Wrap Text
June 2014 Quarterly Activities Report
Firestone Energy Limited
(Incorporated in Australia)
Registration Number: ABN 058 436 794
Share Code JSE: FSE
Share Code ASX: FSE
ISIN: AU000000FSE6
("FSE or "the Company") ASX Release
SA Registration Number: 2008/023973/10
31 July 2014
FIRESTONE ENERGY
LIMITED
ABN 71 058 436 794
JUNE 2014 QUARTERLY Registered office:
Level 2, 1 Walker Avenue West Perth,
ACTIVITIES REPORT Western Australia 6005
Australia
The Waterberg Coal Project (WCP) Tel:+61 8 9485 0888
Fax: +61 8 9485 0077
Firestone Energy Limited (FSE) is a participant in the Waterberg Coal South African office:
Project (WCP) joint venture, situated in the Limpopo Province, South Level 1, The Place,
Africa. The Project currently has identified coal resources of 3.883 billion 1 Sandton Dr, Sandton, 2146, South
tonnes1 of coal contained within the granted mining rights; of which 2.070 Africa
Billion tonnes are contained within the measured category1.
Tel: +27 10 594 2240
Fax: +27 10 594 2253
The WCP Joint venture entered into a Memorandum of Understanding
with Eskom Holdings in March 2012 for the supply and delivery of 10
million tonnes per annum (mtpa) of coal from the Project.
Contact:
In May 2012 the mineral consultancy, SRK Consulting of Johannesburg, Mr Stephen Miller
South Africa were commissioned by the WCP joint venture partners to Executive Director/CEO
undertake a technical and economic feasibility study for the development Or
Investor relations
of the Project. In October 2013, SRK Consulting delivered to the project
in South Africa:
partners the results of the feasibility study (FS). A summary of the Bruce Tinney
activities arising from the FS in the period ending 30 June 2014 is set out +27 (83) 408 3028
below.
E-mail:
EPC Contract info@waterbergcoal.net
Corporate Details:
During the quarter, the WCP Partners awarded the Engineering,
Major Shareholders:
Procurement and Construction Management contract for the The Waterberg Coal Company Ltd
development of the plant and associated infrastructure to Ardbel (a joint
venture between ELB Engineering Services and the DRA Group). Directors and Officers:
Specifically, Ardbel’s brief is to design, manufacture, supply, delivery, Non Executive Directors:
assemble, install and commission the 22mtpa coal handling and George Oupa Magashula
preparation plant (CHPP). Edwin Leith Boyd
Ardbel have also commenced work on a review of the project capital Officers:
Mr Stephen Miller CEO and Executive
expenditure requirements arising from the SRK Feasibility Study. This
Director
process is envisaged to be completed mid-August 2014 and which will Ms Amanda Matthee CFO
complement the on-going optimisation of the overall project by the WCP Mr Edwin Leith Boyd Company
project team. Secretary
Ardbel also commenced preparation of a Project Execution Plan (PEP) ASX / JSE Symbol:
following completion of the Waterberg Coal Project Feasibility Study; FSE
which study is now the subject of due diligence by a Banking Syndicate
for the purposes of project funding. The PEP should be completed during Web: www.firestoneenergy.com.au
August 2014.
Project Optimisation Study
The WCP technical team continued to work on project “value engineering” and optimisation;
focussing on production scheduling, savings on mining contractor costs, plant operating costs
and capital savings associated with the materials handling and CHPP.
Pursuant to the optimisation work being undertaken on both the mine plan and infrastructure
development; the WCP are currently engaging with Exxaro Resources Limited (Exxaro) to
investigate the potential of sharing of logistics infrastructure in future.
The JSE listed Exxaro is the operator of the immediately adjacent Grootegeluk Mine which
currently produces approximately 18 mtpa of coal product and is also looking at expanding its
operations through the development of the Thabametsi coal project which shares a common
boundary with the WCP. The Grootegeluk mine has been producing coal for over 25 years.
The WCP team have been engaging with the “short listed” mining contractors during the
quarter with a view to finalisation of the process to appoint a preferred mining contractor. It is
anticipated that the preferred mining contractor status should be awarded in the September
quarter.
Eskom; Coal Supply Agreement (CSA) negotiations
Pursuant to the Eskom MOU; Eskom have now been provided demonstrable evidence that the
quantum and qualities of the specified coal can be delivered by the WCP Joint Venture. During
the quarter, Eskom requested that the proposed offtake term be increased from a 30 year
period, to a 40 year period.
Subsequent to receiving the updated economic model, Eskom has relaxed the very strict cut
off for coal specifications which will increase the yield and reduce the operating costs. The
WCP technical team have adjusted the economic model accordingly. As a result of this, Eskom
and WCP are now able to advance discussions to reach agreement on price for delivery of the
specified coal product requested by Eskom. The basis for price negotiation is a base price and
escalator, with five-yearly price re-openers.
WCP have notified Eskom that a construction build commencing January 2015 would see first
coal product in Q4, 2015.
Project funding
As previously advised, the Standard Bank of South Africa Limited (SBSA), have been
mandated to arrange project finance for the construction and development of the WCP. SBSA
have appointed Hatch Goba as the Independent Technical Consultant to review all technical
matters for the WCP as part of its due diligence for the credit process.
During the quarter, the WCP team continued to work closely with Hatch pursuant to the review
process. The team expect completion of the Hatch review by the end of August 2014.
WCP Stakeholder engagement
Interaction by the WCP technical team with strategic stakeholders continued during the
quarter, including meetings with the Lephalale municipality and participation at the Strategic
Infrastructure Project 1 forum.
