GLN - 2014 Half-Year Production Report
Glencore plc
(Incorporated in Jersey under the Companies (Jersey) Law 1991)
(Registration number 107710)
JSE Share Code: GLN
LSE Share Code: GLEN
HKSE Share Code: 805HK
ISIN: JE00B4T3BW64
NEWS RELEASE
Baar, 13 August 2014
2014 Half-Year Production Report
Following completion of the Glencore Xstrata merger on 2 May 2013, production information for all periods covered in
this report has been presented on a combined basis.
Key Highlights:
– Own sourced copper production up 13% to 741,000 tonnes, primarily driven by Mutanda ramp-up and improved
production at Collahuasi. Sequential half-yearly production was down 12%, reflecting lower head grades on account
of mine sequencing (Collahuasi and Antamina) and planned maintenance shuts (Collahuasi, Mount Isa and Mopani).
– Own sourced zinc production was 650,400 tonnes, down 11%, primarily due to Perseverance and Brunswick mines
having depleted their reserves in June 2013. Sequential half-yearly production was broadly in line, reflecting Perkoa
ramp-up, largely offsetting mine sequencing lower grades at Antamina and some opportunistic favouring of 3rd party
feed at Kazzinc.
– Own sourced nickel production was 49,100 tonnes, down 8%, reflecting the XNA (Sinclair and Cosmos) and
Falcondo mines now all being placed on care and maintenance. Sequential half-yearly production was up 8%, due
to higher production at INO (increased Raglan volumes) and the continued start-up / ramp-up at Koniambo.
– Own sourced ferrochrome production was 652,000 tonnes, up 16%, reflecting increased capacity due to the prior
period Eskom power buy-back programme and a ramp-up in production relating to the Lion 2 expansion project.
– Own sourced coal production was up 5% to 71.2 million tonnes, mainly due to productivity improvements and
ongoing expansion projects in Australian thermal coal, and a 32 day strike at Cerrejón which impacted Q1 2013.
– Gross oil E&P production was 14.0 million barrels, up 41%, relating to full period operations at Alen (EG) and Badila
(Chad) which came on line during 2013.
– On 31 July 2014, the sale of Las Bambas completed, whereby Glencore received proceeds, net of tax, of
approximately $6.5 billion, including the reimbursement of capital expenditure and other project costs incurred since
1 January 2014.
– On 8 July 2014, Glencore completed the acquisition of Caracal Energy Inc., an oil exploration and development
company with operations in the Republic of Chad for consideration of approximately $1.6 billion.
For further information please contact:
Investors Media
Paul Smith Charles Watenphul
t: +41 (0)41 709 24 87 t: +41 (0)41 709 24 62
m: +41 (0)79 947 13 48 m: +41 (0)79 904 33 20
e: paul.smith@glencore.com e: charles.watenphul@glencore.com
Investors Investors Finsbury (Media)
Martin Fewings Elisa Morniroli Guy Lamming
t: +41 (0)41 709 28 80 t: +41 (0)41 709 28 18 Dorothy Burwell
m: +41 (0)79 737 56 42 m: +41 (0)79 833 05 08 t: +44 (0)20 7251 3801
e: martin.fewings@glencore.com e: elisa.morniroli@glencore.com
www.glencore.com
Metals and Minerals
Production from own sources – Total(1)
H1 H1 Change
2014 2013 %
Total Copper kt 741.0 658.0 13
Total Zinc kt 650.4 729.5 (11)
Total Lead kt 148.9 153.2 (3)
Total Nickel kt 49.1 53.1 (8)
Total Gold koz 450 478 (6)
Total Silver koz 16,621 19,761 (16)
Total Cobalt kt 9.8 9.1 8
Total Ferrochrome kt 652 561 16
Total Platinum2 koz 43 44 (2)
Total Palladium2 koz 24 24 -
Total Rhodium2 koz 8 8 -
Total Vanadium Pentoxide mlb 9.7 9.8 (1)
Production from own sources – Copper assets(1)
H1 H1 Change
2014 2013 %
African Copper (Katanga, Mutanda, Mopani)
Total Copper metal(3) kt 212.3 171.5 24
Total Cobalt(4) kt 8.1 7.4 9
Collahuasi(5)
Copper metal kt 4.3 7.1 (39)
Copper in concentrates kt 101.6 60.1 69
Silver in concentrates koz 1,355 747 81
Antamina(6)
Copper in concentrates kt 61.4 62.2 (1)
Zinc in concentrates kt 27.1 53.2 (49)
Silver in concentrates koz 2,005 2,377 (16)
Other South America (Alumbrera, Lom as Bayas, Antapaccay, Punitaqui)
Total Copper metal kt 35.3 45.4 (22)
Total Copper in concentrates kt 138.6 121.8 14
Total Gold in concentrates and in dore koz 176 184 (4)
Total Silver in concentrates and in dore koz 919 1,148 (20)
Australia (Ernest Henry, Mount Isa, Cobar)
Total Copper in anode kt 92.5 88.9 4
Total Copper in concentrates kt 23.5 22.6 4
Total Gold koz 27 16 69
Total Silver koz 625 711 (12)
Total Copper department
Total Copper kt 669.5 579.6 16
Total Cobalt kt 8.1 7.4 9
Total Zinc kt 27.1 53.2 (49)
Total Gold koz 203 200 1
Total Silver koz 4,904 4,983 (2)
Production from own sources – Zinc assets(1)
H1 H1 Change
2014 2013 %
Kazzinc
Zinc metal kt 99.2 105.6 (6)
Lead metal kt 11.5 15.6 (26)
Copper metal kt 19.1 26.8 (29)
Gold koz 246 277 (11)
Silver koz 1,889 2,848 (34)
Australia (Mount Isa, McArthur River)
Total Zinc in concentrates kt 302.2 298.4 1
