Production report for the third quarter ended 30 September 2016
ANGLO AMERICAN PLATINUM LIMITED
(Incorporated in the Republic of South Africa)
(Registration number: 1946/022452/06)
Share Code: AMS
ISIN: ZAE000013181
(“The Company" or "Anglo American Platinum")
PRODUCTION REPORT FOR THE THIRD QUARTER ENDED 30 SEPTEMBER 2016
OVERVIEW
- Tragically, two fatalities occurred during the quarter
- Total platinum production (expressed as metal in concentrate) was 1% higher than the comparative
period at 619,100 ounces
- Strong operational performances achieved by retained own mines, with Mogalakwena up 12%,
Amandelbult up 1% and Unki up 16%
- Refined platinum production increased by 14% to 694,600 ounces for the quarter, reflecting the
recovery at the Precious Metals Refinery
- Sales volumes of 588,000 ounces were less than refined production, as leases of 49,000 ounces
were repaid and the balance used to build up refined inventory
- Following the run-out of molten furnace matte at the Waterval Smelter on 10 September 2016, year-
end refined production will be impacted by c.75,000 platinum ounces
REVIEW OF THE QUARTER
OPERATIONS
Tragically we had two losses of life due to work related incidents during the third quarter of 2016.
Mr Amos Mataboge was fatally injured in a fall of ground incident at Rustenburg East mine
(Siphumelele) on 5 August 2016 and Mr Nekisile Zibonti was fatally injured in an explosion related
incident at Rustenburg West mine (Thembelani) on 18 August 2016. An independent and
comprehensive investigation into these fatal incidents are under way to understand the circumstances
and learn from them in order to create a safer work environment for all.
The Lost Time Injury Frequency Rate (“LTIFR”) per 200,000 hours worked at managed operations
reduced 19% to 0.77 compared to the LTIFR of 0.95 of Q3 2015.
Total platinum production was up 1% to 619,100 ounces as a result of improved performances during
the quarter at Mogalakwena, Amandelbult, Unki, and at JV’s Modikwa, Kroondal and BRPM.
Mogalakwena production increased 12% to 100,700 ounces. This was driven by a 19% increase in total
tonnes milled, though the comparative period was impacted by community disruption partially offset by
a return to normalised lower grades of 2.92g/t in the period (with normalised grade ranging between
2.8g/t to 3.0 g/t).
Amandelbult production increased marginally, up 1% to 128,300 ounces.
Unki production increased 16% to 18,200 ounces for the period. The increased production was due to
improved underground mining efficiencies which resulted in a 5% increase in tonnes milled, and a 9%
increase in grade due to improved mining height control.
Joint venture production (mined and purchased) was broadly unchanged, down 1% to 207,100 ounces
driven primarily by Bokoni due to closure of two shafts in Q4 2015, offset by strong performance at
Modikwa, Kroondal and BRPM. On a normalised basis, excluding production from the closure of the
two vertical shafts, production at Bokoni increased 12% year-on-year.
Platinum production from Rustenburg operations including the Western Limb Tailings Retreatment
(WLTR) was down 3% to 120,900 ounces. Mine production was impacted by two fatal incidents in Q3
2016, and the subsequent safety stoppages. This was offset by a strong performance from the WLTR
which increased 38% to 13,800 ounces in part due to new production from the East tailings dams.
Following the significant restructuring at Union, the mine continued to perform in line with its optimised
mine plan, maintaining production at 37,700 ounces, despite a reduction in labour.
Refined platinum production increased by 14% to 694,600 ounces following recovery at the Precious
Metals Refinery in processing additional matte material that was built-up ahead of the refinery, after a Section
54 safety stoppage in Q1 2016.
Sales volumes for the quarter of 588,000 ounces were less than refined production of 694,600 ounces,
as leases of 49,000 ounces were repaid and the balance used to build up refined inventory.
As announced on 13 September 2016, the run-out of molten furnace matte at the Waterval Smelter on
10 September has resulted in the need to bring forward a planned furnace rebuild from 2018 to Q4
2016. This rebuild impacted Q3 2016 refined production by c.6,000 ounces and is now estimated to
impact full year refined production by c.75,000 ounces (previously 70,000-100,000 ounces). This will
result in a build-up of concentrate ahead of the smelters; however the concentrate will be processed in
full by the end of 2017. Mining and concentrating activities are unaffected, therefore there is no change
to the full year production guidance.
GUIDANCE
Full year guidance remains in place for 2016 with produced ounces (metal in concentrate) between
2.3 - 2.4 million platinum ounces; Unit costs between R19,250 and R19,750 per platinum ounce (metal
in concentrate); SIB and project capex guidance between R3.5 and R4.0 billion; and capitalised waste
stripping of c.R1.2 billion.
The full impact on refined production from the run-out of the Waterval smelter is unlikely to flow through
to sales volumes in 2016, which will be supplemented by inventory and market activities. The estimated
impact in 2016 on EBIT will be c.R750 million.
