To view the PDF file, sign up for a MySharenet subscription.

GLENCORE PLC - GLN - 2014 Half-Year Production Report

Release Date: 13/08/2014 08:00
Code(s): GLN     PDF:  
Wrap Text
GLN - 2014 Half-Year Production Report

Glencore plc 
(Incorporated in Jersey under the Companies (Jersey) Law 1991) 
(Registration number 107710) 
JSE Share Code: GLN 
LSE Share Code: GLEN 
HKSE Share Code: 805HK 
ISIN: JE00B4T3BW64 

NEWS RELEASE
Baar, 13 August 2014

2014 Half-Year Production Report

Following completion of the Glencore Xstrata merger on 2 May 2013, production information for all periods covered in
this report has been presented on a combined basis.

Key Highlights:

–      Own sourced copper production up 13% to 741,000 tonnes, primarily driven by Mutanda ramp-up and improved
       production at Collahuasi. Sequential half-yearly production was down 12%, reflecting lower head grades on account
       of mine sequencing (Collahuasi and Antamina) and planned maintenance shuts (Collahuasi, Mount Isa and Mopani).
–      Own sourced zinc production was 650,400 tonnes, down 11%, primarily due to Perseverance and Brunswick mines
       having depleted their reserves in June 2013. Sequential half-yearly production was broadly in line, reflecting Perkoa
       ramp-up, largely offsetting mine sequencing lower grades at Antamina and some opportunistic favouring of 3rd party
       feed at Kazzinc.
–      Own sourced nickel production was 49,100 tonnes, down 8%, reflecting the XNA (Sinclair and Cosmos) and
       Falcondo mines now all being placed on care and maintenance. Sequential half-yearly production was up 8%, due
       to higher production at INO (increased Raglan volumes) and the continued start-up / ramp-up at Koniambo.
–      Own sourced ferrochrome production was 652,000 tonnes, up 16%, reflecting increased capacity due to the prior
       period Eskom power buy-back programme and a ramp-up in production relating to the Lion 2 expansion project.
–      Own sourced coal production was up 5% to 71.2 million tonnes, mainly due to productivity improvements and
       ongoing expansion projects in Australian thermal coal, and a 32 day strike at Cerrejón which impacted Q1 2013.
–      Gross oil E&P production was 14.0 million barrels, up 41%, relating to full period operations at Alen (EG) and Badila
       (Chad) which came on line during 2013.
–      On 31 July 2014, the sale of Las Bambas completed, whereby Glencore received proceeds, net of tax, of
       approximately $6.5 billion, including the reimbursement of capital expenditure and other project costs incurred since
       1 January 2014.
–      On 8 July 2014, Glencore completed the acquisition of Caracal Energy Inc., an oil exploration and development
       company with operations in the Republic of Chad for consideration of approximately $1.6 billion.




For further information please contact:

    Investors                              Media
    Paul Smith                             Charles Watenphul
    t: +41 (0)41 709 24 87                 t: +41 (0)41 709 24 62
    m: +41 (0)79 947 13 48                 m: +41 (0)79 904 33 20
    e: paul.smith@glencore.com             e: charles.watenphul@glencore.com


    Investors                              Investors                                 Finsbury (Media)
    Martin Fewings                         Elisa Morniroli                           Guy Lamming
    t: +41 (0)41 709 28 80                 t: +41 (0)41 709 28 18                    Dorothy Burwell
    m: +41 (0)79 737 56 42                 m: +41 (0)79 833 05 08                    t: +44 (0)20 7251 3801
    e: martin.fewings@glencore.com         e: elisa.morniroli@glencore.com

www.glencore.com

Metals and Minerals

Production from own sources – Total(1)

                                     H1       H1   Change   
                                   2014     2013        %   
Total Copper                kt    741.0    658.0       13   
Total Zinc                  kt    650.4    729.5     (11)   
Total Lead                  kt    148.9    153.2      (3)   
Total Nickel                kt     49.1     53.1      (8)   
Total Gold                 koz      450      478      (6)   
Total Silver               koz   16,621   19,761     (16)   
Total Cobalt                kt      9.8      9.1        8   
Total Ferrochrome           kt      652      561       16   
Total Platinum2            koz       43       44      (2)   
Total Palladium2           koz       24       24        -   
Total Rhodium2             koz        8        8        -   
Total Vanadium Pentoxide   mlb      9.7      9.8      (1)   


Production from own sources – Copper assets(1)

                                                                                            H1       H1   Change   
                                                                                          2014     2013        %   
African Copper (Katanga, Mutanda, Mopani)                                                                    
                                        Total Copper metal(3)                       kt   212.3    171.5       24   
                                        Total Cobalt(4)                             kt     8.1      7.4        9   
Collahuasi(5)                                                                                                      
                                        Copper metal                                kt     4.3      7.1     (39)   
                                        Copper in concentrates                      kt   101.6     60.1       69   
                                        Silver in concentrates                     koz   1,355      747       81   
Antamina(6)                                                                                                          
                                        Copper in concentrates                      kt    61.4     62.2      (1)   
                                        Zinc in concentrates                        kt    27.1     53.2     (49)   
                                        Silver in concentrates                     koz   2,005    2,377     (16)   
Other South America (Alumbrera, Lom as Bayas, Antapaccay, Punitaqui)                                          
                                        Total Copper metal                          kt    35.3     45.4     (22)   
                                        Total Copper in concentrates                kt   138.6    121.8       14   
                                        Total Gold in concentrates and in dore     koz     176      184      (4)   
                                        Total Silver in concentrates and in dore   koz     919    1,148     (20)   
Australia (Ernest Henry, Mount Isa, Cobar)                                                                     
                                        Total Copper in anode                       kt    92.5     88.9        4   
                                        Total Copper in concentrates                kt    23.5     22.6        4   
                                        Total Gold                                 koz      27       16       69   
                                        Total Silver                               koz     625      711     (12)   
Total Copper department                                                                                            
                                        Total Copper                                kt   669.5    579.6       16   
                                        Total Cobalt                                kt     8.1      7.4        9   
                                        Total Zinc                                  kt    27.1     53.2     (49)   
                                        Total Gold                                 koz     203      200        1   
                                        Total Silver                               koz   4,904    4,983      (2)   

Production from own sources – Zinc assets(1)

