        o     ~2.0Mtpa ROM coal (ex-discard) trucked to Vele Colliery
        o     ROM coal processed at enhanced Vele plant
        o     ~1.1Mtpa of saleable coal produced (at steady state):
                  -   ~0.54Mtpa of hard coking coal (“HCC”)
                  -   ~0.57Mtpa of 5,500kcal thermal coal
        o     hard coking and thermal coal trucked to Musina siding for railing to domestic and/or
              export customers
        o     internal rate of return (“IRR”) in excess of 45%
        o     peak funding payback of less than 2.5 years
•   Phase 2
        o     Makhado Lite plan implemented as Phase 2 in circa FY2022
        o     development and mining of east pit, Makhado processing plant and related infrastructure



Background

The Company effectively owns 69% of Baobab Mining & Exploration (Pty) Ltd (“Baobab”), the owner
of the Makhado Project, the balance being and/or to be held by the Industrial Development
Corporation of South Africa Limited (“IDC”), seven communities located in the vicinity of Makhado
and a black industrialist. The development of Makhado will provide significant direct and indirect
benefits to these communities located in one of the poorest areas of South Africa.

MC Mining previously announced the Makhado ‘Lite’ project plan, producing 4.0Mtpa of ROM coal
yielding 1.6 to 1.8Mtpa of saleable product. The development of Makhado Lite was delayed for
approximately one year mainly due to lack of access to two key properties where the east pit,
processing and other infrastructure would be located. The impact of this delay results in, amongst
other things, the repayment date for the existing IDC Loan occurring ahead of significant cashflows
from Makhado Lite. Consequently, in parallel with pursuing various strategies to obtain access to the
two properties, management assessed alternative project development plans, which included
developing Makhado in phases by commencing mining on the west pit and processing through the
existing Vele plant (Phase 1) and then progressing to the east pit (Phase 2).



Makhado Phase 1

Phase 1 entails:

•   mining commencing on the west pit where a large diameter confirmatory drilling programme was
    completed in Q4 CY2018;
•   utilising the existing but to be modified Vele processing plant, thereby reducing construction time
    and cost; and
•   Using previously tested logistics infrastructure.

The development of Phase 1 fast-tracks the development of a second cash generating asset in the
Group, reduces debt/equity funding requirements and significantly reduces execution risk.                                                                                                    
The development of Phase 1 was conditionally approved by the Directors of MC Mining in March 2019
and the Company has commenced with the various work streams required to satisfy these conditions.

The conditions are:


 Finalise thermal offtake                                                              ~ Q2 CY 2019
 Finalise debt funding ~ $20 million                                                   ~ Q2 CY 2019
 Raise equity to repay IDC and contribute to Phase 1 funding ~ $30 million               Q3 CY 2019



Phase 1 salient features
Phase 1 commences with the development of the Makhado west pit as well as modifications to the
existing Vele Colliery processing plant. The drilling programme completed in Q4 CY2018 confirms the
west pit’s limit of oxidation at 17m below surface, indicating that the coal deeper than 17m has not
oxidised. This is shallower than the previously modelled depth of 30m and translates into a lower strip
ratio of 2.08m3/t over the nine-year life of the pit. The approximate 3.0Mtpa of ROM coal from the
west pit will be mined by an independent mining contractor using a truck and shovel, modified terrace
mining method. The ROM coal will be hauled to a crushing and screening plant consisting of a feeder
breaker to crush the coal that is then scalped, removing the coarse parting and waste. The circa
2.0Mtpa of scalped ROM coal will be transported by road to the Vele Colliery for final processing.


The Vele plant modifications will facilitate the simultaneous production of HCC and a 5,500 kcal export
quality thermal coal. The plant modifications consist of amongst others, a new fines circuit comprising
of Reflux Classifier in series with the existing spiral plant, low density secondary wash plant and a froth
flotation plant to capture the ultra-fine coal. The plant will be managed by independent processing
experts to produce approximately 1.1Mtpa of saleable coal comprising 0.54Mtpa of HCC and
0.57Mtpa of thermal coal.


Construction at Makhado and Vele will occur at the same time and will take nine months to complete
requiring peak funding of R460 million ($33.5 million), including a 10% design contingency. The Phase
1 construction costs were assessed by DRA Global during a February 2019 FEED process, delivering a
+-10% accurate capital estimate, while operational costs were obtained from independent mining,
processing and transport contractors, also during February 2019. The Phase 1 mining and processing                                                                                                         
will be outsourced to experienced third parties who have previously operated in South Africa and is
expected to create approximately 650 permanent employment opportunities.


Offtake negotiations for thermal coal are well advanced. The Company is considering various
debt/equity funding options with the existing IDC debt of R120 million ($8.3 million), plus interest to
be accrued up to date of repayment and Phase 1 capital requirements resolved simultaneously
through a composite funding plan.