Anglo American Platinum Q3 2016 Q3 2016
Third Quarter Production Report Q3 Q3 vs Q2 vs
Period 1 July 2016 - 30 September 2016 2016 2015 Q3 2015 2016 Q2 2016
Attributable Pt production
Total Production 000 oz 619.1 614.2 1% 585.7 6%
Own mines (inc. Twickenham) 000 oz 247.6 236.8 5% 224.7 10%
Joint ventures - mined volume 000 oz 65.0 62.3 4% 66.8 (3)%
Joint ventures and associates - purchased 000 oz 142.2 146.7 (3)% 136.4 4%
Third parties - purchased 000 oz 5.8 6.8 (15)% 4.3 34%
Rustenburg (incl. WLTR) and Union 000 oz 158.5 161.7 (2)% 153.6 3%
Gross refined production
Platinum 000 oz 694.6 611.0 14% 747.7 (7)%
Palladium 000 oz 412.9 390.7 6% 472.3 (13)%
Rhodium 000 oz 86.8 77.5 12% 90.7 (4)%
Gold 000 oz 24.1 23.0 4% 22.3 8%
Platinum group metals (6E) plus Gold 000 oz 1,356.7 1,244.1 9% 1,485.9 (9)%
Nickel - Refined 000 tonne 7.1 6.4 11% 6.4 10%
Copper - Refined 000 tonne 3.8 4.2 (9)% 3.7 2%
Platinum Sales Volumes
Total Sales 000 oz 588.0 690.1 (15)% 808.4 (27)%
Total Operations
Tonnes Milled 000 tonne 10,788 10,086 7% 10,988 (2)%
Grade (4E) g/t 3.19 3.27 (2)% 3.00 6%
M&C production 000 oz 619.1 614.2 1% 585.7 6%
Mogalakwena mine
Tonnes Milled 000 tonne 3,246 2,732 19% 3,224 1%
Grade (4E) g/t 2.92 3.07 (5)% 2.82 3%
M&C production 000 oz 100.7 89.7 12% 98.8 2%
Amandelbult mine
Tonnes Milled 000 tonne 1,829 1,814 1% 1,693 8%
Grade (4E) g/t 4.25 4.29 (1)% 3.91 9%
M&C production 000 oz 128.3 127.6 1% 106.2 21%
Unki Platinum mine
Tonnes Milled 000 tonne 414 396 5% 426 (3)%
Grade (4E) g/t 3.48 3.21 9% 3.38 3%
M&C production 000 oz 18.2 15.7 16% 17.8 2%
Joint Venture Operations - mined (excl POC)
Tonnes Milled 000 tonne 1,185 1,190 (0)% 1,233 (4)%
Grade (4E) g/t 3.78 3.58 6% 3.75 1%
M&C production 000 oz 65.0 62.3 4% 66.8 (3)%
Rustenburg mine (excluding Western limb tailings retreatment)
Tonnes Milled 000 tonne 1,832 1,947 (6)% 1,700 8%
Grade (4E) g/t 3.57 3.56 0% 3.53 1%
M&C production 000 oz 107.1 114.0 (6)% 98.3 9%
Western Limb tailings retreatment
Tonnes Milled 000 tonne 1,583 1,330 19% 1,940 (18)%
Grade (4E) g/t 1.38 1.19 15% 1.15 20%
M&C production 000 oz 13.8 10.0 38% 14.0 (2)%
Union mine
Tonnes Milled 000 tonne 690 575 20% 716 (4)%
Grade (4E) g/t 3.62 4.16 (13)% 3.77 (4)%
M&C production 000 oz 37.7 37.7 0% 41.2 (9)%
Achieved metal prices
Platinum (US$/oz) 1,083 992 9% 1,006 8%
Palladium (US$/oz) 659 643 2% 571 15%
Rhodium (US$/oz) 646 832 (22)% 693 (7)%
Realised basket price (US$/Pt oz) 1,936 1,705 14% 1,560 24%
Realised basket price (ZAR/Pt oz) 27,174 22,252 22% 23,583 15%
Johannesburg, South Africa
25 October 2016
Sponsor
RAND MERCHANT BANK (A division of FirstRand Bank Limited).
For further information, please contact:
Investors: Media:
Emma Chapman Mpumi Sithole
(SA) +27 (0) 11 373 6239 (SA) +27 (0) 11 373 6246
emma.chapman@angloamerican.com mpumi.sithole@angloamerican.com
Notes to editors:
Anglo American Platinum Limited is a member of the Anglo American plc Group and is the world’s
leading primary producer of platinum group metals. The company is listed on the Johannesburg
Securities Exchange (JSE). Its mining, smelting and refining operations are based in South Africa.
Elsewhere in the world, the Group owns Unki Platinum Mine in Zimbabwe. Anglo American Platinum
has a number of joint ventures with several historically disadvantaged South African consortia as part
of its commitment to the transformation of the mining industry. Anglo American Platinum is committed
to the highest standards of safety and continues to make a meaningful and sustainable difference in
the development of the communities around its operations.
www.angloamericanplatinum.com
Anglo American is a globally diversified mining business. Our portfolio of world-class competitive mining
operations and undeveloped resources provides the raw materials to meet the growing consumer-
driven demands of the world’s developed and maturing economies. Our people are at the heart of our
business. It is our people who use the latest technologies to find new resources, plan and build our
mines and who mine, process and move and market our products – from diamonds (through De Beers)
to platinum and other precious metals and copper – to our customers around the world.
As a responsible miner, we are the custodians of those precious resources. We work together with our
key partners and stakeholders to unlock the long-term value that those resources represent for our
shareholders, but also for the communities and countries in which we operate – creating sustainable
value and making a real difference.
www.angloamerican.com
Date: 25/10/2016 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.