                                                                                        H1       H1   Change   
                                                                                      2014     2013        %   
Kazzinc                                                                                                        
                                        Zinc metal                             kt     99.2    105.6      (6)   
                                        Lead metal                             kt     11.5     15.6     (26)   
                                        Copper metal                           kt     19.1     26.8     (29)   
                                        Gold                                  koz      246      277     (11)   
                                        Silver                                koz    1,889    2,848     (34)   
Australia (Mount Isa, McArthur River)                                                                        
                                        Total Zinc in concentrates             kt    302.2    298.4        1   
                                        Total Lead in concentrates             kt    107.0     97.8        9   
                                        Total Silver in concentrates          koz    4,149    3,740       11   
North America (Matagami, Kidd, Brunswick)                                                                
                                        Total Zinc in concentrates             kt     69.0    131.6     (48)   
                                        Total Lead in concentrates             kt        -     13.5    (100)   
                                        Total Copper in concentrates           kt     23.0     24.4      (6)   
                                        Total Silver in concentrates          koz      891    3,371     (74)   
Other Zinc (AR Zinc, Los Quenuales, Sinchi Wayra, Rosh Pinah, Perkoa)                                    
                                        Zinc metal                             kt     10.2     16.0     (36)   
                                        Zinc in concentrates                   kt    142.7    124.7       14   
                                        Lead metal                             kt      5.4      4.9       10   
                                        Lead in concentrates                   kt     25.0     21.4       17   
                                        Copper in concentrates                 kt      1.6      0.8      100   
                                        Silver metal                          koz      292      324     (10)   
                                        Silver in concentrates                koz    4,496    4,495        -   
Total Zinc department                                                                                          
                                        Total Zinc                             kt    623.3    676.3      (8)   
                                        Total Lead                             kt    148.9    153.2      (3)   
                                        Total Copper                           kt     43.7     52.0     (16)   
                                        Total Gold                            koz      246      277     (11)   
                                        Total Silver                          koz   11,717   14,778     (21)   


Production from own sources – Nickel assets(1)

                                                                              H1     H1   Change   
                                                                            2014   2013        %   
Integrated Nickel Operations (Sudbury, Raglan, Nikkelverk)                                     
                                       Total Nickel metal              kt   27.1   23.6       15   
                                       Total Nickel in concentrates    kt    0.3    0.3        -   
                                       Total Copper metal              kt    8.0    8.6      (7)   
                                       Total Copper in concentrates    kt   19.8   17.6       13   
                                       Total Cobalt metal              kt    0.4    0.3       33   
Australia (Murrin Murrin, XNA)                                                                     
                                       Total Nickel metal              kt   17.6   19.1      (8)   
                                       Total Nickel in concentrates    kt      -    3.1    (100)   
                                       Total Copper in concentrates    kt      -    0.2    (100)   
                                       Total Cobalt metal              kt    1.3    1.3        -   
                                       Total Cobalt in concentrates    kt      -    0.1    (100)   
Falcondo                               Nickel in ferronickel           kt      -    7.0    (100)   
Koniambo                               Nickel in ferronickel           kt    4.1      -     n.m.   
Total Nickel department                                                                            
                                       Total Nickel                    kt   49.1   53.1      (8)   
                                       Total Copper                    kt   27.8   26.4        5   
                                       Total Cobalt                    kt    1.7    1.7        - 

Production from own sources – Ferroalloys assets1                                          
                                                                              H1     H1   Change   
                                                                            2014   2013        %   
Ferrochrome(7)                                                         kt    652    561       16   
PGM(8)                                 Platinum                       koz     43     44      (2)   
                                       Palladium                      koz     24     24        -   
                                       Rhodium                        koz      8      8        -   
                                       Gold                           koz      1      1        -   
                                       4E                             koz     76     77      (1)   
Vanadium Pentoxide                                                    mlb    9.7    9.8      (1)   


Total production – Custom metallurgical assets(1)

                                                                             H1      H1   Change   
                                                                           2014    2013        %   
Copper (Altonorte, Townsville, Pasar, Horne, CCR)                                              
                                        Copper metal                 kt   345.1   373.7      (8)   
                                        Custom copper anode          kt   266.0   257.0        4   
Zinc (Portovesme, San Juan de Nieva, Nordenham, Northfleet)                                  
                                        Zinc metal                   kt   388.2   372.7        4   
                                        Lead metal                   kt   100.5    78.6       28   
                                        Silver                      koz   5,165   3,280       57   
Ferroalloys                                                                                        
                                        Ferromanganese               kt      57      52       10   
                                        Silicon Manganese            kt      52      42       24   
Aluminium (Sherwin Alumina)                                                                        
                                        Alumina                      kt     776     777        -   


(1)   Controlled industrial assets and joint ventures only. Production is on a 100% basis, except as stated.
(2)   Relating to the PGM business within ferroalloys only.
(3)   Copper metal includes copper contained in copper concentrates and blister.
(4)   Cobalt contained in concentrates and hydroxides.
(5)   The Group's pro-rata share of Collahuasi production (44%).
(6)   The Group's pro-rata share of Antamina production (33.75%).
(7)   The Group's 79.5% share of the Glencore-Merafe Chrome Venture.
(8)   Consolidated 100% of Eland and 50% of Mototolo.

Selected average commodity prices

                                                                         H1       H1   Change   
                                                                       2014     2013        %   
S&P GSCI Industrial Metals Index                                        343      365      (6)   
LME (cash) copper price ($/t)                                         6,916    7,543      (8)   
LME (cash) zinc price ($/t)                                           2,049    1,936        6   
LME (cash) lead price ($/t)                                           2,100    2,172      (3)   
LME (cash) nickel price ($/t)                                        16,534   16,137        2   
Gold price ($/oz)                                                     1,291    1,524     (15)   
Silver price ($/oz)                                                      20       27     (26)   
Metal Bulletin cobalt price 99.3% ($/lb)                                 14       12       17   
LME (cash) aluminium price ($/t)                                      1,755    1,919      (9)   
Metal Bulletin alumina price ($/t)                                      323      334      (3)   
Metal Bulletin ferrochrome 6-8% C basis 60% Cr, max 1.5% Si (¢/lb)      106      102        4   
Platinum price ($/oz)                                                 1,438    1,549      (7)   
Iron ore (Platts 62% CFR North China) price ($/DMT)                     111      137     (19)   


OPERATING HIGHLIGHTS

Copper assets
Total own sourced copper production was 741,000 tonnes, 13% (83,000 tonnes) higher than the comparable period. The
increase mainly relates to the ramp-up in production at Mutanda, Katanga and Antapaccay, plus improved production at
Collahuasi as the operation continues to process at the higher levels achieved during H2 2013, following the restart of
the SAG mill.

African copper
African copper production was 212,300 tonnes, 24% (40,800 tonnes) ahead of the comparable period. The increase
primarily relates to the ramp up at Mutanda, which produced 98,600 tonnes, an increase of 37,400 tonnes (61%) and
reflects the recent expansion to 200,000 tonnes per annum. Katanga also increased production by 12,300 tonnes (20%)
relating to the ongoing commissioning of phase IV. Katanga production is expected to ramp up further during the rest of
2014 as phase V is completed and further operational improvements, including adding some back-up power generator
capacity, are implemented.

Cobalt production was 8,100 tonnes, 9% higher than the comparable period and relates to the Mutanda expansion.

