KUMBA IRON ORE LIMITED - Sishen mine to be restored to full production capacity by 2016

Release Date: 12/12/2013 12:30
Code(s): KIO     PDF:  
Wrap Text
Sishen mine to be restored to full production capacity by 2016

Kumba Iron Ore Limited
A member of the Anglo American plc group
(Incorporated in the Republic of South Africa)
(Registration number 2005/015852/06)
JSE Share code: KIO
ISIN: ZAE000085346
("Kumba" or the “Company”)

Sishen mine to be restored to full production capacity by 2016

Kumba announces plans to restore Sishen mine to production capacity of 37 Mtpa by 2016 and to
sustain production at Kolomela mine at 10 Mtpa, an 11% increase above the mine’s original design
capacity.

The Company will detail its plans at the Anglo American plc (“Anglo American”) investor presentation
this afternoon in London. The presentation will begin at 14:30 and end at approximately 19:00 (SA
times) and will be webcast live via the Anglo American website [www.angloamerican.com] and the
presentation slides will be available on the Company’s website [www.angloamericankumba.com] from
12:30 today.

The Sishen mine recovery and optimisation plan expects phased production increases from ~30 Mt in
2013 to ~35 Mt in 2014, ~36 Mt in 2015 and ~37 Mt in 2016. Production of 37 Mtpa has been confirmed
in several technical studies as Sishen’s life-of-mine production capacity.

Sishen mine’s pit is currently constrained due to inadequate waste stripping, resulting in insufficient
exposed ore. As the ore body dips and thins to the west, waste stripping of up to 270 Mtpa is required
for the production of 37 Mtpa at current marketing specifications, which will see the strip ratio peak at
between 5.5x and 5.7x before stabilising at a lower level over the life of mine.

To facilitate the expansion of Sishen mine to the west, the Company has completed a comprehensive
feasibility study for the relocation of the Dingleton community and an extensive consultation process
with interested and affected parties, the community and the relevant government departments. The
Kumba board has now approved the plan to resettle the community in Kathu, which is expected to cost
an estimated R4.2 billion capex (nominal) over a 4 – 6 year period.

At Kolomela, technical studies have confirmed the mine’s capacity to sustain production at 10 Mtpa,
1 Mtpa above its original design capacity. Further, incremental expansions of the mine are also being
studied.

Kumba anticipates total iron ore production, excluding Thabazimbi, of between 44 – 46 Mt in 2014, 45 –
47 Mt in 2015 and 46 – 48 Mt in 2016.

A further operational update will be given at the Company’s 2013 annual results presentation on
11 February 2014.
This announcement contains forward-looking statements and is subject to a number of risks and
uncertainties, many of which are beyond Kumba’s control and all of which are based on the Company's
current beliefs and expectations about future events. The operational forecasts provided in this
announcement are estimates and have not been reviewed and reported on by the Company’s external
auditors.

Centurion
12 December 2013

For further information, please contact:

Media                                                Investors
Gert Schoeman                                        Esha Mansingh
Tel: +27 (0)12 683 7019                              Tel: +27 (0)12 683 7257


Sponsor
RAND MERCHANT BANK (A division of FirstRand Bank Limited)

Date: 12/12/2013 12:30:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story