To view the PDF file, sign up for a MySharenet subscription.

COAL OF AFRICA LIMITED - Report for the Quarter ended 31 March 2015

Release Date: 23/04/2015 09:00
Code(s): CZA     PDF:  
Wrap Text
Report for the Quarter ended 31 March 2015

Coal of Africa Limited
(Incorporated and registered in Australia)
Registration number ABN 008 905 388
ISIN AU000000CZA6
JSE/ASX/AIM share code: CZA
("CoAL or the "Company" or the "Group")




ANNOUNCEMENT          

23 April 2015                                                             

REPORT FOR THE QUARTER ENDED 31 MARCH 2015
Makhado Empowerment Structure Finalised

Coal of Africa Limited (“CoAL” or “the Company”) which operates in South Africa, together with its
subsidiaries, hereby provides its update for the quarter ended 31 March 2015. All figures are denominated in
United States dollars unless otherwise stated. A copy of this report is available on the Company's website,
www.coalofafrica.com.

Salient Operational Features

-    No lost-time injuries recorded during the quarter (FY2015 Q2: nil).

-    Approval granted for the amended and updated Environmental Authorisation (“EA”) for the Vele Colliery to
     include the anticipated plant modifications while the application for the amendment and extension of the
     IWUL for the colliery is still pending following which the Company will make a decision on the timing of the
     start of the plant modifications.

Corporate and Financial Features

-    Submission to the Department of Mineral Resources (“DMR”) after the conclusion of agreements with
     broad based black economic empowerment (“BBBEE”) partners to acquire up to 26 per cent of the
     Makhado Project.

-    The Makhado BBBEE partners have two years to raise sufficient capital to acquire their interests in the
     project with the final amount payable subject to due diligence and will be negotiated with the Company.
     The transaction ensures that the Makhado Project complies with mining legislation in South Africa and is
     an important step in the process for the granting of a New Order Mining Right (“NOMR”).

-    The liability owing to Rio Tinto was reduced during the quarter on the payment of $1.0 million (FY2015
     Q2: $6.3 million) while discussions continued on the settlement of the remaining capital balance of $22.5
     million.

-    Continued discussions with stakeholders including the communities and the Department of Mineral
     Resources in advancing the award of the Makhado Project NOMR.

-    The Company continued to engage with the Department of Water Affairs to progress the application for
     the Makhado Project Integrated Water Use Licence (“IWUL”), which CoAL anticipates should be issued
     after the receipt of the NOMR.
-   Receipt of R1.5 million ($0.13 million) for the sale of the Opgoedenhoop NOMR with the balance of R17.6
    million ($1.5 million) (including VAT) due by the end of H1 CY2015.

-   Resignation of Michael Meeser as Chief Financial Officer and Executive Director during the quarter.

-   Available cash at period end was $13.5 million and restricted cash of $2.1 million.

Post Period Event

-    An appeal against the Vele Colliery amended and updated EA was lodged with the Department of
     Environmental Affairs (“DEA”) during April 2015.

Commenting today, Mr David Brown, Chief Executive Officer said: “The Makhado Project empowerment
structure was formalised during the quarter and completes one of the last requirements for the granting of a
mining right for the project. The structure results in communities residing in the vicinity of the project acquiring
20 per cent of the project with a further 6 per cent acquired by Historically Disadvantaged South Africans. The
Company expects that the Makhado Project mining right will be granted during H1 CY2015, a critical step to
unlock the significant value of CoAL’s flagship hard coking and thermal coal asset.”

QUARTERLY COMMENTARY

Mooiplaats Colliery – Ermelo Coalfield (74% owned)

The Mooiplaats thermal coal colliery (“Mooiplaats Colliery”) was placed on care and maintenance during the
September 2013 quarter and recorded no lost time injuries (“LTIs”) during the period (FY2015 Q2: no LTIs).

During Q1 FY2015 the Company signed an SPA with Blackspear Capital Proprietary Limited ("Blackspear")
for the disposal of the Mooiplaats Colliery for R250 million ($20.7 million). Blackspear has until 30 April 2015,
on a non-exclusive basis, to agree terms with a financial and operational partner to fund its acquisition of
Mooiplaats. During the quarter the Company commenced discussions with other potential purchasers.