Total Lead in concentrates kt 107.0 97.8 9
Total Silver in concentrates koz 4,149 3,740 11
North America (Matagami, Kidd, Brunswick)
Total Zinc in concentrates kt 69.0 131.6 (48)
Total Lead in concentrates kt - 13.5 (100)
Total Copper in concentrates kt 23.0 24.4 (6)
Total Silver in concentrates koz 891 3,371 (74)
Other Zinc (AR Zinc, Los Quenuales, Sinchi Wayra, Rosh Pinah, Perkoa)
Zinc metal kt 10.2 16.0 (36)
Zinc in concentrates kt 142.7 124.7 14
Lead metal kt 5.4 4.9 10
Lead in concentrates kt 25.0 21.4 17
Copper in concentrates kt 1.6 0.8 100
Silver metal koz 292 324 (10)
Silver in concentrates koz 4,496 4,495 -
Total Zinc department
Total Zinc kt 623.3 676.3 (8)
Total Lead kt 148.9 153.2 (3)
Total Copper kt 43.7 52.0 (16)
Total Gold koz 246 277 (11)
Total Silver koz 11,717 14,778 (21)
Production from own sources – Nickel assets(1)
H1 H1 Change
2014 2013 %
Integrated Nickel Operations (Sudbury, Raglan, Nikkelverk)
Total Nickel metal kt 27.1 23.6 15
Total Nickel in concentrates kt 0.3 0.3 -
Total Copper metal kt 8.0 8.6 (7)
Total Copper in concentrates kt 19.8 17.6 13
Total Cobalt metal kt 0.4 0.3 33
Australia (Murrin Murrin, XNA)
Total Nickel metal kt 17.6 19.1 (8)
Total Nickel in concentrates kt - 3.1 (100)
Total Copper in concentrates kt - 0.2 (100)
Total Cobalt metal kt 1.3 1.3 -
Total Cobalt in concentrates kt - 0.1 (100)
Falcondo Nickel in ferronickel kt - 7.0 (100)
Koniambo Nickel in ferronickel kt 4.1 - n.m.
Total Nickel department
Total Nickel kt 49.1 53.1 (8)
Total Copper kt 27.8 26.4 5
Total Cobalt kt 1.7 1.7 -
Production from own sources – Ferroalloys assets1
H1 H1 Change
2014 2013 %
Ferrochrome(7) kt 652 561 16
PGM(8) Platinum koz 43 44 (2)
Palladium koz 24 24 -
Rhodium koz 8 8 -
Gold koz 1 1 -
4E koz 76 77 (1)
Vanadium Pentoxide mlb 9.7 9.8 (1)
Total production – Custom metallurgical assets(1)
H1 H1 Change
2014 2013 %
Copper (Altonorte, Townsville, Pasar, Horne, CCR)
Copper metal kt 345.1 373.7 (8)
Custom copper anode kt 266.0 257.0 4
Zinc (Portovesme, San Juan de Nieva, Nordenham, Northfleet)
Zinc metal kt 388.2 372.7 4
Lead metal kt 100.5 78.6 28
Silver koz 5,165 3,280 57
Ferroalloys
Ferromanganese kt 57 52 10
Silicon Manganese kt 52 42 24
Aluminium (Sherwin Alumina)
Alumina kt 776 777 -
(1) Controlled industrial assets and joint ventures only. Production is on a 100% basis, except as stated.
(2) Relating to the PGM business within ferroalloys only.
(3) Copper metal includes copper contained in copper concentrates and blister.
(4) Cobalt contained in concentrates and hydroxides.
(5) The Group's pro-rata share of Collahuasi production (44%).
(6) The Group's pro-rata share of Antamina production (33.75%).
(7) The Group's 79.5% share of the Glencore-Merafe Chrome Venture.
(8) Consolidated 100% of Eland and 50% of Mototolo.
Selected average commodity prices
H1 H1 Change
2014 2013 %
S&P GSCI Industrial Metals Index 343 365 (6)
LME (cash) copper price ($/t) 6,916 7,543 (8)
LME (cash) zinc price ($/t) 2,049 1,936 6
LME (cash) lead price ($/t) 2,100 2,172 (3)
LME (cash) nickel price ($/t) 16,534 16,137 2
Gold price ($/oz) 1,291 1,524 (15)
Silver price ($/oz) 20 27 (26)
Metal Bulletin cobalt price 99.3% ($/lb) 14 12 17
LME (cash) aluminium price ($/t) 1,755 1,919 (9)
Metal Bulletin alumina price ($/t) 323 334 (3)
Metal Bulletin ferrochrome 6-8% C basis 60% Cr, max 1.5% Si (¢/lb) 106 102 4
Platinum price ($/oz) 1,438 1,549 (7)
Iron ore (Platts 62% CFR North China) price ($/DMT) 111 137 (19)
OPERATING HIGHLIGHTS
Copper assets
Total own sourced copper production was 741,000 tonnes, 13% (83,000 tonnes) higher than the comparable period. The
increase mainly relates to the ramp-up in production at Mutanda, Katanga and Antapaccay, plus improved production at
Collahuasi as the operation continues to process at the higher levels achieved during H2 2013, following the restart of
the SAG mill.
African copper
African copper production was 212,300 tonnes, 24% (40,800 tonnes) ahead of the comparable period. The increase
primarily relates to the ramp up at Mutanda, which produced 98,600 tonnes, an increase of 37,400 tonnes (61%) and
reflects the recent expansion to 200,000 tonnes per annum. Katanga also increased production by 12,300 tonnes (20%)
relating to the ongoing commissioning of phase IV. Katanga production is expected to ramp up further during the rest of
2014 as phase V is completed and further operational improvements, including adding some back-up power generator
capacity, are implemented.
Cobalt production was 8,100 tonnes, 9% higher than the comparable period and relates to the Mutanda expansion.
Collahuasi
The group's share of production was 105,900 tonnes, 58% (38,700 tonnes) above the comparable period. The increase
in production reflects a continuation of the high levels of processing seen in H2 2013 following the SAG mill restart and
higher head grades.
