Wrap Text
MCPP and Imweru Gold Project Interim Update
Kibo Mining Plc (Incorporated in Ireland)
(Registration Number: 451931)
(External registration number: 2011/007371/10)
Share code on the JSE Limited: KBO
Share code on the AIM: KIBO
ISIN:IE00B97C0C31
("Kibo" or "the Company")
04 August 2016
MCPP and Imweru Gold Project Interim Update
Kibo Mining plc ("Kibo" or the "Company") (AIM: KIBO; AltX: KBO), the Tanzania focused mineral exploration
and development Company provides an interim update on progress at the Company's Mbeya Coal to Power Project
("MCPP") and the Imweru gold project.
MCPP
Work on the MCPP is continuing at pace with all attention and resources focused on completing the Integrated
Bankable Feasibility Study ("IBFS") as soon as possible, so that financial close activities can commence. Policy
changes currently being considered by the Tanzanian Government which are aimed at improving and simplifying
the procurement process for Independent Power Producer ("IPP") projects like the MCPP, may cause a slight delay
in completing the IBFS. These delays may be required to allow the Company to incorporate the latest IPP-policy
(should any change occur) with regard to Power Purchase Agreements ("PPA") associated with IPP-projects.
Productive interaction with the Tanzanian Ministry of Energy and Minerals and TANESCO is continuing, with all
parties working diligently towards the development and conclusion of a mutually agreed commercial PPA for the
MCPP. Parallel work streams are also progressing well:
*Environmental and Social Impact Assessment more than 75% complete;
*Definitive Power Feasibility Study completed with results well above expectations;
*EPC-contracting process underway and within schedule. In this regard a full EPC specification has already
been developed by Tractebel Engineering and the first round of bid discussions with SEPCO III was
successfully completed during June, in accordance with the provisions of the existing Joint Development
Agreement with SEPCO III. The second round of discussions in this regard, specifically aimed at assessing
whether SEPCO III will be able to meet all outstanding conditions precedent to become the preferred EPC-
contractor to the MCPP, will take place during the week of 15 August 2016. This process will amongst
others include discussions on SEPCO III's investment obligations that must be met before it can become
the preferred EPC-contractor to the MCPP;
*Operation and Maintenance contracting is underway and on schedule, with the process to obtain
expressions of interest from leading international O & M service providers successfully completed. Pre-
qualification of prospective bidders is currently underway;
*Definitive Mining Feasibility Study completed, with results well above expectations;
*EPC and Mining-contracting process underway and within schedule, with excellent responses to requests
for budget quotes from prospective bidders. Pre-qualification from prospective bidders now in process;
*Statutory certification (licensing and permitting) process on schedule;
Imweru Project
On June 2 the Company signed a Memorandum of Understanding ("MOU") with Lake Victoria Gold LTD
("LVG") in which the two companies agreed to consolidate their respective Imweru and Imvelo gold projects. On
July 5 the Company announced a minor unforeseen delay in completing the compliance and legal work required to
finalize the definitive agreement which will conclude the transaction contemplated in the MOU. The final
component required to satisfy compliance and legal requirements, was a site visit to Imweru and Imvelo, attended
by representatives of the Company and LVG respectively, as well as independent technical consultants and financial
advisors to the transaction. This site visit was successfully conducted from 26 to 29 July 2016, during which the
independent consultants and advisors were able to obtain conclusive independent verification of all technical and
legal representations fundamental to the definitive agreement. All outstanding compliance and legal work have now
been completed and the Company and LVG are now in a position where they can execute the definitive agreement,
upon receipt of the final version thereof from legal counsel. This is expected by no later than 08 August 2016.
Louis Coetzee, CEO of Kibo Mining, said: "We are very pleased with the continued progress at the Company's two
main projects. Significant progress has been made on both over the past four months and both projects are
continuing to grow in stature and value. We are looking forward to realizing this value over the coming months and
further updates will follow shortly."
Contacts
Louis Coetzee
+27 (0) 83 2606126
Kibo Mining plc
Chief Executive Officer
Andreas Lianos
+27 (0) 83 4408365
River Group
Corporate Adviser and Designated Adviser on JSE
Jon Belliss
+44 (0) 207 382 8300
Beaufort Securities Limited
Broker
Oliver Morse
+61 8 9480 2500
RFC Ambrian Limited
Nominated Adviser on AIM
Daniel Thole / Anna Legge
+44 (0) 203 772 2500
Bell Pottinger
Investor and Media Relations
Kibo Mining - Notes to editors
Kibo Mining is listed on the AIM market in London and the AltX in Johannesburg. The Company is focused on
exploration and development of mineral projects in Tanzania, and controls one of Tanzania's largest mineral right
portfolios. Tanzania provides a secure and stable operating environment for the mineral resource industry and Kibo
Mining therein.
Kibo Mining holds a thermal coal deposit at Mbeya, which has a significant NI 43-101 compliant defined resource,
and is developing a 250-350 MW mouth-of-mine thermal power station, the Mbeya Coal to Power Project
("MCPP"), previously called Rukwa Coal to Power Project ("RCPP"), with an established management team that
includes Standard Bank as Financial Advisor. Kibo is undertaking a Coal Mining Definitive Feasibility Study and a
Power Pre-Feasibility Study for the Mbeya project with an integrated Bankable Feasibility Study report for the
MCPP to be released in the near term. On 20th April 2015, Kibo signed a Joint Development Agreement for the
completion of the Definitive Feasibility Studies and development of the MCPP with China based EPC
contractor SEPCO III.
The Company also has extensive gold focused interests including Lake Victoria Goldfields and Morogoro projects.
At Lake Victoria, the Company has 100% owned projects with a 550,000 oz. JORC compliant gold Mineral
Resource at the Imweru Project and a 168,000 oz. NI 43-101 compliant gold Mineral Resource at the Lubando
Project. The Company is currently undertaking a Definitive Feasibility Study on its Imweru Project.
Kibo also holds the Haneti Project on which the latest technical report confirms prospectivity for nickel, PGMs, gold
and strategic metals including lithium.
Kibo Mining further holds the Pinewood (coal & uranium) project where the company has entered into a 50/50
Exploration Joint Venture with Metal Tiger plc.
Finally, the Company also holds the Morogoro (gold) project where the company has also entered into a 50/50
Exploration Joint Venture with Metal Tiger plc.
The Company's projects are located in the established and gold prolific Lake Victoria Goldfields, the emerging
goldfields of eastern Tanzania and the Mtwara Corridor in southern Tanzania where the Government has prioritized
infrastructural development attracting significant recent investment in coal and uranium. The Company has a
positive working relationship with the Tanzanian government at local, regional and national levels and works hard to
maintain positive relationships with all communities where company interests are held. The Company recognizes the
potential to enhance the quality of life and opportunity for Tanzanian citizens through careful development of its
projects.
Updates on the Company's activities are regularly posted on its website www.kibomining.com
Johannesburg
04 August 2016
Corporate and Designated Adviser
River Group
Date: 04/08/2016 07:05:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.