Collahuasi
The group's share of production was 105,900 tonnes, 58% (38,700 tonnes) above the comparable period. The increase
in production reflects a continuation of the high levels of processing seen in H2 2013 following the SAG mill restart and
higher head grades.

Antamina
The group's share of copper production was 61,400 tonnes, in line with the comparable period. Copper production has
benefited from higher milled volumes, offset by lower grades and recoveries in Q2 2014, due to the processing of long
term lower grade stockpiles.

Zinc production was 27,100 tonnes, 49% lower than the comparable period and relates to the mining of higher grade
copper / lower grade zinc areas during the period.

Other South America
Copper production from Other South America was 173,900 tonnes, 4% (6,700 tonnes) higher than the comparable
period. The increase relates to higher milling rates at Antapaccay, partially offset by the closure of the Tintaya SX/EW
operations in October 2013.

Gold production was 176,000 oz, 4% lower than the comparable period, relating to expected lower head grades at
Antapaccay.

Australia
Australia copper production was 116,000 tonnes, 4% (4,500 tonnes) higher than the comparable period, relating to
higher own sourced production at the Mount Isa smelter due to the production of more own sourced concentrates.
Gold production was 27,000 oz, 69% higher than the comparable period relating to the treatment of a higher proportion
of Ernest Henry concentrate (containing gold) versus Mount Isa concentrate (containing no gold) than in H1 2013.

Custom metallurgical assets
Custom copper cathode production was 345,100 tonnes, 8% (28,600 tonnes) lower than the comparable period. The
reduction mainly relates to lost production at Pasar due to the damage caused by typhoon Haiyan, offset by higher
throughput at Townsville. Pasar restarted production at the end of Q1 2014, ramping up during Q2 2014.

Custom copper anode production was 266,000 tonnes, 4% higher than the comparable period, relating to higher
throughput at Horne.

Zinc assets
Total own sourced zinc production was 650,400 tonnes, 11% (79,100 tonnes) below the comparable period. The
reduction mainly relates to the end of mine closure of the Perseverance and Brunswick mines in June 2013 and, to a
lesser degree, the lower grades being mined at Antamina in the current year.

Total own sourced lead production was 148,900 tonnes, 3% (4,300 tonnes) lower than the comparable period. The
principal movements relates to the lost production from the closure of Brunswick (13,500 tonnes) as noted above, offset
by growth (11,700 tonnes) at the Lady Loretta mine (part of Mount Isa complex).

Kazzinc
Zinc production from own sources was 99,200 tonnes, 6% below the comparable period, reflecting an opportunistic
decision (cost savings etc.) to treat more third party sulphide material and therefore less own source oxide ore. Total zinc
production including third party material was up 3% at 151,200 tonnes.

Gold production from own sources was 246,000 oz, 11% lower than the comparable period due to the decision to once
again treat less own source concentrates in favour of more third party precious metal containing material. Own sourced
concentrate production (and gold contained) was in line with the comparable period, with the untreated concentrates
remaining in inventory for treatment in future periods. Total gold production (including third party material) was only
slightly less than the comparable period.

Lead production from own sources was 11,500 tonnes, down 26% versus the comparable period and relates to lower
work in progress being processed at the smelters in 2014 and an expected small reduction in head grades. On a total
metal basis (including third party material), lead production was 61,500 tonnes, up 41% on the comparable period and
reflects the higher output of the new Isa lead smelter.

Copper production from own sources was 19,100 tonnes, down 29% versus the comparable period, relating to temporary
repair work, plus the impact of processing less work in progress at the smelters in 2014. Total copper metal production
(including third party material), was similarly impacted, down 19% over the comparable period.

Australia
Australia zinc production was 302,200 tonnes, in line with the comparable period. This relates to higher production at
Mount Isa (growth from the Lady Loretta expansion), partially offset by a reduction at McArthur River as a result of lower
head grades due to mine sequencing and minor disruptions associated with the expansion project.
Lead production was 107,000 tonnes, 9% higher than the comparable period. The increase relates to the expansion at
Lady Loretta and strong production at Black Star (both Mount Isa), offset by lower production at McArthur River (noted
above).

North America
North America zinc produced 69,000 tonnes of zinc, 48% lower than the comparable period and no lead, reflecting the
end of mine life closures of Perseverance and Brunswick in June 2013. Excluding the impact of the closed mines, North
America zinc increased production by 25,100 tonnes, reflecting the ramp-up of the Bracemac mine (started production in
May 2013), offset by lower production from Kidd due to mining restrictions as a result of temporary stope unavailability
and a focus on higher copper grade areas.

Copper production was 23,000 tonnes, 6% lower than the comparable period, relating to lost copper production from the
closed Perseverance mine, offset by mining higher copper grade areas at the Kidd mine.

Other Zinc
The Other zinc asset group produced 152,900 tonnes, 12,200 tonnes (9%) above the comparable period, relating to the
ramp-up of Perkoa (24,900 tonnes), offset by net lower production from the other assets, including the maintenance
smelter shut down at AR Zinc.

Lead production was 30,400 tonnes, 16% (4,100 tonnes) above the prior year period, mainly relating to higher production
from AR Zinc due to increasing the milling capacity and higher head grades.

European custom metallurgical assets
Custom zinc and lead production were 388,200 tonnes and 100,500 tonnes, up 4% and 28% respectively versus the
prior year period. The increases mainly relate to the full period contribution from Portovesme's zinc and lead plants
following the respective SX plant commissioning and Kivcet plant restart in 2013.

Nickel assets
Own sourced nickel production was 49,100 tonnes, 4,000 tonnes (8%) lower than the comparable period. The decline
relates mainly to the XNA (Cosmos and Sinclair) and Falcondo operations, which together produced 10,100 tonnes in 
H1 2013, subsequently being placed into care and maintenance. The lost production was in part offset by production from
Koniambo as it ramps up and production growth at INO, due to increased output from the Raglan mine.

Integrated Nickel Operations ("INO")
INO's own sourced nickel production was 27,400 tonnes, 15% (3,500 tonnes) higher than the comparable period, due to
a higher proportion of own sourced feed (total nickel production was 44,700 tonnes, broadly in line with the comparable
period). The higher proportion of own source feed was driven primarily by increased production from the Raglan mine.

Own sourced copper production was 27,800 tonnes, 6% higher than the comparable period. The increase relates to the
maintenance shut at the Strathcona mill in Q1 2013, which resulted in a reduction in the quantity of Sudbury ore being
processed and better processing rates in general.

Australia
Own sourced nickel production was 17,600 tonnes, 21% below the comparable period. The reduction relates to the
Cosmos and Sinclair mines being placed in care and maintenance and a slight decline in average ore grades at Murrin
Murrin. Total packaged nickel at Murrin Murrin (including third party material) was 2% higher than the comparable period
due to higher throughput at the plant.