Vele Colliery – Limpopo (Tuli) Coalfield (100% owned)

The Vele coking and thermal coal colliery (“Vele Colliery”) recorded no LTIs during the quarter (FY2015 Q2:
no LTIs).

The Company’s applications to amend the colliery’s EA to include the plant modifications were approved by
the DEA during the quarter. The Company previously submitted applications to amend and renew Vele’s
IWUL and is confident these will be received during H1 CY2015. The current Vele Colliery IWUL is valid until
March 2016 and the Company has delayed the commencement of the plant modification construction to Q3
CY2015 pending these approvals, which also gives the Company further time to assess the outlook for coal
prices.
Makhado Coking Coal Project – Soutpansberg Coalfield (100% owned – 74% post BBBEE transaction)

The Makhado coking coal project (“Makhado Project”) recorded no LTIs (FY2015 Q2: no LTIs) during the
quarter.

South African mining legislation requires that mining and exploration projects have a minimum 26% black
economic empowerment shareholding and CoAL previously signed a Memorandum of Agreement to enable
seven local communities (the “Communities”) to acquire a 20% interest in the Makhado Project. During the
quarter the Company signed acquisition agreements with the Makhado Colliery Community Development
Trust (the “Trust”), an umbrella trust that will ensure communities are beneficiaries, and Yoright Investments
(Pty) Ltd (“Yoright”) formed by black entrepreneur Mike Nkuna whose shareholders will include other
Historically Disadvantaged South Africans. In terms of the acquisition agreements the Trust and Yoright have
two years to raise sufficient funding to acquire their respective twenty per cent and six per cent interests in the
project, with the final amount payable subject to due diligence and will be negotiated with the Company.

An interim court interdict was issued against the Makhado Project during Q2 FY2015 seeking to halt any
mining or construction activity on the site. During the quarter the Company, as one of the respondents,
continued preparation to have the interim interdict to set aside and does not anticipate that this process the
affect the timetable for the mine to commence commercial production during CY2019.



Greater Soutpansberg Project (MbeuYashu) (74% owned)

The MbeuYashu Project recorded no LTIs (FY2015 Q2: no LTIs) during the period.


Corporate Update

During H2 CY2014 CoAL received $46 million on completion of the first two stages of the shareholder
approved $60 million equity placement process. The attached Appendix 5B excludes potential proceeds from
stage 3 of the equity placement process which is still anticipated by the end of April 2015.

Authorised by
David Brown
Chief Executive Officer
23 April 2015

For more information contact:

David Brown                     Chief Executive Officer    Coal of Africa                 +27 10 003 8000
Michael Meeser                  Chief Financial Officer    Coal of Africa                 +27 10 003 8000
Celeste Harris                  Investor Relations         Coal of Africa                 +27 10 003 8000
Tony Bevan                      Company Secretary          Endeavour Corporate Services   +61 08 9316 9100

Company advisors:

Jos Simson/Emily Fenton                Financial PR (United Kingdom)      Tavistock                          +44 20 7920 3150
Chris Sim/George Price/Jeremy Ellis    Nominated Adviser                  Investec Bank plc                  +44 20 7597 5970
Charmane Russell/Jane Kamau            Financial PR (South Africa)        Russell & Associates               +27 11 880 3924 or
                                                                                                             +27 82 372 5816
Investec Bank Limited is the nominated JSE Sponsor

About CoAL:

CoAL is an AIM/ASX/JSE listed coal exploration and development company operating in South Africa. CoAL’s key projects include the Vele Colliery
(coking and thermal coal), Makhado Project (coking and thermal coal) and the Greater Soutpansberg Project /MbeuYashu.
Tenements held by CoAL and its Controlled Entities

                                                                                                     Change
Project Name   Tenement Number                                                Location   Interest   in quarter

Chapudi        Albert 686 MS-                                                 Limpopo~      74%
Project*
               Bergwater 712 MS--                                                           74%