Phase 1 generates significant cash flows and the project’s IRR is in excess of 45% with a peak funding
payback period of less than 2.5 years. In summary, the key features of Makhado Phase 1 are:


 LOM – west pit only                            9 years
 ROM production                               ~3.0Mtpa
 HCC production                              ~0.54Mtpa
 Thermal coal production                     ~0.57Mtpa
 HCC yield                                      ~19%
 Thermal coal yield                             ~20%
 Construction period                          9 months
 Peak funding                             R460m ($33.5m)*
 Capital expenditure                      R400m ($29.1m)*
 IRR                                            >45%
 Peak funding payback                        <2.5 years
* assumes R13.75/$


Makhado Phase 1 is designed to ensure continued scalability and:


    1. is an organically developed second cash generator;
    2. achieves the stated strategy of Group attaining self-sufficiency with an estimated peak
        funding payback period of <2.5 years;
    3. delivers strong returns with significantly reduced execution risk;
    4. expedites an accelerated time to market by at least one year compared to the original
        Makhado Lite, as:
                                                                                                     
        •   no further confirmatory geotechnical drilling is required;
        •   the Phase 1 FEED process is complete;
        •   reduced mine related infrastructure required;
        •   utilize existing plant at Vele; and
        •   shorter construction period
    5. facilitates the development of Phase 2 in circa FY2022.


David Brown, Chief Executive Officer of MCM, commented:

“The approval for the phased development reflects further advancement of Makhado and its ability
to generate significant near-term value by positioning MC Mining to be able take advantage of positive
future global coking coal prices due to limited supply. The use of the existing Vele processing plant
reduces the project’s capital expenditure requirements and together with the completed FEED
process, shortens the construction time while moderating execution risk. The Company is in advanced
thermal coal offtake discussions with various parties and expects that the marketing and fundraising
elements will be completed in early Q3 CY2019. The planned commencement of construction later in
Q3 CY2019 also reduces the period for delivery of saleable coal to market and generates positive
returns for shareholders in the near-term.

MC Mining remains committed to the sustainable development of the Makhado Project, recognising
its potential to drive significant socio-economic transformation and seeking co-operation between
mining, agriculture and heritage land uses.”


Authorised by
David Brown
Chief Executive Officer


For more information contact:
David Brown             Chief Executive               MC Mining Limited         +27 10 003 8000
                        Officer
Brenda Berlin           Chief Financial               MC Mining Limited         +27 10 003 8000
                        Officer
Tony Bevan              Company Secretary             Endeavour Corporate       +61 08 9316
                                                      Services                  9100

Company advisors:
Jos Simson/ Gareth            Financial PR          Tavistock                   +44 20 7920
Tredway                       (United Kingdom)                                  3150




                                                                                                    
Ross Allister/David     Nominated Adviser    Peel Hunt LLP          +44 20 7418
McKeown                 and Broker                                  8900
Charmane Russell/Olwen Financial PR          R&A Strategic          +27 11 880 3924
Auret                   (South Africa)       Communications
Investec Bank Limited is the nominated JSE   Sponsor




About MC Mining Limited:

MC Mining is an AIM/ASX/JSE listed coal exploration, development and mining company
operating in South Africa. MCM’s key projects include the Uitkomst Colliery
(metallurgical and thermal coal), Makhado Project (coking and thermal coal). Vele
Colliery (coking and thermal coal), and the Greater Soutpansberg Projects (MbeuYashu).


Forward-Looking Statements

This Announcement, including information included or incorporated by reference in
this Announcement, may contain "forward-looking statements" concerning MC Mining that
are subject to risks and uncertainties. Generally, the words "will", "may", "should",
"continue", "believes", "expects", "intends", "anticipates" or similar expressions
identify forward-looking statements. These forward-looking statements involve risks
and uncertainties that could cause actual results to differ materially from those
expressed in the forward-looking statements. Many of these risks and uncertainties
relate to factors that are beyond MCM’s ability to control or estimate precisely,
such as future market conditions, changes in regulatory environment and the behaviour
of other market participants. MCM cannot give any assurance that such forward-looking
statements will prove to have been correct. The reader is cautioned not to place
undue reliance on these forward looking statements. MCM assumes no obligation and do
not undertake any obligation to update or revise publicly any of the forward-looking
statements set out herein, whether as a result of new information, future events or
otherwise, except to the extent legally required.

Statements of intention

Statements of intention are statements of current intentions only, which may change
as new information becomes available or circumstances change.

Regulatory

This announcement is inside information for the purposes of Article 7 of Regulation
596/2014.




                                                                                      

Date: 14/03/2019 09:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story