Antamina
The group's share of copper production was 61,400 tonnes, in line with the comparable period. Copper production has
benefited from higher milled volumes, offset by lower grades and recoveries in Q2 2014, due to the processing of long
term lower grade stockpiles.
Zinc production was 27,100 tonnes, 49% lower than the comparable period and relates to the mining of higher grade
copper / lower grade zinc areas during the period.
Other South America
Copper production from Other South America was 173,900 tonnes, 4% (6,700 tonnes) higher than the comparable
period. The increase relates to higher milling rates at Antapaccay, partially offset by the closure of the Tintaya SX/EW
operations in October 2013.
Gold production was 176,000 oz, 4% lower than the comparable period, relating to expected lower head grades at
Antapaccay.
Australia
Australia copper production was 116,000 tonnes, 4% (4,500 tonnes) higher than the comparable period, relating to
higher own sourced production at the Mount Isa smelter due to the production of more own sourced concentrates.
Gold production was 27,000 oz, 69% higher than the comparable period relating to the treatment of a higher proportion
of Ernest Henry concentrate (containing gold) versus Mount Isa concentrate (containing no gold) than in H1 2013.
Custom metallurgical assets
Custom copper cathode production was 345,100 tonnes, 8% (28,600 tonnes) lower than the comparable period. The
reduction mainly relates to lost production at Pasar due to the damage caused by typhoon Haiyan, offset by higher
throughput at Townsville. Pasar restarted production at the end of Q1 2014, ramping up during Q2 2014.
Custom copper anode production was 266,000 tonnes, 4% higher than the comparable period, relating to higher
throughput at Horne.
Zinc assets
Total own sourced zinc production was 650,400 tonnes, 11% (79,100 tonnes) below the comparable period. The
reduction mainly relates to the end of mine closure of the Perseverance and Brunswick mines in June 2013 and, to a
lesser degree, the lower grades being mined at Antamina in the current year.
Total own sourced lead production was 148,900 tonnes, 3% (4,300 tonnes) lower than the comparable period. The
principal movements relates to the lost production from the closure of Brunswick (13,500 tonnes) as noted above, offset
by growth (11,700 tonnes) at the Lady Loretta mine (part of Mount Isa complex).
Kazzinc
Zinc production from own sources was 99,200 tonnes, 6% below the comparable period, reflecting an opportunistic
decision (cost savings etc.) to treat more third party sulphide material and therefore less own source oxide ore. Total zinc
production including third party material was up 3% at 151,200 tonnes.
Gold production from own sources was 246,000 oz, 11% lower than the comparable period due to the decision to once
again treat less own source concentrates in favour of more third party precious metal containing material. Own sourced
concentrate production (and gold contained) was in line with the comparable period, with the untreated concentrates
remaining in inventory for treatment in future periods. Total gold production (including third party material) was only
slightly less than the comparable period.
Lead production from own sources was 11,500 tonnes, down 26% versus the comparable period and relates to lower
work in progress being processed at the smelters in 2014 and an expected small reduction in head grades. On a total
metal basis (including third party material), lead production was 61,500 tonnes, up 41% on the comparable period and
reflects the higher output of the new Isa lead smelter.
Copper production from own sources was 19,100 tonnes, down 29% versus the comparable period, relating to temporary
repair work, plus the impact of processing less work in progress at the smelters in 2014. Total copper metal production
(including third party material), was similarly impacted, down 19% over the comparable period.
Australia
Australia zinc production was 302,200 tonnes, in line with the comparable period. This relates to higher production at
Mount Isa (growth from the Lady Loretta expansion), partially offset by a reduction at McArthur River as a result of lower
head grades due to mine sequencing and minor disruptions associated with the expansion project.
Lead production was 107,000 tonnes, 9% higher than the comparable period. The increase relates to the expansion at
Lady Loretta and strong production at Black Star (both Mount Isa), offset by lower production at McArthur River (noted
above).
North America
North America zinc produced 69,000 tonnes of zinc, 48% lower than the comparable period and no lead, reflecting the
end of mine life closures of Perseverance and Brunswick in June 2013. Excluding the impact of the closed mines, North
America zinc increased production by 25,100 tonnes, reflecting the ramp-up of the Bracemac mine (started production in
May 2013), offset by lower production from Kidd due to mining restrictions as a result of temporary stope unavailability
and a focus on higher copper grade areas.
Copper production was 23,000 tonnes, 6% lower than the comparable period, relating to lost copper production from the
closed Perseverance mine, offset by mining higher copper grade areas at the Kidd mine.
Other Zinc
The Other zinc asset group produced 152,900 tonnes, 12,200 tonnes (9%) above the comparable period, relating to the
ramp-up of Perkoa (24,900 tonnes), offset by net lower production from the other assets, including the maintenance
smelter shut down at AR Zinc.
Lead production was 30,400 tonnes, 16% (4,100 tonnes) above the prior year period, mainly relating to higher production
from AR Zinc due to increasing the milling capacity and higher head grades.
European custom metallurgical assets
Custom zinc and lead production were 388,200 tonnes and 100,500 tonnes, up 4% and 28% respectively versus the
prior year period. The increases mainly relate to the full period contribution from Portovesme's zinc and lead plants
following the respective SX plant commissioning and Kivcet plant restart in 2013.
Nickel assets
Own sourced nickel production was 49,100 tonnes, 4,000 tonnes (8%) lower than the comparable period. The decline
relates mainly to the XNA (Cosmos and Sinclair) and Falcondo operations, which together produced 10,100 tonnes in
H1 2013, subsequently being placed into care and maintenance. The lost production was in part offset by production from
Koniambo as it ramps up and production growth at INO, due to increased output from the Raglan mine.
Integrated Nickel Operations ("INO")
INO's own sourced nickel production was 27,400 tonnes, 15% (3,500 tonnes) higher than the comparable period, due to
a higher proportion of own sourced feed (total nickel production was 44,700 tonnes, broadly in line with the comparable
period). The higher proportion of own source feed was driven primarily by increased production from the Raglan mine.
