Rockwell's 2nd quarter results reveal 5th cosecutive  quarter of revenue growth and improved operating profit

ROCKWELL DIAMONDS INCORPORATED
(A company incorporated in accordance with the laws of British Columbia, Canada)
(Incorporation number BCO354545)
(Formerly Rockwell Ventures Inc.)
(South African registration number: 2007/031582/10)
Share code on the JSE Limited: RDI       ISIN: CA77434W2022
Share code on the TSXV: RDI      CUSIP Number: 77434W103
Share code on the OTCBB:      RDIAF
(“Rockwell”)



ROCKWELL’S SECOND QUARTER RESULTS REVEAL FIFTH CONSECUTIVE QUARTER OF REVENUE
GROWTH AND IMPROVED OPERATING PROFITABILITY



October 11, 2013, Johannesburg, South Africa -- Rockwell Diamonds Inc. ("Rockwell"
or the "Company") (TSX:RDI; JSE:RDI) announces results for the three months ended
August 31, 2013.

Second quarter fiscal 2014 results

Currency values are presented in Canadian dollars, unless otherwise indicated.

Salient features of second quarter:

- Fifth consecutive quarter of US$ denominated revenue growth.

- Strong year-on-year revenue growth of 33%: Total revenue of $9.9 million,
comprising $8.6 million from diamond sales and beneficiation income of $1.3
million, up 24% and 185%, respectively.

- Overall volume of gravel processed and diamond production from Company-owned
properties (including royalty mining contracts) up 26% and 46% year-on-year,
respectively.

- Operating profit of $2.5 million: Improving economies of scale with 2% increase
year-on-year in production costs (after inventory movements) supporting 33% revenue
growth.

- Stable net cash holdings of $0.3 million: Positive cash flow from operations of
$3.6 million offset impact of $3.4 million invested in new capacity.
- Inventory of 2,508 carats carried forward (includes 900 carats on royalty mining
contracts): Positioned to benefit from peak Thanksgiving and Christmas trading
seasons.

- Returns from Tirisano royalty mining contracts continue to grow and Zwemkuil
contract commenced (June 2013): 3,497 carats produced and 2,967 carats sold at
average price of US$638 per carat (Rockwell’s royalty amounts to $236,600) with
additional upside as fifth Tirisano contract started in third quarter.

- The ‘beneficiation pipeline’ of more than 6,272 carats provides continued value-
added revenue potential.

- Net loss for the quarter narrowed to $1.4 million compared to a loss of $2.0
million in the prior year.



Commenting on the second quarter performance of Rockwell, James Campbell, CEO and
President said:

“Our second quarter results confirm that operationally, we are in a stronger
position than two years ago, having delivered on a number of strategic milestones
towards our initial objective of processing 500,000m3 per month of quality gravels.
We have also been able to extend the life of our flagship operation at Saxendrift
by integrating Saxendrift Extension, which has a five-year remaining mine life,
into Saxendrift’s mine plan with pleasing results. The successful commissioning of
the Saxendrift Hill Complex plant, based primarily Bulk X-ray technology, provides
us with a blue print for future mine developments. At Niewejaarskraal, we
commissioned the mine in record time and are on track to achieve nameplate capacity
by the end of 2013, slightly behind our original plans.”

“The steady improvement in our operating results is a direct result of our decision
to exit our lossmaking operations and focus our resources on growing our footprint
in the Middle Orange River region. Notably monthly carat production from our own
operations in July and August was at its highest level since the strategic review
that took place at the start of fiscal 2012. Second quarter highlights include the
33% revenue growth, representing our fifth consecutive quarter with higher US
dollar-denominated revenues. In addition, we achieved a $2.5 million operating
profit and positive cash flow from operations of $3.6 million. From a financial
perspective, the results are starting to reflect the decisions taken during the
course of our corporate turnaround and have equipped us to achieve our objective to
be a mid-tier diamond mining company.”
Review of second quarter delivery on strategy

The performance of Rockwell in the second quarter provides further justification of
the Company’s strategy to focus on growing its production footprint in the Middle
Orange River (“MOR”) region of South Africa where higher diamond values, better
efficiencies and greater economies of scale can be achieved. The mid-term target is
to increase monthly production volumes of quality gravel processed to 500,000m3
while improving quarterly earnings.

