TAWANA RESOURCES NL - Bald Hill Offtake and Project Update -September 2017

Release Date: 10/10/2017 09:10
Code(s): TAW     PDF:  
Wrap Text
Bald Hill Offtake and Project Update -September 2017

Tawana Resources NL
(Incorporated in Australia)
(Registration number ACN 085 166 721)
Share code on the JSE Limited: TAW
JSE ISIN: AU0000TAWDA9
Share code on the Australian Securities Exchange Limited: TAW
ASX ISIN: AU000000TAW7
(“the Company” or “Tawana”)

Bald Hill Offtake and Project Update September 2017


Please note: All graphics have been removed for SENS purposes.
Please refer to the Tawana website for the complete announcement.

Tawana Resources NL (TAW:ASX) (Tawana) and Alliance Mineral Assets Limited (SGX:AMA) (AMAL) are
pleased to provide this update for the Bald Hill Mine located in the Eastern Goldfields region of Western
Australia. The Bald Hill project (the Project) is a joint project between Tawana and Alliance Mineral
Assets Limited.

Highlights
-   Third prepayment of $4,375,000 received by Tawana from Burwill Holdings Ltd (Burwill) under the
    offtake agreement.

-   AMAL received A$4,375,000 from Burwill on 30 September 2017 via subscription for equity shares
    in AMAL in lieu of the third prepayment under its own offtake agreement.

-   EPC contract for Lithium DMS circuit gaining momentum:
    o    Design approximately 70% complete
    o    Concrete works well-advanced
    o    Structural steel packages let, first package on site
    o    Screens and pumps ordered; starting to arrive on site
    o    Majority of mechanical equipment ordered
    o    Buried services installation commenced
-   Bulk earthworks near completion.

-   Additional administration buildings placed.

-   Communications towers installed and commissioned.

-   Fuel and Power tenders closed and under review.

-   Mining tenders closed and three contractors shortlisted. Award expected by mid-October 2017.

-   Senior operations and development personnel appointed.

Tawana Managing Director Mark Calderwood stated: “The rapid progress being made at the Project is
very encouraging and gives us great confidence that the Bald Hill Mine will be in production in the
quarter ending 31 March 2018.

Our EPC contractors, Primero are progressing the Dense Media Separation processing plant on time,
with commissioning still expected in the first quarter of 2018.
A number of key contracts are expected to be awarded in October 2017 including mining, crushing, fuel
and power.

In addition, there have been a number of key appointments to further enhance the development, and
operational skills as the joint venture moves forward with the development of the Bald Hill Lithium and
Tantalum Mine”

EPC Update
    -   Engineering is well-advanced with design more than 70% complete.
    -   Concrete works well-advanced.
    -   Buried services (electrical/piping) progressing with conduits & pits being positioned/installed
        and HDPE pipes being welded ready for installation.
    -   Steelwork is progressively being detailed and progressing through fabrication and painting. First
        package of structural steel has arrived and is being erected.
    -   Procurement of major equipment is progressing with critical orders on track.

Major Contracts
    -   Mining tender closed; unit pricing equal to the Pre-feasibility study (PFS). Three contractors
        shortlisted, with the preferred to be notified by mid October 2017.
    -   Fuel and Power tenders closed; unit pricing consistent with PFS.
    -   Crushing tenders closed, currently under review.
    -   Non-Processing Infrastructure tenders closed; review underway.
    -   Haul road upgrade tender closed.

Key Personnel

Each of the Bald Hill Lithium and Tantalum Joint Venture partners has respectively made a number of
key recent appointments to further enhance the development, and operational skills as it moves
forward with the development of the Bald Hill Lithium and Tantalum Mine in the eastern goldfields of
Western Australia . These key appointments are as follows:

Tony Dominkovich - Project Director, EPC Superintendent (AMAL)

Tony has 37 years’ experience undertaking mining, infrastructure, mineral process and pharmaceutical
research projects in Australia, Africa, USA, the Balkans and Asia. Recent projects include Mt Weld Rare
Earths (Lynas), Barrick Granny Smith upgrades, Barrick Bulyanhulu and Buzwagi and FMG Christmas
Creek. In addition to these projects, Tony has also been consulting to Pela Global on the restart of
several brownfield polymetallic mining and process operations in the Balkans.

Other related roles include Directorship of an industry superannuation fund and lecturing contract law
and estimating.

Tony undertakes an oversight and review function for AMAL, monitoring all project activities, approvals
and expenditure.