Own sourced copper production was 27,800 tonnes, 6% higher than the comparable period. The increase relates to the
maintenance shut at the Strathcona mill in Q1 2013, which resulted in a reduction in the quantity of Sudbury ore being
processed and better processing rates in general.
Australia
Own sourced nickel production was 17,600 tonnes, 21% below the comparable period. The reduction relates to the
Cosmos and Sinclair mines being placed in care and maintenance and a slight decline in average ore grades at Murrin
Murrin. Total packaged nickel at Murrin Murrin (including third party material) was 2% higher than the comparable period
due to higher throughput at the plant.
Koniambo
Koniambo production was 4,100 tonnes of nickel in ferronickel during the period. Ramp-up activities remain ongoing with
full annualised production expected in 2016.
Ferroalloys assets
Ferrochrome
Attributable ferrochrome production was 652,000 tonnes, 16% (91,000 tonnes) above the comparable period. The
increase relates to the non-recurring Eskom power buy-back programme that occurred during 2013 and the ramp up in
production of Lion phase 2 (furnaces C and D started production in April and June 2014 respectively).
Platinum Group Metals ("PGM")
PGM H1 2014 production was 76,000 oz, consistent with the comparable period.
Vanadium
Vanadium production was 9.7 million lbs, in line with the comparable period.
Manganese
Total manganese (ferromanganese and silicon manganese) production was 109,000 tonnes, 16% higher than the
comparable period. The increase relates to higher throughput in Norway (silicon manganese) due to efficiency
improvements and demand led increases in France (ferromanganese).
Aluminium assets
Sherwin Alumina
Alumina production was 776,000 tonnes, broadly in line with the comparable period, notwithstanding significant power
and steam outages caused by the third party energy supplier during 2014.
Energy Products
Production from own sources
Coal assets(1)
H1 H1 Change
2014 2013 %
Australian coking coal mt 2.9 4.0 (28)
Australian semi-soft coal mt 1.8 2.3 (22)
Australian thermal coal (export) mt 26.0 23.3 12
Australian thermal coal (domestic) mt 2.7 2.6 4
South African thermal coal (export) mt 10.2 9.8 4
South African thermal coal (domestic) mt 11.5 11.7 (2)
Prodeco mt 10.2 9.6 6
Cerrejón(2) mt 5.9 4.5 31
Total Coal department mt 71.2 67.8 5
(1) Controlled industrial assets and joint ventures only. Production is on a 100% basis except for joint ventures, where the Group's attributable share of
production is included.
(2) The Group's pro-rata share of Cerrejón production (33.3%).
Oil assets
H1 H1 Change
2014 2013 %
Gross basis
Equatorial Guinea kbbl 12,035 9,942 21
Chad kbbl 1,983 - n.m.
Total Oil department kbbl 14,018 9,942 41
Glencore entitlement interest basis
Equatorial Guinea kbbl 2,562 2,159 19
Chad kbbl 597 - n.m.
Total Oil department kbbl 3,159 2,159 46
Selected average commodity prices
H1 H1 Change
2014 2013 %
S&P GSCI Energy Index 338 327 3
Coal API4 ($/t) 76 84 (10)
Coal McCloskey Newcastle (6,000 kcal NAR) ($/t) 75 88 (15)
Australian coking coal average realised export price ($/t) 123 155 (21)
Australian semi-soft coal average realised export price ($/t) 98 118 (17)
Australian thermal coal average realised export price ($/t) 75 86 (13)
Australian thermal coal average realised domestic price ($/t) 31 47 (34)
South African thermal coal average realised export price ($/t) 72 83 (13)
South African thermal coal average realised domestic price ($/t) 23 27 (15)
Prodeco (Colombia) thermal coal average realised export price ($/t) 78 88 (11)
Cerrejón (Colombia) thermal coal average realised export price ($/t) 68 76 (11)
Oil price – Brent ($/bbl) 109 108 1
OPERATING HIGHLIGHTS
Coal assets
Total own sourced production was 71.2 million tonnes, 5% higher than the comparable period. The increase arises from
Australian thermal coal, due to productivity improvements and ongoing expansion projects, and Cerrejón which was
impacted by a 32 day strike in Q1 2013. These increases were, in part, offset by a reduction in coking coal production
due to a decision to scale back production from higher cost mines and areas.
Australian coking
Australian coking coal production was 2.9 million tonnes, 28% lower than the comparable period. The decrease relates to
cost reduction initiatives, which led to mine plan and / or roster changes at Newlands, Oaky Creek and Collinsville, the
latter also being affected by industrial issues. Volumes were also temporarily impacted when mining through a fault zone
at Oaky North.
Australian thermal and semi-soft
Australian thermal and semi-soft coal production was 30.5 million tonnes, 8% higher than the comparable period. The
increase relates to the production ramp up at Ravensworth North and Rolleston, productivity gains at Ulan underground
and Bulga and the commencement of longwall operations at Ulan West.
South African thermal
South African thermal production was 21.7 million tonnes, in line with the comparable period. This reflects the opening of
Wonderfontein open cut mine in Q1 2014, offset by various operational challenges, including wet weather and strike
action at Goedgevonden, the closure of Klippan and Wonderfontein underground mines at the end of 2013 and the
closure of the Middelburg Steelcoal pit in Q1 2014.
Prodeco
Prodeco production was 10.2 million tonnes, 6% higher than the comparable period, relating to the ongoing expansion
project, plus productivity improvements at Calenturitas and improved equipment availability across the operations.
Cerrejón
Glencore's share of Cerrejón production was 5.9 million tonnes, 31% (1.4 million tonnes) higher than the comparable
period. The increase reflects the impact of the 32 day strike that occurred in Q1 2013.
Oil E&P assets
H1 2014 gross oil production was 14.0 million barrels, 41% (4.1 million barrels) above the comparable period, relating to
Alen (Equatorial Guinea) and Badila (Chad), which started production at the end of June and September 2013
respectively.
