To view the PDF file, sign up for a MySharenet subscription.

CRD - Central Rand Gold Limited - Operational update

Release Date: 10/10/2011 08:00
Code(s): CRD
Wrap Text

CRD - Central Rand Gold Limited - Operational update Central Rand Gold Limited (Incorporated as a company with limited liability under the laws of Guernsey, Company Number 45108) (Incorporated as an external company with limited liability under the laws of South Africa, Registration number 2007/0192231/10) ISIN: GG00B24HM601 LSE share code: CRND JSE share code: CRD ("Central Rand Gold" or the "Company") OPERATIONAL UPDATE Introduction On 29 March 2011, Central Rand Gold identified three critical challenges facing the Company, which included the rising water table in the Central Basin, the appearance of double voids (termed Composite Double Voids) and the challenges of dilution through its proposed long hole stoping methodology. The issue around Composite Double Voids was comprehensively addressed in an announcement issued by the Company on 15 September 2011. Not only was the impact of the Composite Double Voids demonstrated to be minimal, the impacted areas were also shown to be relatively predictable. Accordingly, the Company provides the following update with regards to the remaining challenges, namely the rising water table and the dilution challenges resulting from the proposed long hole stoping methodology. 1. Rising water table The Company continues to engage with the South African Government ("Government") around the issue of the rising water table in the Central Basin. As reported on 27 July 2011, the Ritz submersible pumps ("pumps") were successfully tested in Germany in the presence of Trans Caledon Tunnel Authority ("TCTA") (appointed project managers by the Department of Water Affairs). The pumps will remain in Germany until such time as clarity with regards to Company`s Mining Right has been obtained. On 7 September 2011, having completed its due diligence on developing a solution for the Central Basin, TCTA presented a proposed solution to the Government`s Portfolio Committee on Water and Environmental Affairs. The proposed solution includes: * A commitment to protect the Environmental Critical Level ("ECL") in the Central Basin at 186 metres below surface ("mbs"). This represents an approximate level of 225mbs in Central Rand Gold`s mining area. * The construction of a New High Density Sludge Plant with a plant capacity of 84 million litres per day next to the South West Vertical Shaft. * Utilisation of Central Rand Gold`s pumps to de-water and maintain the Central Basin. * The transfer of treated water via pipeline to Elsburg Spruit. * Co-disposal with Durban DRD Gold of sludge via dual lines. * The sale of grey water, where possible. It is anticipated that construction will commence in January 2012, with commissioning occurring in August 2012. TCTA will now approach the National Treasury Department for additional funding as the R225 million (US$27 million) initially allocated to resolve the entire Acid Mine Drainage problem in the Witwatersrand area has proven to be insufficient; a revised budget of R924 million (US$114 million) has been proposed. 2. Feasibility of Conventional Hand Held Stoping One of the main contributing factors leading to the decision to abandon the mechanised longhole stoping previously undertaken at the mine, was the very significant amount of zero grade material arising from the immediate hanging wall of the Main Reef Leader, which was significantly diluting the ore being processed. Joints and bedding planes within the rocks above the reef have, over time, become separated and, to a large extent, delaminated. The explosive concussion associated with the original longhole stoping, which necessitated the drilling of blastholes up to 15 metres in length, often exacerbated the delamination, causing slabs consisting of barren hanging wall waste in excess of two metres to dilute the reef ore. Without the means to efficiently remove this barren material from the broken ore, it became rapidly apparent that the method of longhole extraction of reef ore is not economically viable. A more conservative, hand-held conventional technique was therefore proposed as a potential solution to address this dilution challenge. The Company identified three key points against which this study should be evaluated: 1. Can the reef be safely stoped using the proposed conventional means' 2. Can dilution from the hanging wall be eliminated or managed' 3. Is the methodology commercially viable' Safety in the conventional stoping trial In June 2011, Central Rand Gold initiated a trial phase of conventional hand-held stoping in selected pre- developed areas. To this end, the Company engaged the services of specialist conventional South African mining entity, Sekgwa Mining Services (Proprietary) Limited ("Sekgwa Mining"), for a three month period. Sekgwa Mining has both the relevant experience and necessary competence in scattered conventional mining. During the three months of conventional trials, the Company has not had a single accident resulting from an uncontrolled fall of ground. This has been achieved through a support structure of 1.8 metre long resin bolts in on reef development, 150 millimetre to 200 millimetre elongates installed in a tight one metre by one metre grid within stope panels and a line of three stick clusters on a one metre spacing every 10 metres on strike. In addition, three stick clusters are installed at one metre spacing along gullies and raises. The Company is satisfied that conventional stoping techniques can be undertaken safely. Dilution Management in the conventional stoping trial In table 1 a comparison is made of the impact of hanging wall dilution arising from the three mining methods trialled to date, namely "Reef Drive Longhole Stoping", "Footwall Drive Longhole Stoping" and "Conventional Hand Held Stoping". Table 1: Impact of dilution with different mining methods. Working Method Insitu Stopping/Actual Belt/Stockp Observed Insitu to Place Main Cut Values ile Values Total Belt Reef Dilution Grade
