To view the PDF file, sign up for a MySharenet subscription.

THE WATERBERG COAL COMPANY LIMITED - December 2015 Quarterly Activities Report

Release Date: 02/02/2016 08:00
Code(s): WCC     PDF:  
Wrap Text
December 2015 Quarterly Activities Report

The Waterberg Coal Company Limited
(Incorporated in Australia)
(Registration number ABN 64 065 480 453)
ASX: WCC | JSE: WCC | ISIN: AU000000WCC9
(“WCC” or “the Company”)

December 2015 Quarterly Activities Report

1.         The Waterberg Coal Project
           The Waterberg Coal Company Limited (the Company) is a
           participant in the Waterberg coal project joint venture
           (the   Waterberg  Project),   situated  in   the  Limpopo
           Province, South Africa.   The Waterberg Project currently
           has identified coal resources of 3.4 billion tonnes of
           coal contained within the granted mining and prospecting
           rights1.
           Accruing from the various work streams and technical
           studies that have been carried out to date, the Waterberg
           Project now comprises the following projects:
           -     The Eskom Project;
           -     The Export Project; and
           -     The IPP Project.
           Predicated upon funding being forthcoming, pursuant to
           the proposed arrangements with Sibanye Gold Limited
           (Sibanye) [as set out below], the Company continued to
           advance the progress of the Waterberg Project and
           associated activities.
1.1        The Eskom Project
           Since the completion of the definitive feasibility study
           (DFS), the project team have been engaged in value
           engineering and optimisation studies for the Eskom
           Project with a view to enhancing the bankability of the
           project and reducing the cost of delivery of product to
           Eskom Holdings SOC Ltd (Eskom).   As at the date of this
           report the joint venture partners in the Waterberg
           Project   (the  Waterberg   Project   Partners)  are  in
           discussions with Eskom for producing coal on a long term
           basis.
1.1.1.     Project Optimisation Study
           Value engineering work on the Eskom Project advanced
           during the quarter, including a revised model focusing on
           optimising the output to produce either an Eskom product

1
    See Appendix I for the Resource Statement.
         or a combined Eskom and an independent power producer
         (IPP) feed product.
         The optimisation study also incorporated a revision of
         the Waterberg Project’s mining plan and economic model
         and now is in a position to discuss with Eskom supply
         price with incremental supply tonnages and a range of
         qualities to meet their range of boiler fuel needs.
1.2      The Export Project
         During the 2015 financial year a DFS for a proposed
         development of an export project mine was completed.
         This proposed development would see production of up to
         4 million tonnes per annum of high quality export thermal
         coal product over a 3 to 4 year period.
         An optimisation study for the Export Project is underway.
         The significant focus of this optimisation study is the
         review of the projects capital requirements with a view
         to enhancing the viability of the project.            The
         optimisation includes consultation with world-class plant
         designers and contract vendors for the mining and
         processing facilities and services.        The Waterberg
         Project Partners are confident that the optimisation
         process will derive positive outcomes resulting in
         considerable reductions in capital funding requirements
         for the project.
         A key focus of the optimisation study is to revise the
         original washing process plans to enable production of a
         higher quality of coal suitable for the export market and
         to provide flexibility for production of a higher quality
         power station feed product for a proposed IPP to be
         located within the confines of the Waterberg Project.
         This power station product is planned to be stockpiled
         during the export grade coal mining phase until the
         potential IPP platform is completed. Utilisation of this
         product as IPP feed will result in optimal resource
         utilisation.
1.2.1.   Coal Processing Plant
         The Waterberg Project Partners completed their evaluation
         of build-own-operate (BOO) proposals during the quarter.
         The Waterberg Project Partners are confident that
         adopting a BOO strategy in conjunction with well
         experienced operators will significantly reduce up front
         capital requirements and provide for a swift progression
         to mining and production.
1.2.2.   Mining Operations
         Negotiations with a number of parties for the award of
         the mining contract continued to advance during the
         quarter.   The bidding process, guided by the Waterberg
         Project mining engineer, has progressed to a point where
         we have indicative pricing on a ZAR/ROM per tonne which
         is within the parameters of the Waterberg Project
         Partners’ financial modelling and the costing in the DFS.
         We have used this quarter to investigate alternative
         mining contractors to ensure we have options available,
         specifically regarding price and performance. It is
         envisaged that the Waterberg Project will be a large
         mining operation, by any measure, and multiple mining
         contractors are not being ruled out.
1.2.3.   Project Water Supply
         During the quarter Ceenex (Pty) Ltd (Ceenex), an
         independent management, technology and engineering
         advisory firm, were briefed on the Waterberg Project
         water plan using the Paarl Waste Water Treatment Facility
         (the Facility).   Ceenex has now provided the Waterberg
         Project Partners with a proposed scope of work outlining
         the work required to  comply   with   the   necessary
         environmental, legal and physical project related tasks
         in order to complete the water supply for the mining,
         process and first stage power plant.
         This scope of work is expected to take twelve months and
         integrates well with the Waterberg Project development
         plan. The deliverables from this exercise will include,
         but not limited to, a water use licence, a cost effective
         plan for the operation and management of the Facility and
         the delivery of process water to the Waterberg Project
         site.
         The Waterberg Project Partners are also in ongoing
         discussions with the South African authorities in
         connection with the planned Mokolo Crocodile River Water
         Augmentation Project that will supply adequate long term
         water for the development of the Waterberg Project’s long
         term IPP plans and the entire region.
1.2.4.   Power Production for Project Construction Purposes
         The Waterberg Project Partners continued discussions with
         multiple parties regarding the onsite production of power
         generation for the proposed mining project development.
         SMEC Holdings Limited (SMEC), as consultants, will
         provide guidance and advice to the Waterberg Project
         Partners in respect of electricity generation plant
         specifications   to   ensure   achievement   of   optimal
         technological configuration and operational efficiency
         for the plant.