Koniambo
Koniambo production was 4,100 tonnes of nickel in ferronickel during the period. Ramp-up activities remain ongoing with
full annualised production expected in 2016.

Ferroalloys assets
Ferrochrome
Attributable ferrochrome production was 652,000 tonnes, 16% (91,000 tonnes) above the comparable period. The
increase relates to the non-recurring Eskom power buy-back programme that occurred during 2013 and the ramp up in
production of Lion phase 2 (furnaces C and D started production in April and June 2014 respectively).

Platinum Group Metals ("PGM")
PGM H1 2014 production was 76,000 oz, consistent with the comparable period.

Vanadium
Vanadium production was 9.7 million lbs, in line with the comparable period.

Manganese
Total manganese (ferromanganese and silicon manganese) production was 109,000 tonnes, 16% higher than the
comparable period. The increase relates to higher throughput in Norway (silicon manganese) due to efficiency
improvements and demand led increases in France (ferromanganese).

Aluminium assets
Sherwin Alumina
Alumina production was 776,000 tonnes, broadly in line with the comparable period, notwithstanding significant power
and steam outages caused by the third party energy supplier during 2014.

Energy Products

Production from own sources

Coal assets(1)                                                        
                                               H1     H1   Change   
                                             2014   2013        %   
Australian coking coal                  mt    2.9    4.0     (28)   
Australian semi-soft coal               mt    1.8    2.3     (22)   
Australian thermal coal (export)        mt   26.0   23.3       12   
Australian thermal coal (domestic)      mt    2.7    2.6        4   
South African thermal coal (export)     mt   10.2    9.8        4   
South African thermal coal (domestic)   mt   11.5   11.7      (2)   
Prodeco                                 mt   10.2    9.6        6   
Cerrejón(2)                             mt    5.9    4.5       31   
Total Coal department                   mt   71.2   67.8        5   


(1) Controlled industrial assets and joint ventures only. Production is on a 100% basis except for joint ventures, where the Group's attributable share of
    production is included.
(2) The Group's pro-rata share of Cerrejón production (33.3%).

Oil assets                                                                                              
                                                                                  H1      H1   Change   
                                                                                2014    2013        %   
Gross basis                                                                                             
Equatorial Guinea                                                      kbbl   12,035   9,942       21   
Chad                                                                   kbbl    1,983       -     n.m.   
Total Oil department                                                   kbbl   14,018   9,942       41   
Glencore entitlement interest basis                                                                     
Equatorial Guinea                                                      kbbl    2,562   2,159       19   
Chad                                                                   kbbl      597       -     n.m.   
Total Oil department                                                   kbbl    3,159   2,159       46  

Selected average commodity prices                                                                       
                                                                                  H1      H1   Change   
                                                                                2014    2013        %   
S&P GSCI Energy Index                                                            338     327        3   
Coal API4 ($/t)                                                                   76      84     (10)   
Coal McCloskey Newcastle (6,000 kcal NAR) ($/t)                                   75      88     (15)   
Australian coking coal average realised export price ($/t)                       123     155     (21)   
Australian semi-soft coal average realised export price ($/t)                     98     118     (17)   
Australian thermal coal average realised export price ($/t)                       75      86     (13)   
Australian thermal coal average realised domestic price ($/t)                     31      47     (34)   
South African thermal coal average realised export price ($/t)                    72      83     (13)   
South African thermal coal average realised domestic price ($/t)                  23      27     (15)   
Prodeco (Colombia) thermal coal average realised export price ($/t)               78      88     (11)   
Cerrejón (Colombia) thermal coal average realised export price ($/t)              68      76     (11)   
Oil price – Brent ($/bbl)                                                        109     108        1   


OPERATING HIGHLIGHTS

Coal assets
Total own sourced production was 71.2 million tonnes, 5% higher than the comparable period. The increase arises from
Australian thermal coal, due to productivity improvements and ongoing expansion projects, and Cerrejón which was
impacted by a 32 day strike in Q1 2013. These increases were, in part, offset by a reduction in coking coal production
due to a decision to scale back production from higher cost mines and areas.

Australian coking
Australian coking coal production was 2.9 million tonnes, 28% lower than the comparable period. The decrease relates to
cost reduction initiatives, which led to mine plan and / or roster changes at Newlands, Oaky Creek and Collinsville, the
latter also being affected by industrial issues. Volumes were also temporarily impacted when mining through a fault zone
at Oaky North.

Australian thermal and semi-soft
Australian thermal and semi-soft coal production was 30.5 million tonnes, 8% higher than the comparable period. The
increase relates to the production ramp up at Ravensworth North and Rolleston, productivity gains at Ulan underground
and Bulga and the commencement of longwall operations at Ulan West.

South African thermal
South African thermal production was 21.7 million tonnes, in line with the comparable period. This reflects the opening of
Wonderfontein open cut mine in Q1 2014, offset by various operational challenges, including wet weather and strike
action at Goedgevonden, the closure of Klippan and Wonderfontein underground mines at the end of 2013 and the
closure of the Middelburg Steelcoal pit in Q1 2014.

Prodeco
Prodeco production was 10.2 million tonnes, 6% higher than the comparable period, relating to the ongoing expansion
project, plus productivity improvements at Calenturitas and improved equipment availability across the operations.

Cerrejón
Glencore's share of Cerrejón production was 5.9 million tonnes, 31% (1.4 million tonnes) higher than the comparable
period. The increase reflects the impact of the 32 day strike that occurred in Q1 2013.

Oil E&P assets
H1 2014 gross oil production was 14.0 million barrels, 41% (4.1 million barrels) above the comparable period, relating to
Alen (Equatorial Guinea) and Badila (Chad), which started production at the end of June and September 2013
respectively.

Agricultural Products

Processing / production data                                      
                                            H1      H1   Change   
                                          2014    2013        %   
Farming                             kt     266     385     (31)   
Crushing                            kt   2,678   1,548       73   
Long term toll agreement            kt     206     289     (29)   
Biodiesel                           kt     341     252       35   
Rice milling                        kt     127     120        6   
Wheat milling                       kt     525     555      (5)   
Sugarcane processing                kt     723     509       42   
Total agricultural products         kt   4,866   3,658       33 

Selected average commodity prices                                 
                                            H1      H1   Change   
                                          2014    2013        %   
S&P GSCI Agriculture Index                 384     434     (12)   
CBOT wheat price (US¢/bu)                  635     716     (11)   
CBOT corn no.2 price (US¢/bu)              466     688     (32)   
CBOT soya beans (US¢/bu)                 1,414   1,459      (3)   
ICE cotton price (US¢/lb)                   88      84        5   
NYMEX sugar # 11 price (US¢/lb)             17      18      (6)   


OPERATING HIGHLIGHTS

Agriculture produced / processed 4.9 million tonnes in H1 2014, 33% higher than the comparable period. The increase in
volumes mainly relates to the continued ramp up at Timbues (Argentinean crush plant), including the impact of Glencore
increasing its stake from 33% to 50%, plus higher sugarcane processing volumes, reflecting the increase in processing
capacity, as part of Rio Vermelho's ongoing expansion.