Agricultural Products
Processing / production data
H1 H1 Change
2014 2013 %
Farming kt 266 385 (31)
Crushing kt 2,678 1,548 73
Long term toll agreement kt 206 289 (29)
Biodiesel kt 341 252 35
Rice milling kt 127 120 6
Wheat milling kt 525 555 (5)
Sugarcane processing kt 723 509 42
Total agricultural products kt 4,866 3,658 33
Selected average commodity prices
H1 H1 Change
2014 2013 %
S&P GSCI Agriculture Index 384 434 (12)
CBOT wheat price (US¢/bu) 635 716 (11)
CBOT corn no.2 price (US¢/bu) 466 688 (32)
CBOT soya beans (US¢/bu) 1,414 1,459 (3)
ICE cotton price (US¢/lb) 88 84 5
NYMEX sugar # 11 price (US¢/lb) 17 18 (6)
OPERATING HIGHLIGHTS
Agriculture produced / processed 4.9 million tonnes in H1 2014, 33% higher than the comparable period. The increase in
volumes mainly relates to the continued ramp up at Timbues (Argentinean crush plant), including the impact of Glencore
increasing its stake from 33% to 50%, plus higher sugarcane processing volumes, reflecting the increase in processing
capacity, as part of Rio Vermelho's ongoing expansion.
Appendix – Q2 2013 to Q2 2014
Metals and Minerals
Production from own sources – Total(1)
Production from own sources – Total
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Total Copper kt 350.3 412.9 425.8 381.9 359.1 741.0 658.0 13
Total Zinc kt 357.1 332.2 336.8 306.4 344.0 650.4 729.5 (11)
Total Lead kt 74.1 80.7 81.1 79.0 69.9 148.9 153.2 (3)
Total Nickel kt 26.8 22.5 22.8 22.3 26.8 49.1 53.1 (8)
Total Gold koz 254 278 267 234 216 450 478 (6)
Total Silver koz 10,178 9,652 9,843 8,768 7,853 16,621 19,761 (16)
Total Cobalt kt 5.2 5.6 4.7 4.6 5.2 9.8 9.1 8
Total Ferrochrome kt 301 332 345 335 317 652 561 16
Total Platinum(2) koz 23 24 22 21 22 43 44 (2)
Total Palladium(2) koz 12 14 12 12 12 24 24 -
Total Rhodium(2) koz 4 4 3 4 4 8 8 -
Total Vanadium Pentoxide mlb 4.2 6.1 5.7 5.5 4.2 9.7 9.8 (1)
Production from own sources – Copper assets(1)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
African Copper (Katanga, Mutanda, Mopani, Sable)
Katanga Copper metal(3) kt 31.7 34.5 41.4 31.6 41.0 72.6 60.3 20
Cobalt kt 0.7 0.8 0.5 0.5 0.5 1.0 1.0 -
Mutanda Copper metal(3) kt 31.4 40.3 49.1 47.1 51.5 98.6 61.2 61
Cobalt(4) kt 3.6 3.8 3.5 3.3 3.8 7.1 6.4 11
Mopani Copper metal kt 24.8 30.4 31.4 27.7 13.4 41.1 50.0 (18)
African Copper - total production including third party feed
Mopani Copper metal kt 53.6 55.9 53.6 48.5 31.9 80.4 102.5 (22)
Sable Copper metal kt 3.7 3.7 3.7 2.5 1.3 3.8 7.2 (47)
Cobalt(3) kt 0.1 0.1 0.2 0.1 0.2 0.3 0.1 200
Total Copper metal(3) kt 87.9 105.2 121.9 106.4 105.9 212.3 171.5 24
Total Cobalt(4) kt 4.3 4.6 4.0 3.8 4.3 8.1 7.4 9
Collahuasi(5) Copper metal kt 3.7 3.0 2.4 2.3 2.0 4.3 7.1 (39)
Copper in concentrates kt 34.1 60.6 62.4 50.0 51.6 101.6 60.1 69
Silver in concentrates koz 420 663 807 675 680 1,355 747 81
Antamina(6) Copper in concentrates kt 36.1 43.4 43.9 34.2 27.2 61.4 62.2 (1)
Zinc in concentrates kt 30.5 14.9 19.8 11.1 16.0 27.1 53.2 (49)
Silver in concentrates koz 1,441 1,339 1,500 1,068 937 2,005 2,377 (16)
Other South America (Alumbrera, Lomas Bayas, Antapaccay, Punitaqui)
Alumbrera Copper in concentrates kt 26.0 26.0 34.8 26.1 23.3 49.4 48.8 1
Gold in concentrates and in dore koz 80 77 90 81 65 146 146 -
Silver in concentrates and in dore koz 409 350 177 180 179 359 618 (42)
Lomas Bayas Copper metal kt 18.8 18.4 18.2 18.0 17.3 35.3 37.6 (6)
Antapaccay Copper metal kt 4.2 4.1 0.3 - - - 7.8 (100)
Copper in concentrates kt 33.5 39.9 31.4 37.3 46.0 83.3 67.7 23
Gold in concentrates koz 19 30 11 12 18 30 38 (21)
Silver in concentrates koz 242 280 188 220 301 521 478 9
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Punitaqui Copper in concentrates kt 2.5 3.3 3.2 3.3 2.6 5.9 5.3 11
Silver in concentrates koz 22 24 25 21 18 39 52 (25)
Punitaqui - total production including third party feed
Copper in concentrates kt 2.6 3.3 3.3 3.3 2.6 5.9 5.4 9
Silver in concentrates koz 23 25 25 22 18 40 53 (25)
Total Copper metal kt 23.0 22.5 18.5 18.0 17.3 35.3 45.4 (22)
Total Copper in concentrates kt 62.0 69.2 69.4 66.7 71.9 138.6 121.8 14
Total Gold in concentrates and in dore koz 99 107 101 93 83 176 184 (4)
Total Silver in concentrates and in dore koz 673 654 390 421 498 919 1,148 (20)
Australia (Ernest Henry, Mount Isa, Cobar)
Ernest Henry mine, Copper anode kt 51.2 55.0 57.2 54.6 37.9 92.5 88.9 4
Mt Isa mine and smelter Copper in concentrates kt - 2.9 - - - - - n.m.