As Rockwell focuses on developing its portfolio of properties in the region, it has
reached a number of strategic milestones:

- Volumes processed from Saxendrift and Saxendrift Hill Complex were up 32% year-
on-year, and 42%, overall, including the commissioning volumes of gravel processed
at Niewejaarskraal: Overall 88% increase in carat production in MOR.

- Production at Saxendrift, comprising traditional Saxendrift and the higher grade
Saxendrift Extension gravels, achieved a 41% grade improvement: Carat production up
35% to 2,543 carats.

- Average carat value from own operations improved 84% to US$2,488 per carat as 98%
of carats sold (excluding royalty mining contractors) originated from the MOR.

- The new Saxendrift Hill Complex mine achieved an average value of US$3,636 per
carat related to the sale of several high-valued diamonds: Revenue from second
quarter diamond sales of US$2.0 million, exceed the capital investment cost.

- The effectiveness of the Bulk X-ray technology at Saxendrift Hill Complex was
confirmed: A grade improvement exceeding 40% was achieved compared to the
traditional Saxendrift pan plant, shown by processing Saxendrift Extension gravels
in parallel though both plants.

- Production commissioning commenced at Niewejaarskraal in July 2013 on Rooikoppie
gravels with the recovery of 175 carats, including three stones exceeding 10
carats.

- The royalty mining contractors continue to growth: Value of sales amounts to
US$1.9 million, with US$236,600 accruing to the Company.

- Having eliminated the impact of the loss-making operations at Tirisano and
Klipdam, the Company reported a gross profit (after amortization and depreciation)
of $1.3 million compared to a loss of $1.7 million a year ago.
- Subsequent to the balance sheet date, the Company recovered four rough diamonds
each exceeding 100 carats in weight from its operations in the MOR region including
two typical yellow MOR stones.

Second Quarter Performance Summary

The Company’s overall production and sales results for the quarter are:

                            Production                           Sales and inventories
                                        Productio     Value of     Sales      Average
                   Volume                                                                Inventory
                             Carats       n costs        Sales    (carat   value (US$
                     (m3)                                                                 (carats)
                                              ($)        (US$)        s)     / carat)
Own operations    627,746     3,549     8,805,727    6,608,040     2,656        2,488        1,608
   Contractors’
        mining    307,229     3,497             -    1,892,793     2,967          638          900
Total: Company
    properties    934,975     7,046     8,805,727    8,500,833     5,623        1,512        2,508

Second quarter processed gravel volumes from Company properties reflects the
transition towards the MOR. Volumes processed increased 26% to 934,975m3 of which
627,746m3 was recovered from Rockwell’s own operations in the MOR and the remainder
processed by the royalty mining contractors. Total carat production grew by 46%,
and was made up of 3,549 carats from own operations in the MOR (the 25% year-on-
year reduction is due to exiting Klipdam and Tirisano) and 3,497 carats from
contractors.

Notable impacts of second quarter production compared to the comparable prior year
period are as follows:

                     Volume     Change      Carats    Change                    Notable impacts
                       (m3)
Saxendrift          462,777           -3%    2,543       35%       Impact of integrating higher
                                                                     grade Saxendrift Extension
                                                                      into Saxendrift mine plan
Saxendrift Hill     164,969             -      831         -       Successful commissioning and
Complex                                                                grade improvement due to
                                                                          processing Saxendrift
                                                                              Extension gravels
Niewejaarskraal     48,512*             -      175         -               Commissioning of new
                                                                    processing plant started in
                                                                                      July 2013
Contractors         307,229             -    3,497         -          Number of contract miners
                                                                 operating increased from three
                                                                                        to four
* Commissioning volumes in July and August 2013.
 The Company’s reported revenue from diamond sales (including beneficiation)
 increased 33% year-on-year to $9.9 million, representing the fifth consecutive
 quarter of US$-denominated revenue growth in line with the strategy to focus on
 growing production in the MOR which typically yields high value diamonds. Reported
 revenue includes the Company’s 12.5% royalty from the sale of royalty mining
 contractors’ rough diamond production. The average carat value (own operations)
 increased by 84%, as a result of the sale of a number of large, high-quality
 diamonds recovered during the quarter.