               Remaining Extent and Portion 2 of Bergwater 697 MS--                         74%
               Blackstone Edge 705 MS                                                       74%
               Remaining Extent & Portion 1 of Bluebell 480 MS-                             74%
                                                                                            74%
               Remaining Extent & Portion 1 of Bushy Rise 702 MS--
               Castle Koppies 652 MS--                                                      74%
               Chapudi 752 MS --                                                            74%
               Remaining Extent, Portions 1, 3 & 4 of Coniston 699 MS--                     74%
               Driehoek 631 MS--                                                            74%
               Remaining Extent of Dorps-rivier 696 MS--                                    74%
               Enfield 512 MS (consolidation of Remaining Extent of                         74%
               Enfield 474 MS, Brosdoorn 682 MS & Remaining Extent of
               Grootvlei 684 MS)--
               Remaining Extent and Portion 1 of                                            74%
               Grootboomen 476 MS-                                                          74%
               Grootvlei 684 MS--                                                           74%
               Kalkbult 709 MS                                                              74%
               Remaining Extent, Remaining Extent of Portion 2,                             74%
               Remaining Extent of Portion 3, Portions 1, 4, 5, 6, 7 & 8 of
               Kliprivier 692 MS-
               Remaining Extent of Koodoobult 664 MS-                                       74%
               Koschade 657 MS (Was Mapani Kop 656 MS)-                                     74%
               Malapchani 659 MS-                                                           74%
               Mapani Ridge 660 MS-                                                         74%
               Melrose 469 MS-                                                              74%
               Middelfontein 683 MS-                                                        74%
               Mountain View 706 MS-                                                        74%
               M'tamba Vlei 654 MS                                                          74%
               Remaining Extent & Portion 1 of Pienaar 635 MS-                              74%
               Remaining Extent & Portion 1 of Prince's Hill 704 MS-                        74%
               Qualipan 655 MS-                                                             74%
               Queensdale 707 MS-                                                           74%
               Remaining Extent & Portion 1 of Ridge End 662 MS-                            74%
               Remaining Extent & Portion 1 of Rochdale 700 MS-                             74%
               Sandilands 708 MS-                                                           74%
               Portions 1 & 2 of Sandpan 687 MS--                                           74%
               Sandstone Edge 658 MS-                                                       74%
               Remaining Extent of Portions 2 & 3 of Sterkstroom 689                        74%
               MS--
               Sutherland 693 MS-                                                           74%
               Remaining Extent & Portion 1 of Varkfontein 671 MS--                         74%
               Remaining Extent, Portion 2, Remaining Extent of Portion                     74%
               1 of Vastval 477 MS-
               Vleifontein 691 MS-                                                          74%
               Ptn 3, 4, 5 & 6 of Waterpoort 695 MS--                                       74%
                                                                                                   Change
Project Name   Tenement Number                                           Location      Interest   in quarter

               Wildebeesthoek 661 MS-                                                     74%
               Woodlands 701 MS-                                                          74%
Kanowna West   M27/41                                                    Coolgardie^   23.68%
and
Kalbara        M27/47                                                                  23.68%
               M27/59                                                                  23.68%
               M27/72,27/73                                                            23.68%
               M27/114                                                                 23.68%
               M27/181                                                                 21.31%
               M27/196                                                                 23.68%
               M27/414,27/415                                                          23.68%
               P27/1826-1829                                                           23.68%
               P27/1830-1842                                                           23.68%
               P27/1887                                                                23.68%
Abbotshall     ML63/409,410                                              Norseman^     Royalty
Royalty
Kookynie       ML40/061                                                  Leonora^      Royalty
Royalty
               ML40/135,136                                                            Royalty
Holfontein     Remaining extent, Remaining Extent of portions 1, 5 and   Mpumalanga~    100%
               11 and portions 4, 6, 9, 10, 12 and 13 of the farm
               Holfontein 138 IS
Makhado        Fripp 645 MS                                              Limpopo~        100%
Project
               Lukin 643 MS                                                              100%
               Remaining Extent and Portion 1 of Overwinning 713 MS                      100%