Appendix – Q2 2013 to Q2 2014

Metals and Minerals

Production from own sources – Total(1)

Production from own sources – Total
                                                Q2      Q3      Q4      Q1      Q2       H1      H1     Change
                                              2013    2013    2013    2014    2014     2014    2013   H1 14 vs
                                                                                                        H1 13
                                                                                                            %
Total Copper                          kt     350.3   412.9   425.8   381.9   359.1    741.0   658.0        13
Total Zinc                            kt     357.1   332.2   336.8   306.4   344.0    650.4   729.5      (11)
Total Lead                            kt      74.1    80.7    81.1    79.0    69.9    148.9   153.2       (3)
Total Nickel                          kt      26.8    22.5    22.8    22.3    26.8     49.1    53.1       (8)
Total Gold                            koz      254     278     267     234     216      450     478       (6)
Total Silver                          koz   10,178   9,652   9,843   8,768   7,853   16,621  19,761      (16)
Total Cobalt                          kt       5.2     5.6     4.7     4.6     5.2      9.8     9.1         8
Total Ferrochrome                     kt       301     332     345     335     317      652     561        16
Total Platinum(2)                     koz       23      24      22      21      22       43      44       (2)
Total Palladium(2)                    koz       12      14      12      12      12       24      24         -
Total Rhodium(2)                      koz        4       4       3       4       4        8       8         -
Total Vanadium Pentoxide              mlb      4.2     6.1     5.7     5.5     4.2      9.7     9.8       (1)

Production from own sources – Copper assets(1)

                                                                           Q2      Q3      Q4      Q1      Q2      H1      H1    Change
                                                                         2013    2013    2013    2014    2014    2014    2013  H1 14 vs
                                                                                                                                  H1 13
                                                                                                                                      %
African Copper (Katanga, Mutanda, Mopani, Sable)
Katanga                       Copper metal(3)                     kt     31.7    34.5    41.4    31.6    41.0    72.6    60.3        20
                              Cobalt                              kt      0.7     0.8     0.5     0.5     0.5     1.0     1.0         -
Mutanda                       Copper metal(3)                     kt     31.4    40.3    49.1    47.1    51.5    98.6    61.2        61
                              Cobalt(4)                           kt      3.6     3.8     3.5     3.3     3.8     7.1     6.4        11
Mopani                        Copper metal                        kt     24.8    30.4    31.4    27.7    13.4    41.1    50.0      (18)


African Copper - total production including third party feed
Mopani                        Copper metal                        kt     53.6    55.9    53.6    48.5    31.9    80.4   102.5      (22)
Sable                         Copper metal                        kt      3.7     3.7     3.7     2.5     1.3     3.8     7.2      (47)
                              Cobalt(3)                           kt      0.1     0.1     0.2     0.1     0.2     0.3     0.1       200


                              Total Copper metal(3)               kt     87.9   105.2   121.9   106.4   105.9   212.3   171.5        24
                              Total Cobalt(4)                     kt      4.3     4.6     4.0     3.8     4.3     8.1     7.4         9


Collahuasi(5)                 Copper metal                        kt      3.7     3.0     2.4     2.3     2.0     4.3     7.1      (39)
                              Copper in concentrates              kt     34.1    60.6    62.4    50.0    51.6   101.6    60.1        69
                              Silver in concentrates              koz    420     663     807     675     680    1,355    747         81


Antamina(6)                   Copper in concentrates              kt     36.1    43.4    43.9    34.2    27.2    61.4    62.2       (1)
                              Zinc in concentrates                kt     30.5    14.9    19.8    11.1    16.0    27.1    53.2      (49)
                              Silver in concentrates              koz   1,441   1,339   1,500   1,068     937   2,005   2,377      (16)

Other South America (Alumbrera, Lomas Bayas, Antapaccay, Punitaqui)

Alumbrera                    Copper in concentrates               kt     26.0    26.0    34.8    26.1    23.3    49.4    48.8         1   
                             Gold in concentrates and in dore     koz      80      77      90      81      65     146     146         -   
                             Silver in concentrates and in dore   koz     409     350     177     180     179     359     618      (42)   
Lomas Bayas                  Copper metal                         kt     18.8    18.4    18.2    18.0    17.3    35.3    37.6       (6)   
Antapaccay                   Copper metal                         kt      4.2     4.1     0.3       -       -       -     7.8     (100)   
                             Copper in concentrates               kt     33.5    39.9    31.4    37.3    46.0    83.3    67.7        23   
                             Gold in concentrates                 koz      19      30      11      12      18      30      38      (21)   
                             Silver in concentrates               koz     242     280     188     220     301     521     478         9   


                                                                                  Q2     Q3     Q4     Q1     Q2     H1      H1     Change
                                                                                2013   2013   2013   2014   2014   2014    2013   H1 14 vs
                                                                                                                                     H1 13
                                                                                                                                         %
Punitaqui                      Copper in concentrates                     kt     2.5    3.3    3.2    3.3    2.6     5.9     5.3        11
                               Silver in concentrates                     koz     22     24     25     21     18      39      52      (25)


Punitaqui - total production including third party feed
                               Copper in concentrates                     kt     2.6    3.3    3.3    3.3    2.6     5.9     5.4        9
                               Silver in concentrates                     koz     23     25     25     22     18      40      53      (25)


                               Total Copper metal                         kt    23.0   22.5   18.5   18.0   17.3    35.3    45.4      (22)
                               Total Copper in concentrates               kt    62.0   69.2   69.4   66.7   71.9   138.6   121.8        14
                               Total Gold in concentrates and in dore     koz     99    107    101     93     83     176     184       (4)
                               Total Silver in concentrates and in dore   koz    673    654    390    421    498     919   1,148      (20)

Australia (Ernest Henry, Mount Isa, Cobar)

Ernest Henry mine,             Copper anode                                kt   51.2   55.0   57.2   54.6   37.9    92.5    88.9         4   
Mt Isa mine and smelter        Copper in concentrates                      kt      -    2.9      -      -      -       -       -      n.m.   
                               Gold in anode                              koz      8     16     18     15     12      27      16        69   
                               Gold in concentrates                       koz      -      1      -      -      -       -       -      n.m.   
                               Silver in anode                            koz    265    312    305    241    172     413     493      (16)   
                               Silver in concentrates                     koz      -      -     11      -      -       -       -      n.m.   