Gold in anode koz 8 16 18 15 12 27 16 69
Gold in concentrates koz - 1 - - - - - n.m.
Silver in anode koz 265 312 305 241 172 413 493 (16)
Silver in concentrates koz - - 11 - - - - n.m.
Ernest Henry mine, Mount Isa mine and smelter - total production including third party feed
Copper anode kt 53.6 57.6 57.2 54.7 38.9 93.6 93.0 1
Copper in concentrates kt - 2.9 - - - - - n.m.
Gold in anode koz 10 16 18 15 12 27 18 50
Gold in concentrates koz - 1 - - - - - n.m.
Silver in anode koz 265 312 305 241 172 413 493 (16)
Silver in concentrates koz - - 11 - - - - n.m.
Cobar Copper in concentrates kt 11.4 11.5 11.5 12.6 10.9 23.5 22.6 4
Silver in concentrates koz 116 103 107 113 99 212 218 (3)
Total Copper in anode kt 51.2 55.0 57.2 54.6 37.9 92.5 88.9 4
Total Copper in concentrates kt 11.4 14.4 11.5 12.6 10.9 23.5 22.6 4
Total Gold koz 8 17 18 15 12 27 16 69
Total Silver koz 381 415 423 354 271 625 711 (12)
Total Copper department
Total Copper kt 309.4 373.3 387.2 344.8 324.7 669.5 579.6 16
Total Cobalt kt 4.3 4.6 4.0 3.8 4.3 8.1 7.4 9
Total Zinc kt 30.5 14.9 19.8 11.1 16.0 27.1 53.2 (49)
Total Gold koz 107 124 119 108 95 203 200 1
Total Silver koz 2,915 3,071 3,120 2,518 2,386 4,904 4,983 (2)
Production from own sources – Zinc assets(1)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Kazzinc
Zinc metal kt 53.0 54.7 55.9 49.2 50.0 99.2 105.6 (6)
Lead metal kt 7.4 7.0 7.2 7.4 4.1 11.5 15.6 (26)
Copper metal kt 13.4 12.4 11.7 10.8 8.3 19.1 26.8 (29)
Gold koz 146 154 148 126 120 246 277 (11)
Silver koz 1,022 1,146 1,257 1,132 757 1,889 2,848 (34)
Kazzinc - total production including third party feed
Zinc metal kt 75.0 76.1 77.1 75.3 75.9 151.2 147.2 3
Lead metal kt 21.7 23.2 23.9 32.2 29.3 61.5 43.5 41
Copper metal kt 16.0 15.0 16.3 15.4 9.8 25.2 31.1 (19)
Gold koz 174 190 190 161 159 320 328 (2)
Silver koz 4,772 5,000 4,599 5,014 6,065 11,079 9,082 22
Australia (Mount Isa, McArthur River)
Mount Isa Zinc in concentrates kt 103.2 106.4 102.7 100.8 102.9 203.7 196.0 4
Lead in concentrates kt 39.0 46.5 46.8 47.2 39.0 86.2 74.5 16
Silver in concentrates koz 1,435 2,057 1,927 2,054 1,461 3,515 2,886 22
McArthur River Zinc in concentrates kt 47.5 53.6 47.3 45.2 53.3 98.5 102.4 (4)
Lead in concentrates kt 11.4 11.6 10.9 9.3 11.5 20.8 23.3 (11)
Silver in concentrates koz 392 347 379 297 337 634 854 (26)
Total Zinc in concentrates kt 150.7 160.0 150.0 146.0 156.2 302.2 298.4 1
Total Lead in concentrates kt 50.4 58.1 57.7 56.5 50.5 107.0 97.8 9
Total Silver in concentrates koz 1,827 2,404 2,306 2,351 1,798 4,149 3,740 11
North America (Matagami, Kidd, Brunswick, CEZ Refinery)
Matagami/Perseverance Zinc in concentrates kt 18.0 15.1 20.0 17.9 19.0 36.9 39.4 (6)
Copper in concentrates kt 2.2 2.0 2.7 2.1 2.5 4.6 4.4 5
Kidd Zinc in concentrates kt 19.3 13.6 14.0 10.1 22.0 32.1 40.2 (20)
Copper in concentrates kt 9.9 10.6 9.3 10.3 8.1 18.4 17.0 8
Silver in concentrates koz 1,153 606 572 385 506 891 2,056 (57)
Brunswick Mine Zinc in concentrates kt 9.2 - - - - - 52.0 (100)
Lead in concentrates kt 2.4 - - - - - 13.5 (100)
Copper in concentrates kt 0.3 - - - - - 3.0 (100)
Silver in concentrates koz 658 - - - - - 1,315 (100)
Total Zinc in concentrates kt 46.5 28.7 34.0 28.0 41.0 69.0 131.6 (48)
Total Lead in concentrates kt 2.4 - - - - - 13.5 (100)
Total Copper in concentrates kt 12.4 12.6 12.0 12.4 10.6 23.0 24.4 (6)
Total Silver in concentrates koz 1,811 606 572 385 506 891 3,371 (74)
North America - total production including third party feed
Brunswick Mine Zinc in concentrates kt 13.3 - - - - - 56.1 (100)
Lead in concentrates kt 3.5 - - - - - 14.6 (100)
Copper in concentrates kt 0.3 - - - - - 3.0 (100)
Silver in concentrates koz 745 - - - - - 1,402 (100)
Brunswick Smelter Lead metal kt 18.0 19.2 20.1 18.7 17.5 36.2 36.0 1
Silver metal koz 4,022 4,098 4,555 3,120 2,852 5,972 7,493 (20)
CEZ Refinery(7) Zinc metal kt 17.1 15.3 16.8 14.9 15.6 30.5 34.2 (11)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Other Zinc (AR Zinc, Los Quenuales, Sinchi Wayra, Rosh Pinah, Perkoa)
Zinc metal kt 9.5 7.5 6.2 1.9 8.3 10.2 16.0 (36)