               Salaita 188 MT                                                            100%
               Tanga 648 MS                                                              100%
               Remaining Extent, Portion 1 and                                           100%
               Portion 2 of the farm Windhoek 649 MS
Generaal                                                                 Limpopo~         74%
               Beck 568 MS--
Project
               Bekaf 650 MS-                                                              74%
               Remaining Extent & Portion 1 of Boas 642 MS-                               74%
               Chase 576 MS-                                                              74%
               Coen Britz 646 MS-                                                         74%
               Fanie 578 MS-                                                              74%
               Gray 189 MT                                                               100%
               Portions 1, 2 and Remaining Extent of Generaal 587 MS-                     74%
               Joffre 584 MS-                                                             74%
               Juliana 647 MS                                                             74%
               Kleinenberg 636 MS-                                                        74%
               Remaining Extent of Maseri Pan 520 MS-                                     74%
               Remaining Extent and Portion 2 of Mount Stuart 153 MT--                   100%
               Nakab 184 MT--                                                            100%
               Phantom 640 MS--                                                           74%
               Riet 182 MT--                                                             100%
               Rissik 637 MS-                                                            100%
               Salaita 188 MS-                                                            74%
                                                                                                         Change
Project Name    Tenement Number                                                Location      Interest   in quarter

                Schuitdrift 179 MT-                                                            100%
                Septimus 156 MT--                                                              100%
                Solitude 111 MT-                                                                74%
                Stayt 183 MT--                                                                 100%
                Telema 190 MT                                                                  100%
                Remaining Extent & Portion 1 of Terblanche 155 MT--                            100%
                Van Deventer 641 MS-                                                            74%
                Wildgoose 577 MS-                                                               74%
Mopane                                                                         Limpopo~        100%
                Ancaster 501 MS--
Project*
                Banff 502 MS-                                                                   74%
                Bierman 599 MS-                                                                 74%
                Cavan 508 MS                                                                   100%
                Cohen 591 MS--                                                                 100%
                Remaining Extent, Portions 1 & 2 of Delft 499 MS-                               74%
                Dreyer 526 MS--                                                                 74%
                Remaining Extent of Du Toit 563 MS-                                             74%
                Faure 562 MS                                                                    74%
                Remaining Extent and Portion 1 of Goosen 530 MS --                              74%
                Hermanus 533 MS-                                                                74%
                Jutland 536 MS--                                                               100%
                Krige 495 MS-                                                                   74%
                Mons 557 MS-                                                                   100%
                Remaining Extent of Otto 560 MS (Now Honeymoon)-                                74%
                Remaining Extent & Portion 1 of Pretorius 531 MS-                               74%
                Schalk 542 MS-                                                                  74%
                Stubbs 558 MS-                                                                 100%
                Ursa Minor 551 MS--                                                             74%
                Van Heerden 519 MS--                                                            74%
                Portions 1, 3, 4, 5, 6, 7, 8, 9, Remaining Extent of Portion                    74%
                10, Portions 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24,
                26, 27, 29, 30, 35, 36, 37, 38, 39, 40, 41, 44, 45, 46, 48,
                49, 50, 51, 52 & 54 of Vera 815 MS
                Remaining Extent of Verdun 535 MS-                                              74%
                Voorburg 503 MS--                                                              100%
Mooiplaats                                                                     Mpumalanga~      74%
Colliery and    Portions 1, 9,14,17,18,19,20 & Remaining Extent of
prospects       Mooiplaats 290 IT
                Portion 2, 3 and Remaining Extent of Klipbank 295 IT                            74%
                Portions 1, 2 and Remaining Extent of Adrianople296 IT                          74%
                Portions 2 & 3 of Willemsdal 330 IT                                             74%
                Portions 2, 3, 4 & Remaining Extent) of De Emigratie 327                        74%
                IT
                Remaining Extent and Portions 2, 5, 8,10 & 13 of                                74%
                Buhrmansvallei 297 IT
                Klipfontein 442 IT                                                              74%
Vele Colliery   Portions of Overvlakte 125 MS (Remaining Extent, 3, 4, 5,      Limpopo~        100%
and prospect    6, 13, 14)
                Bergen Op Zoom 124 MS                                                          100%
                Semple 155 MS                                                                  100%
                Voorspoed 836 MS                                                               100%
                Alyth 837 MS                                                                   100%
                                                                                           Change
Project Name   Tenement Number                                      Location   Interest   in quarter

