FIRESTONE ENERGY LIMITED - Quarterly Activities Report for the Period to 30 June 2013

Release Date: 30/07/2013 08:45
Code(s): FSE FSEO1     PDF:  
Wrap Text
Quarterly Activities Report for the 
Period to 30 June 2013

                                                                               
FIRESTONE ENERGY LIMITED 
(Incorporated in Australia) 
(Registration number ABN 058 436 794) 
Share code on the JSE Limited: FSE   
Share code on the ASX: FSE 
ISIN: AU000000FSE6 
(SA company registration number 2008/023973/10) 
("FSE" or "the Company")

                                                                                

                                                                               About Firestone Energy

                                                                               Firestone Energy Limited is an
                                                                               independent, Australian exploration and
                  Quarterly Activities Report for the                          development company listed on the
                       Period to 30 June 2013                                  Australian Stock Exchange Ltd (ASX) and
                                                                               the Johannesburg Stock Exchange (JSE).
The Board of Firestone Energy Limited (ASX/JSE: FSE) (the                      Firestone Energy has entered into a Joint
“Company”, "FSE" or “Firestone”) is pleased to provide Shareholders with       Venture with Sekoko Resources (Pty) Ltd
                                                                               through which Firestone Energy has
its Quarterly Activities Report for the 3 month period ended 30 June 2013.
                                                                               acquired the right to 60% participation
                                                                               interests in the Waterberg Coal Project
The Waterberg Coal Project: The Definitive Feasibility Study
                                                                               located in Lephalale area, Limpopo Province,
                                                                               South Africa.
During the quarter, the Waterberg Joint Venture Partners continued the
progression of the Definitive Feasibility Study (“DFS”) on the proposed        The first stage of the project is to develop the
development of an opencast mining operation to produce 10 Million tonnes       Smitspan mine which has a substantial
of coal (product) per annum to Eskom for an initial term of 30 years           measured thermal coal resource and to
pursuant to the Memorandum of Understanding (“MOU”) that the joint             develop the Vetleegte mine which is a
venture entered into with Eskom in March 2012 (as amended).                    substantial metallurgical coal deposit.

The production of the DFS is one of the Conditions Precedent in the            Firestone Energy is committed to becoming a
process of converting the current Eskom MOU to a Coal Supply Agreement.        profitable independent coal and energy
The Chapters of the DFS are in final draft stage, and the technical team are   producer at its projects in South Africa,
currently interrogating the financial model as prepared by SRK and             thereby making a substantial contribution to
reviewing the proposed mine plan.                                              the social and economic development of the
                                                                               Lephalale area and South Africa.
As part of the DFS, the technical team are engaging with strategic
                                                                               Corporate Details
stakeholders, including inter-alia, Eskom, the Department of Water Affairs,                                         ASX: FSE
and Transnet Freight Rail about the delivery of services to the project.                                            JSE: FSE
These discussions regarding proposed arrangements for the delivery of
                                                                                                               Issued Capital:
service are progressing well.                                                                   3,549 million ordinary shares

Based on current discussions and arrangements; and subject to                                          Major Shareholders:
                                                                                            The Waterberg Coal Company Ltd
confirmation of funding arrangements, project start-up and pre-production                       Sekoko Resources (Pty) Ltd
works is expected to commence in January 2014; and coal production (of                                     Linc Energy Ltd
product) is expected to commence in the 2nd half of 2015.                                             BBY Nominees Pty Ltd

                                                                                                     Directors and Officers
Drilling
                                                                                                   Non Executive Directors:
All Phase 2 drilling to delineate major faults on the Smitspan Project area,                         Tim Tebeila (Chairman)
                                                                                                             Dr Pius Kasolo
and extend the resources on Smitspan and Massenberg, was completed                                            Ben Mphahlele
during the June quarter. Drill samples have been submitted to the                                            Brian McMaster
laboratory; and sample results are expected at the end of July 2013.                                             David Knox

                                                                                                                  Officers:
A further 55 boreholes are planned in order to upgrade the geological                   Mr Stephen Miller CEO and Executive
confidence from inferred to indicated levels on the remaining farms. 30 of                                         Director
the holes are scheduled to be drilled on Hooikraal, and the remainder on                              Ms Amanda Matthee CFO
                                                                                     Mr David McEntaggart Company Secretary
Massenberg, Swanepoelpan and Vetleegte. The drill rigs are already on
site at Massenberg.
                                                                                                                    Contact:
                                                                                       Level1, 33 Richardson St, West Perth,
                                                                                                      Western Australia 6005
                                                                                                     Tel: +61 (08) 9200 4465
                                                                                                       Fax:+61(08) 9200 4469
                                                                                             Web: www.firestoneenergy.com.au
Interim Resource Statement

During the June quarter SRK released an Interim Resource Statement1, covering the Smitspan
and Massenberg properties only. The updated Resource Statements2 reflect a resource
tonnage of 1,090.88 Million tonnes (“Mt”) at Measured Status, 69.04 Mt at Indicated Status,
and 23.27 Mt at inferred Status for Smitspan and Massenberg. The balance of the resources
on the farms held under Mining Rights and Prospecting Rights are not included in this estimate
and reflect further potential.

Geological Model

A new contract has been negotiated with Sable© to maintain and update the Sekoko
Geological Database. The updated database will be passed onto Gemecs Pty Limited, who
will create a new Geological Model incorporating the data, to be used for both a Resource
update and further mine planning and value engineering pursuant to the DFS.

Surface rights

During the quarter, negotiations for the purchase of surface rights, commenced with the
surface rights holders. It is expected that agreements with current owners will be finalised
during the next quarter.

Corporate Activities

There were several board changes during the quarter with the resignation of Mr David Perkins,
deputy chairman, Mr Oren Zohar, Mr Jack James and Mr Kobus Terblanche. Mr Brian
McMaster, Mr Stephen Miller and Mr David Knox were appointed to the board. Additionally, Mr
Stephen Miller was appointed CEO of the Company to replace Mr David Knox.

The Company continued discussions during the quarter with interested parties regarding the
future funding for Firestone. Discussions are on-going. The Company received notification
during the quarter that the Waterberg Coal Company’s off-market takeover bid for all the
ordinary shares in Firestone had been extended to 30 July 2013.

Yours sincerely




Stephen Miller
Chief Executive Officer

www.firestoneenergy.com.au


Footnote:

1
 Competent Persons Statement: Information in this announcement that relates to exploration results, coal resources or reserves on the properties
Smitspan 306LQ and Massenberg 305LQ is based on information compiled by Mr Sello Nzama. Mr Nzama who is employed by SRK Consulting
(Pty) Ltd is a member of the South African Council for Natural Scientific Professions. . Mr Nzama has sufficient experience which is relevant to the
style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as
defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (The JORC
Code). Mr Nzama consents to the inclusion in the announcement of the matters based on his information in the form and context in which it appears.

2
    This resource upgrade and attaching report was advised to the market and lodged with ASX on 28th May 2013.

30 July 2013
Johannesburg

Sponsor
River Group


                                                                                                                                           

Date: 30/07/2013 08:45:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story