 Notable impacts of second quarter sales versus the comparable prior year period are
 as follows:
               Carats   Change       Revenue   Change   Price   Change          Notable impacts
                                        (US$              per
                                   millions)            carat
                                                        (US$)
Saxendrift      1,937        14%   4,377,094       3%   2,260     -10%    Increased carat sales
                                                                         offset impact of lower
                                                                            average carat value
Saxendrift        555          -   2,017,992        -   3,636        -        Higher revenue as
Hill Complex                                                                  production gained
                                                                                       momentum
Klipdam            53     -98%        27,975     -99%     528     -39%        Sale of remaining
                                                                                inventory after
                                                                                       disposal
Contractors*    2,967          -   1,892,793        -       -        -    Contractors increased
                                                                          from three to four at
                                                                                       Tirisano

 * Contractors refers to carats from gravel processed by independent royalty
 contractors and sold through the Company’s tender process.

 During the second quarter, the average total cash cost (including rehabilitation
 and depreciation) for all the operations, increased to US$12.50/m3 from a total cash
 cost of US$9.78/m3 in the comparative period of fiscal 2013. This increase is
 attributable to higher unit costs that were incurred at Saxendrift Hill Complex
 during production ramp up.

 Average cash operating costs and revenues for Rockwell’s own operations during the
 period are:
                Revenue/m3    Mining cash                                          Comments
                     (US$)        cost/m3
                                    (US$)
 Saxendrift        US$9.5          US$8.2              Lower unit revenue due to product mix of
                                                    carats sold in second quarter. Reduction in
                                                     unit cost after once-off maintenance costs
                                                                     expensed in first quarter.
Saxendrift        US$12.2      US$16.2            Good quality diamond recoveries led to higher
Hill Complex                                                                     unit revenues.
                                                   Unit cost up due to rental of EMV, increased
                                                        fuel and haulage costs while processing
                                                                   Saxendrift Extension gravels.