Values Reduction 1534RD Reef Drive 5.03g/t 1.8g/t / 325cm 1.72g/t 207% 66% Longhole / 106cm 15719_13 FW Drive 4.51g/t 2.43g/t / 293cm 1.71g/t 95% 62% Longhole / 150cm 15113_10 Conventional 4.44g/t 4.13g/t / 206cm 3.41g/t 29% 23% Hand Held / 160cm The Reef Drive Longhole stoping method was successful in the initial 2009 trial area and realised only a modest amount of hanging wall dilution. However, when full production was attempted it was observed that there was in excess of 200% dilution by zero grade material, due to the excessive hanging wall failure. Whilst the Reef Drive method did allow for limited underground and surface waste sorting, the reduction in grade from insitu to stockpile was in excess of 60% which was clearly not acceptable. The replacement mechanised mining technique, involving the development of the Footwall drives and cross-cutting to the reef at regular intervals, was certainly effective in reducing high development costs. Unfortunately, the excessive blast concussion from longhole stoping recreated a similar pattern of hanging wall dilution to that previously observed. The mining area where this methodology was initially employed showed less dilutive hanging wall (due presumably to localised lower incidence of jointing). Unfortunately, the ability to conduct waste sorting underground and on surface was hampered due to the constricted nature of the draw-point geometry, which required regular re-blasting of hanging wall slabs, which frequently choked the draw-points. As a result of this inability to remove dilution, the actual reduction in grade from insitu to stockpile was also shown to be in excess of 60%. Consequently, this methodology is not economically viable. The introduction of hand-held conventional mining has been shown to improve the situation significantly. This method uses much shorter blastholes (around one metre in length) which consequently carry a much reduced concussive charge. Even if there is hanging wall failure due to delamination, it is limited to the one metre blasted panel advance and can therefore be easily sorted and contained prior to tramming. Hanging wall support between blasts allows for the continuous assessment of hanging wall dilution and remedial action such as barring or implementing additional support. As a result, an improvement in overall grade reduction of only 23% from insitu to stockpile was measured. In the absence of actual ore processing, this figure can be considered to approximate to a calculated Mine Call Factor of 77%. It is also important to highlight the fact that of the three methods employed to date, conventional hand-held stoping is the most amenable to selective mining which allows for a high degree of flexibility and optimisation. Commercial viability of conventional stoping In addition to contracting Sekgwa Mining to test the practicalities of conventional hand held mining, a specialist mining engineering consultancy, MineQuest Consult (Proprietary) Limited ("MineQuest"), was engaged to develop a Life of Mine ("LOM") feasibility and economic study on the western portion of the CMR property to a depth of approximately 450 mbs. MineQuest`s initial study was based on a hybrid mining style combining conventional hand-held stoping and mechanised development and tramming. The initial study concluded that a 30 000 to 40 000 ounce per annum operation is viable, giving a LOM of approximately 12 years. This initial study and schedule estimates a project cash operating cost (mine site cash expenses which includes direct mining, ore processing and on-site general and administrative costs) of R427 per ton (US$779/oz) and total production cost (cash operating costs plus capital expenditure which includes plant, equipment and development costs) of R586 per ton (US$1,068/oz). If the initial mine plan was implemented, approximately 700 new jobs could be created during the course of the CMR West LOM. The full report was supplied to the Department of Mineral Resources in support of a rescaling of the Company`s original mine work programme. A further report was subsequently compiled by MineQuest to optimise the CMR West mining plan maximising extraction economics. The optimised 50 000 ounce per annum plan suggests a cash operating cost of R342 per ton (US$623/oz) and total production cost of R492 per ton (US$899/oz) and a positive LOM net operating cashflow of R1.5 billion (US$187 million) at an average gold price of $1,613 per ounce. The complete MineQuest scoping study is available on the Company`s website: www.centralrandgold.com Way Forward The Company believes that the new conventional mining method is scalable and repeatable across its tenement area, which would enable the creation of the original `string of pearls` concept. There remains sufficient mineral inventory on both CMR East and Crown West to establish two similar sized operations that could be brought on line in parallel with the proposed CMR West operation and generate a significant number of additional jobs over and above the 700 required under the mine plan for CMR West. In light of the Department of Mineral Resources` cancellation of the Company`s Mining Right, the implementation of the above plan can only be considered once its has successfully appealed the Minster`s decision. The Company, dependant on court availability, hopes that its appeal will be heard by the Pretoria High Court by end October 2011. For further information, please contact: Central Rand Gold +27 (0) 11 674 2304 Johan du Toit / Patrick Malaza Evolution Securities Limited +44 (0) 20 7071 4300 Chris Sim / Neil Elliot Merchantec Capital +27 (0) 11 325 6363 Roger Pitt / Monique Martinez Buchanan +44 (0) 20 7466 5000 Bobby Morse / James Strong Jenni Newman Public Relations (Proprietary) Limited +27 (0) 11 506 7351 Jenni Newman 10 October 2011 Johannesburg JSE Sponsor Merchantec Capital Date: 10/10/2011 08:00:02 Supplied by www.sharenet.co.za Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on, information disseminated through SENS.

Share This Story