1.2.5.   Export Product Offtake Arrangements
         The Waterberg Project Partners are in discussions with
         parties with respect to memorandums of understanding for
         the initial export production offtake.       The product
         specifications  for   the   export   product   that  are
         anticipated to be sold into long-term offtake agreements
         are as follows:
                           Combined Total   Upper Zone   Lower Zone
                               Average       (03-15)       (17-20)
              Ash (%)           17.39          24.73        16.38
              CV (MJ/kg)
              (ad)             25.99           23.21       26.37
              Moisture
              (%)               3.25           2.51         3.35
              Volatiles
              (%)              24.86           26.88       24.59
              Sulphur
              (%)               0.71            0.72       0.71
              Yield (%)        71.52           37.39       76.19
1.3      IPP - Power Transmission
         As previously reported, the Waterberg Project Partners
         have   been  carrying   out  preliminary   work  on   the
         incorporation of an IPP platform on the Waterberg Project
         site.
         During the quarter the study team continued its scope of
         works.  As part of this scope, the study consultants,
         SMEC, concluded an investigation and study of the current
         transmission capacity  of the existing   transmission
         infrastructure available for the transmission of the
         first stage planned IPP production.     This verified that
         the evacuation of the planned power production for the
         first phase IPP is viable with the   existing
         infrastructure. Further power generation units will have
         additional transmission capacity challenges, which will
         be addressed when appropriate.
         Additionally, during the quarter a number of critical
         aspects of the IPP development study were completed,
         including a technology survey which determined that
         circulating fluidised bed technology was the most
         appropriate for the Waterberg Project resource.  There
         were a number of positive reasons for this including,
         inter alia, lower emissions and the ability to utilise
         lower grade carbon fuel, thus maximising the yield or
         carbon utilisation from the deposit. It also allows the
         utilisation of the fines discard for fuel, minimising or
         negating the need for tailings disposal.

2.    South Australian Tenements
      The Company holds exploration tenements EL5221 and EL5397
      in the Gawler Craton, South Australia; these are
      prospective for gold and copper-gold mineralisation. The
      Gawler Craton is host to large copper-gold deposits such
      as Olympic Dam and Prominent Hill to the east, and gold
      deposits such as Challenger, Tarcoola and Tunkillia in
      the west.
      On 29 September 2015 the Company entered into an
      agreement with Stockworks Exploration and Mining Pty Ltd
      (Stockworks)   for  Stockworks   to  acquire   EL5397 in
      consideration of an initial cash payment of $25,000, a
      further cash payment of $75,000 on registration of the
      transfer of the tenement and an ongoing 1% net smelter
      royalty for the benefit of the Company for any type of
      ore mined on the tenement.      The transfer application
      documentation is currently under consideration by the
      South Australian Mineral Resources Division and is
      expected to be effected by the end of January 2016.   In
      the interim the Company, in conjunction with Stockworks,
      has effected renewal of the tenement and continued to
      compile and validate exploration data relating to it.
      Compilation and validation of exploration data continued
      for EL5221. Further work has not been undertaken on this
      tenement due to the Company’s focus on the Waterberg
      Project.   Consequently, the Company does not consider
      this tenement to be core to its future business prospects
      and has undertaken to seek expressions of interest from
      potential buyers.