Ernest Henry mine, Mount Isa mine and smelter - total production including third party feed

                               Copper anode                                kt   53.6   57.6   57.2   54.7   38.9    93.6    93.0         1   
                               Copper in concentrates                      kt      -    2.9      -      -      -       -       -      n.m.   
                               Gold in anode                              koz     10     16     18     15     12      27      18        50   
                               Gold in concentrates                       koz      -      1      -      -      -       -       -      n.m.   
                               Silver in anode                            koz    265    312    305    241    172     413     493      (16)   
                               Silver in concentrates                     koz      -      -     11      -      -       -       -      n.m.   
Cobar                          Copper in concentrates                      kt   11.4   11.5   11.5   12.6   10.9    23.5    22.6         4   
                               Silver in concentrates                     koz    116    103    107    113     99     212     218       (3)   
                               Total Copper in anode                       kt   51.2   55.0   57.2   54.6   37.9    92.5    88.9         4   
                               Total Copper in concentrates                kt   11.4   14.4   11.5   12.6   10.9    23.5    22.6         4   
                               Total Gold                                 koz      8     17     18     15     12      27      16        69   
                               Total Silver                               koz    381    415    423    354    271     625     711      (12)   
Total Copper department                                                                                                                      
                               Total Copper                                kt  309.4  373.3  387.2  344.8  324.7   669.5   579.6        16   
                               Total Cobalt                                kt    4.3    4.6    4.0    3.8    4.3     8.1     7.4         9   
                               Total Zinc                                  kt   30.5   14.9   19.8   11.1   16.0    27.1    53.2      (49)   
                               Total Gold                                 koz    107    124    119    108     95     203     200         1   
                               Total Silver                               koz  2,915  3,071  3,120  2,518  2,386   4,904   4,983       (2)   


Production from own sources – Zinc assets(1)

                                                                Q2      Q3      Q4      Q1     Q2      H1      H1     Change
                                                              2013    2013    2013    2014   2014    2014    2013   H1 14 vs
                                                                                                                       H1 13
                                                                                                                           %
Kazzinc
                        Zinc metal                     kt     53.0    54.7    55.9    49.2   50.0    99.2   105.6        (6)
                        Lead metal                     kt      7.4     7.0     7.2     7.4    4.1    11.5    15.6       (26)
                        Copper metal                   kt     13.4    12.4    11.7    10.8    8.3    19.1    26.8       (29)
                        Gold                           koz     146     154     148     126    120     246     277       (11)
                        Silver                         koz   1,022   1,146   1,257   1,132    757   1,889   2,848       (34)

Kazzinc - total production including third party feed

                        Zinc metal                      kt    75.0    76.1    77.1    75.3   75.9   151.2   147.2          3   
                        Lead metal                      kt    21.7    23.2    23.9    32.2   29.3    61.5    43.5         41   
                        Copper metal                    kt    16.0    15.0    16.3    15.4    9.8    25.2    31.1       (19)   
                        Gold                           koz     174     190     190     161    159     320     328        (2)   
                        Silver                         koz   4,772   5,000   4,599   5,014  6,065  11,079   9,082         22   


Australia (Mount Isa, McArthur River)

Mount Isa               Zinc in concentrates            kt   103.2   106.4   102.7   100.8  102.9   203.7   196.0          4   
                        Lead in concentrates            kt    39.0    46.5    46.8    47.2   39.0    86.2    74.5         16   
                        Silver in concentrates         koz   1,435   2,057   1,927   2,054  1,461   3,515   2,886         22   
McArthur River          Zinc in concentrates            kt    47.5    53.6    47.3    45.2   53.3    98.5   102.4        (4)   
                        Lead in concentrates            kt    11.4    11.6    10.9     9.3   11.5    20.8    23.3       (11)   
                        Silver in concentrates         koz     392     347     379     297    337     634     854       (26)   
                        Total Zinc in concentrates      kt   150.7   160.0   150.0   146.0  156.2   302.2   298.4          1   
                        Total Lead in concentrates      kt    50.4    58.1    57.7    56.5   50.5   107.0    97.8          9   
                        Total Silver in concentrates   koz   1,827   2,404   2,306   2,351  1,798   4,149   3,740         11   


North America (Matagami, Kidd, Brunswick, CEZ Refinery)

Matagami/Perseverance   Zinc in concentrates            kt    18.0    15.1    20.0    17.9   19.0   36.9     39.4        (6)   
                        Copper in concentrates          kt     2.2     2.0     2.7     2.1    2.5    4.6      4.4          5   
Kidd                    Zinc in concentrates            kt    19.3    13.6    14.0    10.1   22.0   32.1     40.2       (20)   
                        Copper in concentrates          kt     9.9    10.6     9.3    10.3    8.1   18.4     17.0          8   
                        Silver in concentrates         koz   1,153     606     572     385    506    891    2,056       (57)   
Brunswick Mine          Zinc in concentrates            kt     9.2       -       -       -      -      -     52.0      (100)   
                        Lead in concentrates            kt     2.4       -       -       -      -      -     13.5      (100)   
                        Copper in concentrates          kt     0.3       -       -       -      -      -      3.0      (100)   
                        Silver in concentrates         koz     658       -       -       -      -      -    1,315      (100)   
                        Total Zinc in concentrates      kt    46.5    28.7    34.0    28.0   41.0   69.0    131.6       (48)   
                        Total Lead in concentrates      kt     2.4       -       -       -      -      -     13.5      (100)   
                        Total Copper in concentrates    kt    12.4    12.6    12.0    12.4   10.6   23.0     24.4        (6)   
                        Total Silver in concentrates   koz   1,811     606     572     385    506    891    3,371       (74)   
 

North America - total production including third party feed

Brunswick Mine           Zinc in concentrates           kt    13.3       -       -       -       -     -     56.1      (100)   
                         Lead in concentrates           kt     3.5       -       -       -       -     -     14.6      (100)   
                         Copper in concentrates         kt     0.3       -       -       -       -     -      3.0      (100)   
                         Silver in concentrates        koz     745       -       -       -       -     -    1,402      (100)   
Brunswick Smelter        Lead metal                     kt    18.0    19.2    20.1    18.7    17.5  36.2     36.0          1   
                         Silver metal                  koz   4,022   4,098   4,555   3,120   2,852 5,972    7,493       (20)   
CEZ Refinery(7)          Zinc metal                     kt    17.1    15.3    16.8    14.9    15.6  30.5     34.2       (11)   


                                                                           Q2      Q3      Q4      Q1      Q2      H1      H1    Change
                                                                         2013    2013    2013    2014    2014    2014    2013  H1 14 vs
                                                                                                                                  H1 13
                                                                                                                                      %
Other Zinc (AR Zinc, Los Quenuales, Sinchi Wayra, Rosh Pinah, Perkoa)
                          Zinc metal                            kt        9.5     7.5     6.2     1.9     8.3    10.2    16.0      (36)
                          Zinc in concentrates                  kt       66.9    66.4    70.9    70.2    72.5   142.7   124.7        14
                          Lead metal                            kt        2.8     3.1     3.0     2.4     3.0     5.4     4.9        10
                          Lead in concentrates                  kt       11.1    12.5    13.2    12.7    12.3    25.0    21.4        17
                          Copper in concentrates                kt        0.3     0.7     0.6     0.8     0.8     1.6     0.8       100
                          Silver metal                          koz       177     161     185     133     159     292     324      (10)
                          Silver in concentrates                koz     2,426   2,264   2,403   2,249   2,247   4,496   4,495         -