The Company’s 12.5% share of royalty mining contractors’ revenues amounted to
US$236,000, with Tirisano contractors covering that property’s care and maintenance
costs in the second quarter.
Normal operations produced cash flow of $1.8 million (prior to working capital
movements). After a positive cash flow from working capital movements of $1.8
million, the cash flow from operating activities of $3.6 million was mostly spent
on investments in property plant and equipment (mainly Niewejaarskraal plant),
leaving a net cash out flow of $0.1 million for the quarter.
Growth projects
Rockwell continues to deliver on its strategy to increase production from and
extend the mine life of its MOR properties:
- The useful life of processing facility at Saxendrift was extended with the
addition of the Saxendrift Extension, whose indicated and inferred resources of
1,303,400m3 and 577,000m3 have a grade of 0.60 carats per 100m3 compared to
Saxendrift’s grade of 0.40 carats per 100m3, both at a bottom cut off size (“bcos”)
of 5mm. These have been integrated into the Saxendrift mine plan.
- The internally funded first phase of the new Niewejaarskraal processing plant was
completed within three months of obtaining board approval. Ramp up towards
nameplate production capacity of 100,000m3 per month started in July 2013. Although
commissioning volumes were behind plan, the plant did achieve instantaneous
nameplate capacity. It was handed over to the operational team on September 1, 2013
and is on track to be fully ramped up by the end of 2013.
- The Company continues to evaluate the next steps at Wouterspan, following the
positive findings of the preliminary economic assessment announced earlier this
year.
Progress also continues with Rockwell’s secondary strategy to leverage the value of
certain properties that it does not wish to mine due to size or other reasons. Four
royalty contract miners operated at Tirisano during the second quarter and a fifth
is due to start in the third quarter, the projected monthly mining volumes at
Tirisano are 150,000m3. The contract miner at Rockwell’s Zwemkuil property in the
MOR commenced production in June 2013.
The Company continues to evaluate consolidation opportunities in the southern
Africa diamond sector that are value accretive. A strict set of criteria are
applied to evaluate the potential acquisitions in order to leverage the Company’s
production profile towards its goal to become a mid-tier diamond producer.
Market Outlook
Although rough diamond prices were stable during the second quarter, the downstream
diamond industry remains under pressure due to the high cost of rough diamond
production and the devaluation of the Indian Rupee against the US dollar. In
addition, the market in the second quarter was affected by the seasonal impact:
sales are quieter during northern hemisphere summer months. However, activity
levels are expected to recover ahead of the Hong Kong Jewellery and Gem Fair,
setting the mood for the remainder of the year.
Rockwell has carried over an inventory of 2,508 carats into the third quarter of
fiscal 2014 and is, therefore, well positioned to benefit from the peak
Thanksgiving to Christmas retail trading season. This, together with a
beneficiation pipeline comprising some 6,272 carats, provides further potential for
valued-added downstream revenues. Rockwell continues to beneficiate the vast
majority of its diamonds in South Africa. With a number of notable stones recovered
during the second quarter, the beneficiation revenue trend is expected to continue
in line with past results.
In the third quarter, Rockwell will continue to focus on managing its operating
costs and bedding down its new operations in the MOR. At Saxendrift, which is
running consistently, the third quarter mine plan comprises a combination of
gravels from the traditional (Brakfontein) mining area and the Saxendrift Extension
that will be processed at Saxendrift. At the Saxendrift Hill Complex, the mine plan
has been adjusted to open up a new mining area while at Niewejaarskraal the focus
is on completing the ramp up. As such, Rockwell is on track to have three fully
operational mines in the region by the end of the calendar year, with a total
monthly processing capacity of 360,000m3 comprising Saxendrift (160,000m3 per
month), Saxendrift Hill Complex (100,000m3 per month) and Niewejaarskraal (100,000m3
per month), and a further 200,000 m3 per month indirectly through royalty contract
mining production.
Conference Call:
Rockwell will host a telephone conference call on Friday, October 11, 2013 at 10:00
a.m. Eastern Time (4:00 p.m. Johannesburg) to discuss these results. The conference
call may be accessed as follows:
Country                                                                   Access Number
Canada (Toll-Free)                                                       1 855 669 9657
USA (Toll)                                                               1 412 317 6060
USA (Toll-Free)                                                       1 866 652 5200
South Africa (Toll-Free)                                               0 800 200 648
South Africa – Durban                                                   031 812 7600
South Africa – Johannesburg                                             011 535 3600
South Africa - Johannesburg Alternate                                   010 201 6800
UK (Toll-Free)                                                         0808 162 4061
UK Alternative (Toll-Free)                                            0 800 917 7042
Other Countries (Intl Toll)                                          +27 11 535 3600

A transcript of the audio webcast will be available on the Company's website:
www.rockwelldiamonds.com. The conference call will be archived for later playback
until midnight (ET) October 15, 2013 and can be accessed by dialling the relevant
number in the table below and using the pass code 26597#.

Country                                                                Access Number
South Africa (Telkom)                                                   011 305 2030
USA and Canada (Toll)                                                   412 317 0088
Other Countries (Intl Toll)                                          +27 11 305 2030
UK (Toll-Free)                                                        0 808 234 6771



For further details, see the Rockwell’s complete financial results and Management
Discussion and Analysis posted on the website and on the Company's profile at
www.sedar.com. These include additional details on production, sales and revenues
for the quarter, as well as comparative results for fiscal 2013.

Mr Glenn A Norton (Pr. Sci. Nat.), Group Technical Manager for Rockwell and a
qualified person has reviewed and approved the technical information in this
release.