Steve Zaninovich – Project Director (Tawana)

Steve has 25 years’ experience in the development of numerous projects in Australia and West Africa,
with his most recent role being VP - Major Projects at Teranga Gold Corporation, notably leading the
development of the company’s Banfora Gold Project in Burkina Faso. Steve previously worked as COO
for Gryphon Minerals (prior to its acquisition by Teranga Gold Corp.), as a Project Director for
Lycopodium Minerals, a Non-Executive Director for Centaurus Minerals and Orway Mineral
Consultants, and started his career in the construction industry with UGL Limited.
Steve’s project management experience includes as Project Director for Newmont’s $1 billion, 7 million
ounce Akyem Gold Project in Ghana; Project Manager for the H2S Plant Project at Kwinana Nickel
Refinery, Tarkwa Phase IV Project in Ghana, Project Controls Manager at the Ridgeway Gold Project,
Commissioning Manager at the Bibiani Upgrade in Ghana, and various studies.

Steve will lead the project development of the Bald Hill lithium and tantalum operation.

Rob Broad – Project Manager

Robert is a highly experienced Project Manager and Principal Engineer having worked with Worley
Parsons, Kaiser, BHPB, Rio Tinto, Worsley Alumina, Alcoa, Hatch, Karara, Nickel West, Gwalia,
Woodside, Chevron and Horizon Power, on major resource and infrastructure projects. Robert has been
PM Certified by PMI, BHPB and Worley Parsons and has set up project systems for a number of mining
and engineering companies.

As a consultant engineer for over 35 years, Rob has designed and built a wide range of refineries and
minerals processing plants including lithium (spodumene and carbonate) and tantalum.

Darren Buchholz – Operations Manager

Darren has a substantial career in mining operations. Before joining Tawana Resources, Darren was
most recently a site General Manager for Mineral Resources Limited which included managing the
mining operation and associated infrastructure as well as managing the site. Prior to this, Darren was
General Manager for Global Advanced Metals where he led and managed mine-site operations and
notably led strategies to reduce costs through innovative use of technology and driving efficiencies. In
both of these roles Darren led a suite of performance uplifts in the processing plant and tailings dam.

Other previous roles that Darren has held include Processing Superintendent at Talison Tantalum and
Senior Processing Coordinator for Sons of Gwalia, both positions held for a number of years.

In addition, the following key personnel have been appointed and have commenced duties on site in
the last month to oversee or facilitate construction activities and commence operations readiness
preparation as well as take over monitoring activities from contractors:
    -   Superintendent - Mining
    -   Superintendent - Health Safety & Environment
    -   Mine geologist
    -   Surveyor
    -   Environmental Advisor and Radiation Safety Officer

Accommodation Camp

In addition to the 40-room existing camp, personnel are also now being housed at the leased 150-
person Lanfranchi camp. Tawana is currently assessing the merits of expanding the current 40-room
camp at Bald Hill.

About the Bald Hill Project

The Bald Hill Lithium and Tantalum Mine (Bald Hill Mine or the Project) is owned by Singapore Exchange-
listed Alliance Mineral Assets Limited (AMAL), with ASX-listed Tawana Resources NL (Tawana) holding
50% of the lithium rights. The project is subject to a 50% earn-in to existing infrastructure and tantalum
rights by Tawana through the expenditure of A$12.5m on development costs. Following the 50% earn-in
by Tawana, a new Joint Venture will become effective and the Work Program and Budget for remaining
project expenditure in excess of the A$12.5m will be subject to Joint Venture approval.

A Pre-Feasibility Study (PFS) finalised in July 2017 confirmed the technical and financial viability of a low
capital cost 1.2Mtpa lithium Dense Media Separation circuit (DMS) adjacent to the existing tantalum
processing facility (TPF) at Bald Hill.
The first shipment of lithium concentrate is scheduled for March 2018.

EPC Group Primero mobilised to the Bald Hill Mine in July 2017 and construction work commenced,
with bulk earthworks completed and initial cement foundations being poured.

Each of Tawana and AMAL executed an offtake agreement in April 2017 for the supply of lithium
concentrate from Bald Hill over a five-year term with pricing for 2018 and 2019 of US$880/t (FOB
Esperance) for 6% Li2O. The prepayments from the aforesaid offtake agreement will be used towards
the capital costs of the Project. AMAL had entered into a binding term sheet to vary certain terms of
the aforesaid offtake agreement and subsequently, a definitive subscription agreement for the issuance
of ordinary shares in the capital of AMAL to Burwill; further details of which can be found in AMAL’s
announcement on the SGXnet dated 4 October 2017.

The Project is located 50km south east of Kambalda in the Eastern Goldfields of Western Australia. It is
located approximately 75km south east of the Mt Marion Lithium Mine.

The Project comprises four mining leases, one mining lease application, twelve exploration licenses,
eight prospecting licenses and one general purpose lease totalling 790.1km.

A Maiden Indicated and Inferred lithium Mineral Resource of 12.8 million tonnes at 1.18% Li2O, and
158ppm Ta205 at a 0.5% Li2O cut-off for the Project was estimated by CSA Global Pty Ltd and announced
in June 2017. The Project remains significantly underexplored as highlighted by significant exploration
drill results post the June 2017 resource statement.


10 October 2017

Sponsor
PricewaterhouseCoopers Corporate Finance (Pty) Limited

Date: 10/10/2017 09:10:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story