Other Zinc - total production including third party feed

                        Zinc metal                               kt      10.5    10.9     9.5     2.4     9.3    11.7    17.5      (33)   
                        Zinc in concentrates                     kt      66.9    66.4    70.9    70.2    72.5   142.7   124.7        14   
                        Lead metal                               kt       2.8     3.1     3.0     2.4     3.0     5.4     4.9        10   
                        Lead in concentrates                     kt      11.1    12.5    13.2    12.7    12.3    25.0    21.4        17   
                        Copper in concentrates                   kt       0.3     0.7     0.6     0.8     0.8     1.6     0.8       100   
                        Silver metal                            koz       177     161     185     133     159     292     324      (10)   
                        Silver in concentrates                  koz     2,426   2,264   2,403   2,249   2,247   4,496   4,495         -   
Total Zinc department                                                                                                   
                        Total Zinc                               kt     326.6   317.3   317.0   295.3   328.0   623.3   676.3       (8)   
                        Total Lead                               kt      74.1    80.7    81.1    79.0    69.9   148.9   153.2       (3)   
                        Total Copper                             kt      26.1    25.7    24.3    24.0    19.7    43.7    52.0      (16)   
                        Total Gold                              koz       146     154     148     126     120     246     277      (11)   
                        Total Silver                            koz     7,263   6,581   6,723   6,250   5,467  11,717  14,778      (21)   


Production from own sources – Nickel assets1
                                                                Q2     Q3     Q4     Q1     Q2     H1     H1    Change
                                                              2013   2013   2013   2014   2014   2014   2013  H1 14 vs
                                                                                                                 H1 13
                                                                                                                     %

Integrated Nickel Operations (Sudbury, Raglan, Nikkelverk)

                          Total Nickel metal             kt   11.3   10.1   13.4   13.3   13.8   27.1   23.6        15   
                          Total Nickel in concentrates   kt    0.1    0.1    0.1    0.2    0.1    0.3    0.3         -   
                          Total Copper metal             kt    4.2    3.7    4.4    3.8    4.2    8.0    8.6       (7)   
                          Total Copper in concentrates   kt   10.5   10.1    9.9    9.3   10.5   19.8   17.6        13   
                          Total Cobalt metal             kt    0.2    0.2    0.2    0.2    0.2    0.4    0.3        33   

Integrated Nickel Operations - total production including third party feed

                          Total Nickel metal             kt   22.5   23.0   23.2   21.7   22.6   44.3   44.8       (1)   
                          Total Nickel in concentrates   kt    0.2    0.1    0.2    0.2    0.2    0.4    0.4         -   
                          Total Copper metal             kt    9.0    9.2    9.9    8.7    7.8   16.5   18.4      (10)   
                          Total Copper in concentrates   kt   12.9   12.5   12.3   11.7   13.5   25.2   21.5        17   
                          Total Cobalt metal             kt    0.8    0.8    1.0    0.8    0.9    1.7    1.6         6   

Australia (Murrin Murrin, XNA)

                          Total Nickel metal             kt   10.4    9.3    7.5    7.8    9.8   17.6   19.1       (8)   
                          Total Nickel in concentrates   kt    1.7    1.0      -      -      -      -    3.1     (100)   
                          Total Copper in concentrates   kt    0.1    0.1      -      -      -      -    0.2     (100)   
                          Total Cobalt metal             kt    0.7    0.8    0.5    0.6    0.7    1.3    1.3         -   
                          Total Cobalt in concentrates   kt      -      -      -      -      -      -    0.1     (100)   

Australia - total production including third party feed

                          Total Nickel metal             kt   11.6   11.2    8.9    9.4   12.2   21.6   21.2         2   
                          Total Nickel in concentrates   kt    1.7    1.0      -      -      -      -    3.1     (100)   
                          Total Copper in concentrates   kt    0.1    0.1      -      -      -      -    0.2     (100)   
                          Total Cobalt metal             kt    0.8    0.8    0.5    0.6    0.8    1.4    1.4         -   
                          Total Cobalt in concentrates   kt      -      -      -      -      -      -    0.1     (100)   
Falcondo                  Nickel in ferronickel          kt    3.3    2.0    0.4      -      -      -    7.0     (100)   
Koniambo                  Nickel in ferronickel          kt      -      -    1.4    1.0    3.1    4.1      -      n.m.   
Total Nickel department                                                                                                  
                          Total Nickel                   kt   26.8   22.5   22.8   22.3   26.8   49.1   53.1       (8)   
                          Total Copper                   kt   14.8   13.9   14.3   13.1   14.7   27.8   26.4         5   
                          Total Cobalt                   kt    0.9    1.0    0.7    0.8    0.9    1.7    1.7         -   


Production from own sources – Ferroalloys assets(1)
                                                      Q2     Q3     Q4     Q1     Q2     H1     H1    Change
                                                    2013   2013   2013   2014   2014   2014   2013  H1 14 vs
                                                                                                       H1 13
                                                                                                           %

Ferrochrome(8)                                  kt   301    332    345    335    317    652    561        16   
PGM(9)                             Platinum    koz    23     24     22     21     22     43     44       (2)   
                                   Palladium   koz    12     14     12     12     12     24     24         -   
                                   Rhodium     koz     4      4      3      4      4      8      8         -   
                                   Gold        koz     1      -      -      -      1      1      1         -   
                                   4E          koz    40     42     37     37     39     76     77       (1)   
Vanadium Pentoxide                             mlb   4.2    6.1    5.7    5.5    4.2    9.7    9.8       (1)   


Total production – Custom metallurgical assets(1)
                                                                       Q2      Q3      Q4      Q1      Q2      H1      H1     Change
                                                                     2013    2013    2013    2014    2014    2014    2013   H1 14 vs
                                                                                                                               H1 13
                                                                                                                                   %
Copper (Altonorte, Townsville, Pasar, Horne, CCR)
                           Copper metal                       kt    191.3   197.5   179.4   153.7   191.4   345.1   373.7        (8)
                           Copper anode                       kt    127.6   129.2   128.3   125.0   141.0   266.0   257.0          4

Zinc (Portovesme, San Juan de Nieva, Nordenham, Northfleet)
                           Zinc metal                         kt    181.3   181.3   191.0   193.6   194.6   388.2   372.7          4
                           Lead metal                         kt     31.2    43.1    52.5    48.5    52.0   100.5    78.6         28
                           Silver                             koz   1,244   2,162   2,428   2,342   2,823   5,165   3,280         57
Ferroalloys
                           Ferromanganese                     kt       23      24      23      30      27      57      52         10
                           Silicon Manganese                  kt       22      24      26      26      26      52      42         24

Aluminium (Sherwin Alumina)
                           Alumina                            kt      393     410     419     385     391     776     777          -

(1)   Controlled industrial assets and joint ventures only. Production is on a 100% basis, except as stated.
(2)   Relates to the PGM business in ferroalloys only.
(3)   Copper metal includes copper contained in copper concentrates and blister.
(4)   Cobalt contained in concentrates and hydroxides.
(5)   The Group's pro-rata share of Collahuasi production (44%).
(6)   The Group's pro-rata share of Antamina production (33.75%).
(7)   The Group's pro-rata share of CEZ production (25%).
(8)   The Group's 79.5% share of the Glencore-Merafe Chrome Venture.
(9)   Consolidated 100% of Eland and 50% of Mototolo.