Zinc in concentrates kt 66.9 66.4 70.9 70.2 72.5 142.7 124.7 14
Lead metal kt 2.8 3.1 3.0 2.4 3.0 5.4 4.9 10
Lead in concentrates kt 11.1 12.5 13.2 12.7 12.3 25.0 21.4 17
Copper in concentrates kt 0.3 0.7 0.6 0.8 0.8 1.6 0.8 100
Silver metal koz 177 161 185 133 159 292 324 (10)
Silver in concentrates koz 2,426 2,264 2,403 2,249 2,247 4,496 4,495 -
Other Zinc - total production including third party feed
Zinc metal kt 10.5 10.9 9.5 2.4 9.3 11.7 17.5 (33)
Zinc in concentrates kt 66.9 66.4 70.9 70.2 72.5 142.7 124.7 14
Lead metal kt 2.8 3.1 3.0 2.4 3.0 5.4 4.9 10
Lead in concentrates kt 11.1 12.5 13.2 12.7 12.3 25.0 21.4 17
Copper in concentrates kt 0.3 0.7 0.6 0.8 0.8 1.6 0.8 100
Silver metal koz 177 161 185 133 159 292 324 (10)
Silver in concentrates koz 2,426 2,264 2,403 2,249 2,247 4,496 4,495 -
Total Zinc department
Total Zinc kt 326.6 317.3 317.0 295.3 328.0 623.3 676.3 (8)
Total Lead kt 74.1 80.7 81.1 79.0 69.9 148.9 153.2 (3)
Total Copper kt 26.1 25.7 24.3 24.0 19.7 43.7 52.0 (16)
Total Gold koz 146 154 148 126 120 246 277 (11)
Total Silver koz 7,263 6,581 6,723 6,250 5,467 11,717 14,778 (21)
Production from own sources – Nickel assets1
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Integrated Nickel Operations (Sudbury, Raglan, Nikkelverk)
Total Nickel metal kt 11.3 10.1 13.4 13.3 13.8 27.1 23.6 15
Total Nickel in concentrates kt 0.1 0.1 0.1 0.2 0.1 0.3 0.3 -
Total Copper metal kt 4.2 3.7 4.4 3.8 4.2 8.0 8.6 (7)
Total Copper in concentrates kt 10.5 10.1 9.9 9.3 10.5 19.8 17.6 13
Total Cobalt metal kt 0.2 0.2 0.2 0.2 0.2 0.4 0.3 33
Integrated Nickel Operations - total production including third party feed
Total Nickel metal kt 22.5 23.0 23.2 21.7 22.6 44.3 44.8 (1)
Total Nickel in concentrates kt 0.2 0.1 0.2 0.2 0.2 0.4 0.4 -
Total Copper metal kt 9.0 9.2 9.9 8.7 7.8 16.5 18.4 (10)
Total Copper in concentrates kt 12.9 12.5 12.3 11.7 13.5 25.2 21.5 17
Total Cobalt metal kt 0.8 0.8 1.0 0.8 0.9 1.7 1.6 6
Australia (Murrin Murrin, XNA)
Total Nickel metal kt 10.4 9.3 7.5 7.8 9.8 17.6 19.1 (8)
Total Nickel in concentrates kt 1.7 1.0 - - - - 3.1 (100)
Total Copper in concentrates kt 0.1 0.1 - - - - 0.2 (100)
Total Cobalt metal kt 0.7 0.8 0.5 0.6 0.7 1.3 1.3 -
Total Cobalt in concentrates kt - - - - - - 0.1 (100)
Australia - total production including third party feed
Total Nickel metal kt 11.6 11.2 8.9 9.4 12.2 21.6 21.2 2
Total Nickel in concentrates kt 1.7 1.0 - - - - 3.1 (100)
Total Copper in concentrates kt 0.1 0.1 - - - - 0.2 (100)
Total Cobalt metal kt 0.8 0.8 0.5 0.6 0.8 1.4 1.4 -
Total Cobalt in concentrates kt - - - - - - 0.1 (100)
Falcondo Nickel in ferronickel kt 3.3 2.0 0.4 - - - 7.0 (100)
Koniambo Nickel in ferronickel kt - - 1.4 1.0 3.1 4.1 - n.m.
Total Nickel department
Total Nickel kt 26.8 22.5 22.8 22.3 26.8 49.1 53.1 (8)
Total Copper kt 14.8 13.9 14.3 13.1 14.7 27.8 26.4 5
Total Cobalt kt 0.9 1.0 0.7 0.8 0.9 1.7 1.7 -
Production from own sources – Ferroalloys assets(1)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Ferrochrome(8) kt 301 332 345 335 317 652 561 16
PGM(9) Platinum koz 23 24 22 21 22 43 44 (2)
Palladium koz 12 14 12 12 12 24 24 -
Rhodium koz 4 4 3 4 4 8 8 -
Gold koz 1 - - - 1 1 1 -
4E koz 40 42 37 37 39 76 77 (1)
Vanadium Pentoxide mlb 4.2 6.1 5.7 5.5 4.2 9.7 9.8 (1)
Total production – Custom metallurgical assets(1)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Copper (Altonorte, Townsville, Pasar, Horne, CCR)
Copper metal kt 191.3 197.5 179.4 153.7 191.4 345.1 373.7 (8)
Copper anode kt 127.6 129.2 128.3 125.0 141.0 266.0 257.0 4
Zinc (Portovesme, San Juan de Nieva, Nordenham, Northfleet)
Zinc metal kt 181.3 181.3 191.0 193.6 194.6 388.2 372.7 4
Lead metal kt 31.2 43.1 52.5 48.5 52.0 100.5 78.6 28
Silver koz 1,244 2,162 2,428 2,342 2,823 5,165 3,280 57
Ferroalloys
Ferromanganese kt 23 24 23 30 27 57 52 10
Silicon Manganese kt 22 24 26 26 26 52 42 24
Aluminium (Sherwin Alumina)
Alumina kt 393 410 419 385 391 776 777 -
(1) Controlled industrial assets and joint ventures only. Production is on a 100% basis, except as stated.