2
New Office - Johannesburg
During the quarter, the WCP took occupation of its dedicated project offices in Sandton,
Johannesburg. This stronger physical presence coupled with the appointment of additional
members to the technical team, including the project metallurgist and a project manager
reflects the increasing activity as the project further ramps up towards project “readiness”.
Working capital loan
During the period, FSE entered into a further loan agreement with The Waterberg Coal
Company Limited (WCC) (ASX/JSE: WCC), the 45.88% major shareholder in FSE. WCC will
provide additional funding of up to A$3million to be used for FSE’s obligations in relation to the
WCP.
The loan will be under the same conditions as the prior loan. Material terms of which are:
WCC grants an additional loan facility of up to $3m to be used towards project
expenditure.
No interest is payable on the loan.
The loan is unsecured.
Corporate Activities
During the quarter FSE announced the resignation of Mr Jonathan Hart as Company
Secretary and the appointment of Mr Edwin Leith (Lee) Boyd as Company Secretary with
effect from 21 May 2014.
Stephen Miller
Chief Executive Officer
www.firestoneenergy.com.au
3
Table 1 – Coal Resource on all six Waterberg Coal Project Properties under both
Prospecting Permit and Mining Right
CV
Coal Ash % IM % Vol % TS %
Resource Classification (Mj/kg)
Resource¹(Mt) (ad) (ad) (ad) (ad)
(ad)
Measured 2070.3 57.9 2.2 17.6 10.51 0.96
Indicated 856.3 59.4 2.3 17.2 9.96 1.00
Inferred 956.7 58.9 2.2 17.5 10.26 1.03
Total Resources 3883.3 58.5 2.2 17.5 10.33 0.99
Coal Resource ¹ based on minimum thickness cut-off of 0,5m
Note 1: Competent Person Statement
Gemecs (Pty) Limited was commissioned by the Waterberg Coal Company "WCC", to undertake an Updated Independent
Persons Geological Report for the Sekoko Waterberg Coal Project.
The Coal Resources were estimated in accordance with the South African code for the Reporting of Exploration Results,
Mineral Resources and Mineral Reserves (“SAMREC Code”), Australasian Code for Reporting of Exploration Results. Mineral
Resources and Ore Reserves (“the JORC Code”) and South African National Standard (SANS 10320:2004) guidelines.
The information in this announcement that relates to Exploration Results, Mineral Resources or Ore Reserves is based on
information compiled by Mr Coenraad D van Niekerk, Pr.Sci.Nat (Reg. No 400066/98), M.Sc Hons (Geology), MDP, an
employee of Gemecs (Pty) Limited, who is a Fellow of the Geological Society of South Africa. Mr Niekerk is a mining geologist
with 38 years’ experience in the mining industry, sufficient experience relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Niekerk
consents to the inclusion in the announcement of the matters based on this information in the form and context in which it
appears.
Appendix 1 – Interests in mining tenements held
Tenement table
WCC has an interest in the following Exploration and Mining Licences.
Licences are located in South Australia:
Interest at
Property Name Tenement Beginning and Status
End of Quarter
Lyons EL 5221 100% Exploration Licence
Glenloth EL 5397 100% Exploration Licence.
Claypan Dam EL 4445 100% Exploration Licence
The Company’s interest in the Waterberg Coal Project, located in South Africa:
Properties Right under Relevant Holder Interest at Issue Date Expiry Date
which the Joint Venture Beginning
properties are and End of
held Quarter
Vetleegte Vetleegte First Joint Uzalile Joint 37.39% Granted Renewal lodged 19
Prospecting Venture Venture New Order September 2011 and
Right (Sekoko Prospecting prior to the expiry date.
Resources Right No.
and Uzalile) 651/2006, Section 18(5) of the
on 19/10/06 MPRDA provides that
prospecting right in
respect of which an
application for renewal
has been lodged will
remain in force until
such time as the
renewal application has
been granted or
refused.
Olieboomsfontei Duikerfontein First Joint Sekoko Coal 37.39% Granted 3 July 2016
n Prospecting Venture New Order
Right Prospecting
Right No.
681/2007,
on 13/10/05.
Renewal on
3 July 2013
Duikerfontein Duikerfontein First Joint Sekoko Coal 37.39% Granted 3 July 2016
Prospecting Venture New Order
Right Prospecting
Right No.
681/2007,
on 13/10/05.
Renewal on
3 July 2013
Swanepoelpan Duikerfontein First Joint Sekoko Coal 37.39% Granted 3 July 2016
Prospecting Venture New Order
Right Prospecting
Right No.
681/2007,
on 13/10/05
Smitspan Mining Right Second Sekoko Coal 37.39% Granted 16/09/2041
Joint Venture New Order
Mining Right
No. 22/2011,
on 17/09/11
5
Massenberg Mining Right Second Sekoko Coal 37.39% Granted 16/09/2041
Joint Venture New Order
Mining Right
No. 22/2011,
on 17/09/11
Minnasvlakte Mining Right Second Sekoko Coal 37.39% Granted 16/09/2041
Joint Venture New Order
Mining Right
No. 22/2011,
on 17/09/11
Hooikraal Mining Right Second Sekoko Coal 37.39% Granted 16/09/2041
Joint Venture New Order
Mining Right
No. 22/2011,
on 17/09/11
Johannesburg 31 July 2014
Sponsor
Rivergroup
6
Date: 31/07/2014 11:54:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.