For further information on Rockwell and its operations in South Africa, please
contact:

James Campbell
CEO and President
+27 (0)83 457 3724

Stéphanie Leclercq
Investor Relations
+27 (0)83 307 7587

About Rockwell Diamonds:
Rockwell is engaged in the business of developing and operating alluvial diamond mines, with
the aim of becoming a mid-tier diamond mining company. At August 31, 2013, the Group had two
existing mines in operation, namely Saxendrift and Saxendrift Hills Complex. It has completed
the first phase of the development of a new plant at a third mine, Niewejaarskraal, which had
been on care and maintenance since 2007 and was commissioned in July 2013 before going into
production ramp up in the third quarter fiscal 2014. All three mines are located in the
Middle Orange River region.
Rockwell’s operations at the Tirisano Mine are on care and maintenance. Royalty mining
agreements are in place at Tirisano whereby independent contractors (or royalty miners) mine
for own risk and reward, with the Company receiving a 12.5% royalty income based on the
carats recovered and sold through the Company’s tender process.
A Preliminary Economic Assessment has been completed on the Wouterspan project, which would
provide further expansion of the Company’s Middle Orange operations in future. The Group has
a pipeline of other projects with further future development potential under consideration
and evaluation at present.
In addition to its project work, Rockwell continues to evaluate strategic opportunities
through merger and acquisition as they arise, in order to expand its mineral resources and
provide new opportunities to develop the additional production.
The Group is establishing a track record of producing large gem quality diamonds, which
comprise a significant proportion of its production profile. The diamonds recovered from
Rockwell’s mines are frequently acquired for investment purposes. The Group has a
beneficiation agreement in place which enables it to sell rough diamonds, receive 90% of the
fair value sales price at sale and receive the remaining 10% through, and participate in, the
retail profit on the sale of its +2.8 carat sized stones after polishing and finishing.
No regulatory authority has approved or disapproved the information contained in this news release.
Forward Looking Statements
Except for statements of historical fact, this news release contains certain "forward-looking
information" within the meaning of applicable securities law. Forward-looking information is frequently
characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate",
"estimate" and other similar words, or statements that certain events or conditions "may" or "will"
occur. Although the Company believes the expectations expressed in such forward-looking statements are
based on reasonable assumptions, such statements are not guarantees of future performance and actual
results or developments may differ materially from those in the forward-looking statements.
Factors that could cause actual results to differ materially from those in forward-looking statements
include uncertainties and costs related to exploration and development activities, such as those related
to determining whether mineral resources exist on a property; uncertainties related to expected
production rates, timing of production and cash and total costs of production and milling; uncertainties
related to the ability to obtain necessary licenses, permits, electricity, surface rights and title for
development projects; operating and technical difficulties in connection with mining development
activities; uncertainties related to the accuracy of our mineral resource estimates and our estimates of
future production and future cash and total costs of production and diminishing quantities or grades of
mineral resources; uncertainties related to unexpected judicial or regulatory procedures or changes in,
and the effects of, the laws, regulations and government policies affecting our mining operations;
changes in general economic conditions, the financial markets and the demand and market price for
mineral commodities such as and diesel fuel, steel, concrete, electricity, and other forms of energy,
mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the US
dollar, Canadian dollar and South African Rand; changes in accounting policies and methods that we use
to report our financial condition, including uncertainties associated with critical accounting
assumptions and estimates; environmental issues and liabilities associated with mining and processing;
geopolitical uncertainty and political and economic instability in countries in which we operate; and
labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour
in markets in which we operate our mines, or environmental hazards, industrial accidents or other events
or occurrences, including third party interference that interrupt operation of our mines or development
projects.
For further information on Rockwell, Investors should review the Company’s home jurisdiction filings
that are available at www.sedar.com.


Johannesburg
11 October 2013


Sponsor
Sasfin Capital
A division of Sasfin Bank Limited

Date: 11/10/2013 08:15:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story