               Lizzuela 62 MS                                                    100%
               Patracia 65 MS                                                    100%
               Hacyon 69 MS                                                      100%
Tshikunda      Certain portions of Unsurveyed State Land known as   Limpopo~      60%
               Mutale
Coal bed                                                            Limpopo~      50%
               Adelaide 91 MT
methane
               Adieu 118 MT                                                       50%
               Alicedale 138 MT                                                   50%
               Armstice 120 MT                                                    50%
               Bergwater 697 MS                                                   50%
               Bergwater 712 MS                                                   50%
               Blackstone Edge 705 MS                                             50%
               Bushy Rise 702 MS                                                  50%
               Chapudi 752 MS                                                     50%
               Charlotte 90 MT                                                    50%
               Chase 576 MS                                                       50%
               Cross 117 MT                                                       50%
               Doppie 95 MT                                                       50%
               Ettie 33 MT                                                        50%
               Fanie 578 MS                                                       50%
               Feskraal 85 MT                                                     50%
               Folorodwe 79 MT                                                    50%
               Fripp 645 MS                                                       50%
               Gray 189 MT                                                        50%
               Hettey 93 MT                                                       50%
               Jeannette 77 MT                                                    50%
               Joffre 584 MS                                                      50%
               Kalkbult 709 MS                                                    50%
               Laura 115 MT                                                       50%
               Lukin 643 MS                                                       50%
               Magazasand 123 MT                                                  50%
               Malapchani 659 MS                                                  50%
               Mountainview 706 MS                                                50%
               Mount Stuart 153 MT                                                50%
               Nakab 184 MT                                                       50%
               Naus 178 MT                                                        50%
               Neltox 92 MT                                                       50%
               Phantom 640 MS                                                     50%
               Prince’s Hill 704 MS                                               50%
               Queensdale 707 MS                                                  50%
               Riet 182 MT                                                        50%
               Rochdale 700 MS                                                    50%
               Rynie 158 MT                                                       50%
               Salaita 188 MT                                                     50%
               Schuitdrift 179 MT                                                 50%
               Septimus 156 MT                                                    50%
               Stayt 183 MT                                                       50%
               Suzette 32 MT                                                      50%
               Tanga 648 MS                                                       50%
               Telema 190 MT                                                      50%
                                                                                                                                       Change
 Project Name           Tenement Number                                                             Location         Interest         in quarter

                        Terblanche 155 MT                                                                                 50%
                        Trevenna 119 MT                                                                                   50%
                        The Duel 186 MT                                                                                   50%
                        Truida 76 MT                                                                                      50%
                        Van Deventer 641 MS                                                                               50%
                        Wendy 86 MT                                                                                       50%
                        Wildgoose 577 MS                                                                                  50%
                        Windhoek 649 MS                                                                                   50%
                        Zisaan 31 MT                                                                                      50%
                        Ziska 122 MT                                                                                      50%
                        Portion of Unsurveyed state land                                                                  50%

 *          Form part of the Greater Soutpansberg Project
 -          Lapsed – Mining Right Application Lodged
 --         Valid – Mining Right Application Lodged
 ~          Tenement located in the Republic of South Africa
 ^          Tenement located in Western Australia




AU: Coal of Africa Limited, Suite 8, 7 The Esplanade, Mount Pleasant, Perth WA 6153, Australia, Tel: +61 8 9316 9100, Fax: +61 8 9316 5475
ZA: South Block, Summercon Office Park, Cnr Rockery Lane and Sunset Avenue, Lonehill, 2191, Tel: +27 10 003 8000 Fax: +27 11 388 8333 Email:
adminza@coalofafrica.com



Bernard R. Pryor – Chairman, David H. Brown – Chief Executive Officer , Michael G. Meeser – Chief
Financial Officer Non-executive directors: Peter G. Cordin, Andrew D. Mifflin, Khomotso B.
Mosehla ,Thabo F. Mosololi, Rudolph H. Torlage

Date: 23/04/2015 09:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.