Wrap Text
Production Update
ZCI Limited
(Bermudian registration number 661:1969
(South African registration number 1970/000023/10)
JSE share code: ZCI ISIN: BMG9887P1068
Euronext share code: BMG9887P1068
("ZCI")
Production Update
Production report for the third quarter of fiscal 2013
ZCI is pleased to report that its principal subsidiary African Copper plc (“the Company” or “African Copper””)
produced 2577Mt of copper in concentrate during the third quarter of the 2013 fiscal year. This production
was 47% higher than the same period in the previous year.
Mr Tom Kamwendo, the ZCI Group CEO expressed satisfaction with the continued improvements being
made at African Copper.
African Copper issued the following statement:
“The Company announces production figures for the third quarter of fiscal 2013 from its 100% owned
operating mines in Botswana. For the third quarter of fiscal 2013, the Company produced 2,577 Mt of copper
in concentrate.
Third Quarter Production Highlights
* Ore processed of 215,383 Mt; 28% increase over prior year's Q3
* Copper recovery of 69.8%; 20% increase over prior year's Q3
* Copper produced in concentrate of 2,577 Mt; 47% increase over prior year's Q3
Mr Jordan Soko, Acting Chief Executive of African Copper, said, “The Company is on track to achieve
record copper production in fiscal 2013. Our operations teams continue to successfully execute our mine
plans and have done a great job to increase throughput, efficiencies and plant utilization. The focus now is to
exceed these levels as we move into increasing proportions of sulphide ore at Thakadu and to prove up
additional resources from our strong portfolio of appraisal and exploration prospects.”
All of the ore processed at the Mowana facilities during the last three quarters was sourced from the higher
grade Thakadu Mine. Ore processed in the third quarter and concentrate produced were slightly lower
than the second quarter as a result of mining a lower grade split orebody from the western end of the
Thakadu pit in the third quarter. Copper recovery at the plant has continued to benefit from the
increasing proportion of sulphide ore. In the three months reported below, the proportion of sulphide
ore processed increased from 43% of the total in October, to 70% in November and 86% in
December. Trucking operations from Thakadu to the Mowana Mine processing facilities, a distance of 70km,
ran to plan throughout the quarter.
Production levels for the three months ended 31 December 2012 are set out below:
Description Octob Novemb Decemb Total Total Total
er er er 2012 Q3 Q2 Q1
2012 2012 2012/ 2012/ 2012/
2013 2013 2013
Ore processed (Mt) 76,544 58,983 79,855 215,38 250,005
3 171,908
Cu grade (%) 2.18 1.78 1.22 1.71 1.82 1.91
Recovery (%) 54.9 69.6 95.5 69.8 63.4 49
Concentrate produced (Mt) 4,322 3,287 4,220 11,829 13,810 6,888
Copper produced in concentrate 916 730 931 2,577 2,882 1,609
(Mt)
Totals for the Third Quarter Ended 31 December 2012 in comparison with prior periods are presented
as follows:
Description 3Q 2012/13 3Q 2011/12 FY 2011/12
Ore processed (Mt) 637,296 561,256 738,921
Cu grade (%) 1.81 1.89 1.93
Recovery (%) 61.3 49.3 48.4
Concentrate produced (Mt) 32,526 23,210 31,027
Copper produced in concentrate (Mt) 7,067 5,234 6,910
* Production during the first quarter ended 30 June 2012 was adversely affected by the failure of the
mill pinion shaft which caused production to be shut down for 15 days.
As previously announced, the introduction of an increasing proportion of sulphide ore has brought
flotation stability and improved recovery, evidenced by the December 2012 flotation recovery of
95.5%, and has also resulted in the reduction of costs due to curtailed usage of high cost flotation
reagents. Improved plant efficiency continued through the quarter, principally from the Larox filter
plant which increased filtration capacity and reduced moisture content.
The main mining contract at Thakadu mine, which is due to expire on 31 March 2013, is currently
under review and being renegotiated. Pursuant to this, certain mining equipment has been demobilised.
In the interim, mining operations continue with both the existing main contractor and a
second Thakadu mining contractor who has been on-site since mining commenced at Thakadu. As a
short term measure, management is also looking at equipment hire or short term contracts to augment
mining volumes. As a result of the negotiations around the mining contract, the Company is expecting
that less volume will be mined from Thakadu until additional equipment is delivered and the mining
contract review finalised. The reduction in mining volumes is likely to result in lower mining costs.
Any impact on ore delivery during a possible transition phase will be mitigated by the use of oxide ore
stockpiles situated at Thakadu and Mowana Mines but the use of reagents to treat the oxide ore will
increase treatment costs, reducing the benefit of the lower mining costs.
The technical information in this announcement has been reviewed and approved by David De’Ath, BSc
(Hons), MSc, GDE-Mining, MIMM and MAusIMM, the Company’s Manager, Geology, of the Mowana
Mine for the purposes of the current Guidance Note for Mining, Oil and Gas Companies issued by the
London Stock Exchange in June 2009”
Bermuda
24 January 2013
Sponsor: Bridge Capital Advisors (Proprietary) Limited
Date: 24/01/2013 08:00:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.