3.    Corporate
3.1   The SBSA Facility and the Proposed  Transaction with
      Sibanye
      The Company entered into a voluntary suspension of its
      shares on 19 March 2015 whilst it conducted negotiations
      with Standard Bank of South Africa Limited (SBSA) (and
      other participants) (the SBSA Noteholders) with respect
      to “refinancing” the SBSA convertible note facility (the
      Facility).
      On 15 September 2015 the Company and Firestone Energy
      Limited entered into a term sheet with Sibanye whereby,
      inter alia, Sibanye agreed provisional terms with SBSA
      (as the Facility agent) to acquire the Facility.
      As advised to the market on 17 September 2015, the
      transaction contemplated with Sibanye was subject to due
      diligence (legal, technical and financial); the due
      diligence was expected to be completed by end of November
      2015.

      Sibanye has advised that due diligence has been completed
      and, whilst they are desirous of pursing the transaction,
      they wish to vary, inter alia, the terms of the proposed
      transaction with the SBSA Noteholders.    At the date of
      this report, this variation has not been completed or
      documented.
      It is contemplated that once the variation with the SBSA
      Noteholders has been documented a revised term sheet will
      be entered into with all of the parties.

3.2   Annual General Meeting
      The Company held its Annual General Meeting on 30
      November 2015. All resolutions were passed on a show of
      hands at the meeting. Dr Mathews Phosa was re-elected as
      a Director.

Stephen Miller
Managing Director and CEO
The Waterberg Coal Company Limited


Appendix I: Resource Statement1      2

Coal Resource on all six Waterberg Coal Project Properties
under both Prospecting Permit and Mining Right
Resource       Coal       Ash %   IM %    Vol % CV        TS %
Classification Resource* (ad)     (ad)    (ad)   (Mj/kg) (ad)
               (Mt)                              (ad)
Measured       1314.51    57.6    2.2     17.9   10.7     1.00
Indicated      1247.2     57.4    2.3     17.8   10.7     1.13
Inferred       838        58.5    2.2     17.6   10.4     1.19
Total          3400       57.7    2.2     17.8   10.6     1.09
Resources
*Coal resource is based on a minimum thickness cut-off of 0.5m

Stephen Miller
Director & MD
The Waterberg Coal Company Limited

02 February 2016
JSE Sponsor:
The Standard Bank of South Africa Limited


1 Please note that this information was prepared and first disclosed under
  the JORC Code 2004. It has not been updated since to comply with the JORC
  Code 2013 on the basis that the information has not materially changed
  since it was last reported.

2 Competent Person Statement - Gemecs (Pty) Limited was commissioned by the
Company to undertake an Updated Independent Persons Geological Report for
the Waterberg Coal Project. The Coal Resources were estimated in
accordance with the South African code for the Reporting of Exploration
Results, Mineral Resources and Mineral Reserves (SAMREC Code), Australasian
Code for Reporting of Exploration Results.      Mineral Resources and Ore
Reserves (the JORC Code) and South African National Standard (SANS
10320:2004) guidelines.   The information in this report that relates to
Exploration Results, Mineral Resources or Ore Reserves is based on
information compiled by Mr Coenraad D van Niekerk, Pr.Sci.Nat (Reg. No
400066/98), M.Sc Hons (Geology), MDP, an employee of Gemecs (Pty) Limited,
who is a  Fellow of the Geological   Society   of  South   Africa.
Mr Coenraad D van Niekerk is a mining geologist with 38 years’ experience
in the mining industry, sufficient experience relevant to the style of
mineralisation and type of deposit under consideration and to the activity
which he is undertaking to qualify as a Competent Person as defined in the
2004 Edition of the Joint Ore Reserves Committee (JORC) “Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.
Mr Coenraad D van Niekerk consents to the inclusion in the report of the
matters based on his information in the form and context in which it
appears. Any discrepancy is due to rounding.





Date: 02/02/2016 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story