Energy Products
Production from own sources

Coal assets(1)
                                               Q2     Q3     Q4     Q1     Q2     H1     H1    Change
                                             2013   2013   2013   2014   2014   2014   2013  H1 14 vs
                                                                                                H1 13
                                                                                                    %

Australian coking coal                  mt    2.2    1.6    1.7    1.5    1.4    2.9    4.0      (28)   
Australian semi-soft coal               mt    1.2    1.0    1.2    0.9    0.9    1.8    2.3      (22)   
Australian thermal coal (export)        mt   12.3   13.7   11.1   11.8   14.2   26.0   23.3        12   
Australian thermal coal (domestic)      mt    1.0    1.3    1.2    1.4    1.3    2.7    2.6         4   
South African thermal coal (export)     mt    4.9    5.3    5.5    5.0    5.2   10.2    9.8         4   
South African thermal coal (domestic)   mt    5.9    6.1    5.1    5.4    6.1   11.5   11.7       (2)   
Prodeco                                 mt    4.6    4.6    4.4    5.2    5.0   10.2    9.6         6   
Cerrejón(2)                             mt    3.0    3.2    3.3    2.9    3.0    5.9    4.5        31   
Total Coal department                   mt   35.1   36.8   33.5   34.1   37.1   71.2   67.8         5   


1 Controlled industrial assets and joint ventures only. Production is on a 100% basis except for joint ventures, where the Group's attributable share of
  production is included.
2 The Group's pro-rata share of Cerrejón production (33.3%).

Oil assets
                                                Q2      Q3      Q4      Q1      Q2       H1      H1    Change
                                              2013    2013    2013    2014    2014     2014    2013  H1 14 vs
                                                                                                        H1 13
                                                                                                            %

Gross basis                                                                                                  
Equatorial Guinea                     kbbl   4,556   5,862   6,113   6,304   5,731   12,035   9,942        21   
Chad                                  kbbl       -       -     619   1,067     916    1,983       -      n.m.   
Total Oil department                  kbbl   4,556   5,862   6,732   7,371   6,647   14,018   9,942        41   
Glencore entitlement interest basis                                                                             
Equatorial Guinea                     kbbl   1,020   1,246   1,394   1,368   1,194    2,562   2,159        19   
Chad                                  kbbl       -       -     186     321     276      597       -      n.m.   
Total Oil department                  kbbl   1,020   1,246   1,580   1,689   1,470    3,159   2,159        46   

Agricultural Products
Processing / production data
                                      Q2          Q3      Q4      Q1      Q2      H1      H1    Change
                                    2013        2013    2013    2014    2014    2014    2013  H1 14 vs
                                                                                                 H1 13
                                                                                                     %

Farming                       kt      33         262     236     232      34     266     385      (31)   
Crushing                      kt     943       1,128     966   1,062   1,616   2,678   1,548        73   
Long term toll agreement      kt     257         151     101      49     157     206     289      (29)   
Biodiesel                     kt     109         181     191     172     169     341     252        35   
Rice milling                  kt      85          83      70      36      91     127     120         6   
Wheat milling                 kt     273         299     267     262     263     525     555       (5)   
Sugarcane processing          kt     509         933     809       -     723     723     509        42   
Total Agricultural products   kt   2,209       3,037   2,640   1,813   3,053   4,866   3,658        33   

Forward looking statements

This document contains statements that are, or may be deemed to be, "forward looking statements" which are prospective in nature. These forward looking
statements may be identified by the use of forward looking terminology, or the negative thereof such as "plans", "expects" or "does not expect", "is
expected", "continues", "assumes", "is subject to", "budget", "scheduled", "estimates", "aims", "forecasts", "risks", "intends", "positioned", "predicts",
"anticipates" or "does not anticipate", or "believes", or variations of such words or comparable terminology and phrases or statements that certain actions,
events or results "may", "could", "should", "shall", "would", "might" or "will" be taken, occur or be achieved. Such statements are qualified in their entirety by
the inherent risks and uncertainties surrounding future expectations. Forward-looking statements are not based on historical facts, but rather on current
predictions, expectations, beliefs, opinions, plans, objectives, goals, intentions and projections about future events, results of operations, prospects,
financial condition and discussions of strategy.

By their nature, forward looking statements involve known and unknown risks and uncertainties, many of which are beyond Glencore's control. Forward
looking statements are not guarantees of future performance and may and often do differ materially from actual results. Important factors that could cause
these uncertainties include, but are not limited to, those discussed in Glencore's Annual Report 2013.

Neither Glencore nor any of its associates or directors, officers or advisers, provides any representation, assurance or guarantee that the occurrence of the
events expressed or implied in any forward-looking statements in this document will actually occur. You are cautioned not to place undue reliance on these
forward-looking statements which only speak as of the date of this document. Other than in accordance with its legal or regulatory obligations (including
under the UK Listing Rules and the Disclosure and Transparency Rules of the Financial Conduct Authority and the Rules Governing the Listing of
Securities on the Stock Exchange of Hong Kong Limited and the Listing Requirements of the Johannesburg Stock Exchange Limited), Glencore is not
under any obligation and Glencore and its affiliates expressly disclaim any intention, obligation or undertaking to update or revise any forward looking
statements, whether as a result of new information, future events or otherwise. This document shall not, under any circumstances, create any implication
that there has been no change in the business or affairs of Glencore since the date of this document or that the information contained herein is correct as at
any time subsequent to its date.

No statement in this document is intended as a profit forecast or a profit estimate and no statement in this document should be interpreted to mean that
earnings per Glencore share for the current or future financial years would necessarily match or exceed the historical published earnings per Glencore
share.

This document does not constitute or form part of any offer or invitation to sell or issue, or any solicitation of any offer to purchase or subscribe for any
securities. The making of this document does not constitute a recommendation regarding any securities.

SPONSOR
Absa Bank Limited (acting through its Corporate and Investment Banking Division)



Date: 13/08/2014 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story