(2) Relates to the PGM business in ferroalloys only.
(3) Copper metal includes copper contained in copper concentrates and blister.
(4) Cobalt contained in concentrates and hydroxides.
(5) The Group's pro-rata share of Collahuasi production (44%).
(6) The Group's pro-rata share of Antamina production (33.75%).
(7) The Group's pro-rata share of CEZ production (25%).
(8) The Group's 79.5% share of the Glencore-Merafe Chrome Venture.
(9) Consolidated 100% of Eland and 50% of Mototolo.
Energy Products
Production from own sources
Coal assets(1)
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Australian coking coal mt 2.2 1.6 1.7 1.5 1.4 2.9 4.0 (28)
Australian semi-soft coal mt 1.2 1.0 1.2 0.9 0.9 1.8 2.3 (22)
Australian thermal coal (export) mt 12.3 13.7 11.1 11.8 14.2 26.0 23.3 12
Australian thermal coal (domestic) mt 1.0 1.3 1.2 1.4 1.3 2.7 2.6 4
South African thermal coal (export) mt 4.9 5.3 5.5 5.0 5.2 10.2 9.8 4
South African thermal coal (domestic) mt 5.9 6.1 5.1 5.4 6.1 11.5 11.7 (2)
Prodeco mt 4.6 4.6 4.4 5.2 5.0 10.2 9.6 6
Cerrejón(2) mt 3.0 3.2 3.3 2.9 3.0 5.9 4.5 31
Total Coal department mt 35.1 36.8 33.5 34.1 37.1 71.2 67.8 5
1 Controlled industrial assets and joint ventures only. Production is on a 100% basis except for joint ventures, where the Group's attributable share of
production is included.
2 The Group's pro-rata share of Cerrejón production (33.3%).
Oil assets
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Gross basis
Equatorial Guinea kbbl 4,556 5,862 6,113 6,304 5,731 12,035 9,942 21
Chad kbbl - - 619 1,067 916 1,983 - n.m.
Total Oil department kbbl 4,556 5,862 6,732 7,371 6,647 14,018 9,942 41
Glencore entitlement interest basis
Equatorial Guinea kbbl 1,020 1,246 1,394 1,368 1,194 2,562 2,159 19
Chad kbbl - - 186 321 276 597 - n.m.
Total Oil department kbbl 1,020 1,246 1,580 1,689 1,470 3,159 2,159 46
Agricultural Products
Processing / production data
Q2 Q3 Q4 Q1 Q2 H1 H1 Change
2013 2013 2013 2014 2014 2014 2013 H1 14 vs
H1 13
%
Farming kt 33 262 236 232 34 266 385 (31)
Crushing kt 943 1,128 966 1,062 1,616 2,678 1,548 73
Long term toll agreement kt 257 151 101 49 157 206 289 (29)
Biodiesel kt 109 181 191 172 169 341 252 35
Rice milling kt 85 83 70 36 91 127 120 6
Wheat milling kt 273 299 267 262 263 525 555 (5)
Sugarcane processing kt 509 933 809 - 723 723 509 42
Total Agricultural products kt 2,209 3,037 2,640 1,813 3,053 4,866 3,658 33
Forward looking statements
This document contains statements that are, or may be deemed to be, "forward looking statements" which are prospective in nature. These forward looking
statements may be identified by the use of forward looking terminology, or the negative thereof such as "plans", "expects" or "does not expect", "is
expected", "continues", "assumes", "is subject to", "budget", "scheduled", "estimates", "aims", "forecasts", "risks", "intends", "positioned", "predicts",
"anticipates" or "does not anticipate", or "believes", or variations of such words or comparable terminology and phrases or statements that certain actions,
events or results "may", "could", "should", "shall", "would", "might" or "will" be taken, occur or be achieved. Such statements are qualified in their entirety by
the inherent risks and uncertainties surrounding future expectations. Forward-looking statements are not based on historical facts, but rather on current
predictions, expectations, beliefs, opinions, plans, objectives, goals, intentions and projections about future events, results of operations, prospects,
financial condition and discussions of strategy.
By their nature, forward looking statements involve known and unknown risks and uncertainties, many of which are beyond Glencore's control. Forward
looking statements are not guarantees of future performance and may and often do differ materially from actual results. Important factors that could cause
these uncertainties include, but are not limited to, those discussed in Glencore's Annual Report 2013.
Neither Glencore nor any of its associates or directors, officers or advisers, provides any representation, assurance or guarantee that the occurrence of the
events expressed or implied in any forward-looking statements in this document will actually occur. You are cautioned not to place undue reliance on these
forward-looking statements which only speak as of the date of this document. Other than in accordance with its legal or regulatory obligations (including
under the UK Listing Rules and the Disclosure and Transparency Rules of the Financial Conduct Authority and the Rules Governing the Listing of
Securities on the Stock Exchange of Hong Kong Limited and the Listing Requirements of the Johannesburg Stock Exchange Limited), Glencore is not
under any obligation and Glencore and its affiliates expressly disclaim any intention, obligation or undertaking to update or revise any forward looking
statements, whether as a result of new information, future events or otherwise. This document shall not, under any circumstances, create any implication
that there has been no change in the business or affairs of Glencore since the date of this document or that the information contained herein is correct as at
any time subsequent to its date.
No statement in this document is intended as a profit forecast or a profit estimate and no statement in this document should be interpreted to mean that
earnings per Glencore share for the current or future financial years would necessarily match or exceed the historical published earnings per Glencore
share.
This document does not constitute or form part of any offer or invitation to sell or issue, or any solicitation of any offer to purchase or subscribe for any
securities. The making of this document does not constitute a recommendation regarding any securities.
SPONSOR
Absa Bank Limited (acting through its Corporate and Investment Banking Division)
Date: 13/08/2014 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.